Search results for: seagreen 1

189 results

A list of search results

  • 12 March 2024
    Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    The first geotechnical seabed surveys for TotalEnergies and SSE Renewables’ 500 MW Seagreen 1A offshore wind farm in Scotland have been completed. Phase two of the geotechnical works is expected to commence later this year and should take around two weeks to complete. Seagreen 1A lies adjacent to the existing 1,075 MW Seagreen project and […]

  • 27 March 2024
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain

    UK-based Ventus Energy has been awarded a contract by SSE Renewables to provide maintenance work on transmission assets for the Seagreen offshore wind farm in Scotland. Throughout the duration of the contract, the company will operate across primary and secondary equipment at the wind farm’s offshore and onshore substations. In addition to substation asset maintenance, […]

  • 17 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 114 Vestas V164-10.0 MW wind turbines at the Seagreen offshore wind farm in Scotland are fully operational and are generating clean, renewable energy to Britain’s power grid, according to SSE Renewables and TotalEnergies, the owners of the project. Located 27 kilometres off the Angus coast in the North Sea’s Firth of Forth, Seagreen is […]

  • 22 December 2023
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    TotalEnergies has decided to sell a 25.5 per cent equity stake in Seagreen, Scotland’s largest offshore wind farm, in a GBP 522 million (about EUR 602 million) deal with Thailand’s national oil and gas company PTTEP. Following this farm down, TotalEnergies retains 25.5 per cent of Seagreen, alongside PTTEP (25.5 per cent), and SSE Renewables […]

  • 11 July 2023
    Wind Farm Update

    Seaway7 has completed the full engineering, procurement, construction, and installation (EPCI) cables scope on the Seagreen wind farm offshore Scotland, a joint venture project between SSE Renewables and TotalEnergies. The inter-array cable team completed the termination and testing last weekend and the trenching was completed yesterday, said Seaway7. This follows less than six weeks after […]

  • 1 June 2023
    Wind Farm Update

    100 out of 114 Vestas V164-10 MW wind turbines have been installed at what will be Scotland’s largest offshore wind farm – Seagreen – off the coast of Angus. According to AIS, Cadeler’s wind farm installation vessel Wind Orca is at the offshore construction site 27 kilometres from the coast of Angus where it will […]

  • 22 June 2023
    Wind Farm Update

    The final turbine has been installed at Scotland’s largest offshore wind farm, Seagreen, off the coast of Angus. The work was carried out by Cadeler’s wind farm installation vessel Wind Orca, which replaced its sister vessel Wind Osprey in April 2022. Many of the wind turbines are installed in a water depth of more than […]

  • 18 March 2021
    Authorities, Wind Farm Update

    Seagreen 1A Limited has submitted applications to Scottish authorities for onshore and offshore works related to the Seagreen 1A offshore wind project. The applications were sent to East Lothian Council for onshore works and Marine Scotland for offshore works. The applications for Seagreen 1A have been lodged following online consultation, in line with Scottish Government […]

  • 21 June 2023
    Business development, Collaboration, Outlook & Strategy, Research & Development

    Portuguese energy company Galp has decided to join forces with French energy major TotalEnergies to explore the potential development of wind projects offshore Portugal. The partnership combines Galp’s knowledge of the Portuguese market with TotalEnergies’ expertise in large-scale offshore wind projects, according to the press release. The partners said that they intend to contribute with […]

  • 19 August 2021
    Authorities, Grid Connection, Wind Farm Update

    East Lothian Council planning officers have recommended for approval the Seagreen 1A onshore proposals at Cockenzie. The applications were submitted earlier this year to East Lothian Council for onshore works and Marine Scotland for offshore works. No local representations had been received against the plans, the project’s developer said. The project infrastructure is located in […]

  • 12 October 2022
    Wind Farm Update

    Cadeler’s wind farm installation vessel Wind Orca has hit the halfway mark on the Seagreen offshore wind farm in Scotland, where 57 out of the 114 Vestas 10 MW wind turbines have now been installed. The first wind turbine was installed in early December 2021 by the Wind Osprey vessel, which was replaced by its sister vessel […]

  • 13 December 2021
    Authorities, Wind Farm Update

    Scottish Government Ministers have approved the Marine Licence application for the 36-turbine Seagreen 1A offshore wind proposal being brought forward by SSE Renewables and TotalEnergies. The Marine Licence covers the offshore elements of the project, including an export cable approximately 110 kilometres in length, to connect the project to the grid at Cockenzie in East […]

  • 7 June 2022
    Contracts & Tenders, Wind Farm Update

    Seagreen 1 Limited has selected Seaway 7, the Renewables & Heavy Lifting business unit of Subsea 7, as a preferred supplier for the Seagreen 1A wind project offshore Scotland, with the final contract expected to be valued between USD 500 million and USD 750 million. Seagreen 1A lies adjacent to the existing Seagreen project that […]

