215 results found for 'Neart na Gaoithe'

215 results found for 'Neart na Gaoithe'
Order results by

A list of search results

  • 16 May 2019
    Wind Farm Update

    The construction of the 450MW Neart na Gaoithe wind farm offshore Scotland is planned to begin later this year, EDF Renewables in the UK said. The company has opened an extension to its existing office in Edinburgh to accommodate 60 new jobs created on the Neart na Gaoithe offshore wind farm project. Derek Mackay MSP, […]

  • 21 January 2020
    Vessels

    Neart na Gaoithe Offshore Wind Ltd. has shared a video showing the WaveWalker 1 walking jack-up barge in action at the project. WaveWalker 1 has been at the Thorntonloch Beach in East Lothian, Scotland, over the last week, exploring the best options for installing the wind farm’s offshore export cable. The nearshore geotechnical survey work […]

  • 7 April 2020
    Business & Finance

    EUR 6.1 billion was invested in four European offshore wind projects with a combined capacity of around 1.4 GW in 2019, marking the lowest amount invested and the capacity financed in a year since 2012, according to a report by WindEurope. The four wind farms that reached the Final Investment Decision (FID) in 2019 are […]

  • 8 March 2021
    Grid Connection, Wind Farm Update

    Preparation works for the export cable installation for the Neart na Gaoithe offshore wind project are expected to commence in mid-March. The area where the activities will take place is the nearshore extent of the wind farm’s export cable corridor. Two jack-up vessels, Capall Mara and C57 Red Squirrel, will carry out a small amount […]

  • 21 March 2017
    Authorities, Business & Finance, Wind Farm Update

    An arbitration tribunal has ruled in favour of Mainstream Renewable Power in relation to the dispute over the Low Carbon Contracts Company (LCCC) terminating the Contract for Difference (CfD) for Mainstream’s 450MW Neart na Gaoithe wind farm off Scotland.

  • 19 May 2021
    Grid Connection, Wind Farm Update

    Offshore substation (OSS) topsides for the French Saint-Brieuc and Scottish Neart na Gaoithe offshore wind farms have been moved out of Engie Solutions and HSM Offshore’s factories in Belgium and the Netherlands, respectively. Ailes Marines selected a joint venture between Engie Solutions and Iemants (a subsidiary of Smulders) to manufacture the offshore substation for the […]

  • 4 May 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    EDF Group has bought the Neart na Gaoithe offshore wind project from Mainstream Renewable Power, following a competitive bidding process, the two companies informed on 3 May. 

  • 28 January 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Tekmar Energy has secured a contract to provide its Generation 10 TekTube cable protection system (CPS) for the Neart na Gaoithe (NnG) offshore wind farm in the UK. Under the contract secured with Prysmian, Tekmar’s CPS will protect the wind farm’s subsea export cables. The systems will be delivered this year from the company’s manufacturing […]

  • 16 December 2021
    Wind Farm Update

    Preparations for the installation of inter-array cables at the Neart na Gaoithe offshore wind farm site, located some 15 kilometers off the Fife coast in Scotland, have been completed while several other offshore activities are ongoing, including the pile installation for the jacket foundations being performed by the Saipem 3000 crane vessel. Helix Robotics Solutions, […]

  • 25 December 2018
    Authorities, Contracts & Tenders, Wind Farm Update

    The 448MW Neart Na Gaoithe offshore wind project has passed its 12-month Contracts for Difference (CfD) milestone, Low Carbon Contracts Company (LCCC) said.

  • 11 May 2023
    Grid Connection, Wind Farm Update

    Neart na Gaoithe Offshore Wind Farm Limited (NnGOWL) has completed the cable layout for the first campaign of six inter-array cables and one interconnector between the two offshore substations (OSS) within the Neart na Gaoithe offshore wind farm site in Scotland. The works began on Wednesday, 12 April, and were completed on Sunday, 30 April. […]

  • 5 December 2019
    Business & Finance

    K2 Management has advised the Irish electricity company ESB in acquiring a 50% stake in the Neart na Gaoithe (NnG) offshore wind project in Scotland. K2 Management undertook a full scale technical due diligence of the project, including analysis of the project’s design, construction contracts and methodology, as well as energy yield and cost assumptions […]

  • 26 February 2015
    Authorities, Business & Finance, Wind Farm Update

    The UK Department of Energy and Climate Change (DECC) published the outcome of the first allocation round of Contracts for Difference (CfD) this morning, at the same time the National Gid notified applicants of the outcome. Among 27 awarded projects, two offshore wind farms have been selected as winner projects of this CfD round: phase one of […]

  • 20 July 2023
    Vessels, Wind Farm Update

    The jack-up vessel Blue Tern has arrived at the offshore construction site of the Neart na Gaoithe offshore wind farm in Scotland as the installation of the project’s wind turbines has now begun. Earlier this month, the crane vessel Thialf completed the second phase of the installation of wind turbine jacket foundations. The work on […]

  • 3 September 2017

    Nexans Boosts Cable Laying Fleet with High Capacity Newbuild Nexans has announced the start of construction of a new cable-laying vessel for submarine high voltage (HV) cable systems installation. Analysis: Neart Na Gaoithe Offshore Wind Farm to Have GBP 827 Million Impact on Scottish GDP The 450MW Neart Na Gaoithe offshore wind project is estimated […]

  • 23 August 2015

    Gemini Offshore Substations Sail Out The FICG consortium of Cofely Fabricom, Iemants and CG, which was selected by Van Oord for the Gemini offshore wind project in the Netherlands, has finalized the construction of the two HV offshore substations and has shipped them out to their final destination. Bladt Completes First Frame for Iberdrola’s OWF […]

  • 17 October 2013
    Grid Connection

    Survey work has commenced on the new Neart na Gaoithe offshore wind farm. Mainstream Renewable Power will survey the 30km-long cable route with the survey vessel MV Coastal Discovery. The underwater cable will connect to the onshore National Grid connection at Crystal Rig in the Lammermuirs. This survey is expected to be completed in the […]

  • 27 February 2015

    Scottish Enterprise has welcomed yesterday’s announcement about Mainstream’s Neart na Gaoithe (NnG) being awarded a contract for difference by the UK Department of energy and Climate Change (DECC). Seonaid Vass, director of renewables & low carbon technologies at Scottish Enterprise, said: “Today’s announcement reinforces Scotland’s growing position as a global centre for offshore wind and is a real sign […]

  • 7 September 2020
    Operations & Maintenance, Wind Farm Update

    Scottish Borders Council’s (SBC) planning committee has approved plans for the operations and maintenance (O&M) building in Eyemouth for the Neart na Gaoithe (NnG) offshore wind farm. The planning permission is for a new, three-story 1,040m2 main building and a two-story 538m2 storage warehouse. The O&M building, designed by Corstorphine + Wright Architects, will house […]

  • 16 May 2017
    Wind Farm Update

    Following the ruling of the Inner House of the Court of Session, Mainstream Renewable Power plans to speed up the development of its Neart Na Gaoithe offshore wind farm to bring the project to the construction phase, planned to start in 2019.

  • 9 August 2016
    Authorities, Environment, Wind Farm Update

    The Scottish Ministers have lodged an appeal against the Scottish Court of Session’s decision in favour of the petition filed by the Royal Society for the Protection of Birds (RSPB) to review the consent by the Scottish Ministers for four offshore wind farms in the Firths of Forth and Tay, Mainstream Renewable Power, the developer […]

  • 3 July 2023
    Wind Farm Update

    The installation of wind turbines that will make up the Neart na Gaoithe offshore wind farm is scheduled to begin in the coming days, on or after 7 July. The first batches of turbine components have already been delivered to the Port of Dundee and the installation vessel Blue Tern, currently in the Port of […]

  • 19 July 2017
    Wind Farm Update

    The Inner House of the Scottish Court of Session has refused RSPB’s application to appeal the Court’s earlier decision to allow further development of four offshore wind projects in the Firth of Forth and Firth of Tay.  

  • 25 April 2014
    R&D, Technology, Wind Farm Update

    Mainstream Renewable Power have kicked off Phase 2 of their floating LiDAR campaign by deploying a floating LiDAR on its 450MW Neart na Gaoithe offshore wind farm. Technology providers FLiDAR NV (a joint venture between DEME and 3E), deployed the device almost 21km off the Fife coast on April 20th. The technology is designed to […]

  • 14 January 2014
    R&D, Technology

    Mainstream Renewable Power has deployed the North Sea’s first commercial floating LiDAR wind measurement device, designed to capture wind data in the harshest conditions, to support its proposed 450MW Neart Na Gaoithe offshore wind farm. A deal has been signed with technology providers FLiDAR NV, for the launch of the floating LiDAR to the site […]

  • 14 February 2023

    The commissioning work on the second offshore substation (OSS) of the Scottish offshore wind farm Neart na Gaoithe will start on 15 February. The first of Neart na Gaoithe’s two offshore substations, South OSS, was installed in June 2022 by Heerema Marine Contractors, using the world’s largest crane vessel Sleipnir, followed by the installation of the jacket […]