  • 14 January 2021
    Business & Finance, Wind Farm Update

    Seagreen 1A Ltd. is seeking feedback on the onshore and offshore grid connection proposals related to the remaining 36 turbines to be installed at the Seagreen offshore wind project. The company is undertaking pre-application consultation ahead of potentially submitting applications to East Lothian Council and Marine Scotland for the onshore and offshore elements to allow […]

  • 16 June 2020
    Contracts & Tenders, Wind Farm Update

    Seagreen Wind Energy has finalised the wind turbine supply contract with MHI Vestas Offshore Wind, following the preferred supplier agreement signed at the beginning of June. Under the contract, MHI Vestas is in charge of manufacturing and installing 114 of its V164-10 MW turbines for the Seagreen 1 offshore wind project, which will be built […]

  • 4 June 2020
    Contracts & Tenders

    SSE Renewables has awarded Subsea 7 with a contract for engineering, procurement, construction and installation (EPCI) of the foundations and inter-array cables for the Seagreen 1 offshore wind farm. In a press release from 3 June, Subsea 7 did not disclose the contract value, but it did classify it as “major”, noting that it defines […]

  • 8 June 2020
    Contracts & Tenders

    Subsea 7’s renewables business unit Seaway 7 has chosen Lamprell for the delivery of 30 foundations for the Seagreen 1 offshore wind farm. Under the contract, yet to be finalised and to be executed on a lump-sum basis, the UAE-based company will manufacture jackets, transition pieces and suction caissons. Lamprell will deliver the jackets to […]

  • 7 February 2022
    Wind Farm Update

    Lamprell is set to deliver the final ten jacket foundations for the Seagreen 1 offshore wind farm in the first quarter of this year, the Dubai-based company said on 7 February. Under a contract signed in 2020 with Subsea 7’s renewables business unit Seaway 7, Lamprell will deliver a total of 30 jackets for the […]

  • 29 June 2020
    Contracts & Tenders

    Jutal Offshore Oil Services has been awarded a contract for an offshore wind farm in Europe, according to a recent press release from the company. The China-based company informed its wholly owned subsidiary Jutal Offshore Oil Services (Zhuhai) won several new contracts, including one for the construction and delivery of “50 sets of offshore wind […]

  • 24 June 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Linxon, a joint venture between ABB and SNC-Lavalin, has won a contract to support Petrofac in delivering the substations for the Seagreen offshore wind project in Scotland. Linxon is supporting Petrofac, the EPCI contractor for the wind farm’s substations, to deliver the turnkey onshore substation, and supply, install and commission the HVAC equipment for the […]

  • 18 September 2020
    Contracts & Tenders, Wind Farm Update

    Seaway 7 has selected COOEC-Fluor Heavy Industries to manufacture and deliver jackets and suction caissons for the Seagreen 1 offshore wind project. COOEC-Fluor’s scope of work for Seagreen 1 includes the fabrication and load-out of the suction caisson jackets. The manufacturing work will be carried out at COOEC-Fluor’s fabrication yard in Zhuhai, China. COOEC-Fluor is […]

  • 14 July 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Linxon has awarded Kirby Group Engineering a subcontract for the onshore substation mechanical and electrical installation and building services works as part of the Seagreen Offshore Wind Farm Substation package. The works include the installation of the onshore primary and secondary HV power equipment including the super-grid transformers, switchgear, dynamic reactive compensation, shunt reactors, harmonic […]

  • 19 January 2021
    Wind Farm Update

    MMT has commenced the geophysical survey of the export cable route at the Seagreen 1A offshore wind project in Scotland. The team began the operations earlier this week onboard offshore survey vessel Franklin and will later be adjoined by a shallow draft vessel to perform the nearshore and intertidal parts of the survey. The export […]

  • 22 December 2022
    Wind Farm Update

    The final jacket foundation for the Seagreen 1 offshore wind farm has arrived in Port of Nigg, from where the foundations are being installed by Seaway 7. It took a total of 23 shipments to deliver the 114 jackets to the Port of Nigg, which was achieved through collaboration between Seaway7, SSE Renewables, COSCO, Global […]

  • 4 June 2020
    Business & Finance, Wind Farm Update

    SSE Renewables has taken a final investment decision to proceed with the Seagreen 1 offshore wind project which will now be taken forward together with the French energy major Total. Total and SSE Renewables have now entered into an agreement through which Total will take a 51 per cent stake in the GBP 3 billion […]

  • 20 April 2021
    Contracts & Tenders, Wind Farm Update

    SSE Renewables, together with Vestas, has selected the SEANEX inner cone system from Pfisterer for the connections on more than 100 wind turbines at the Seagreen 1 project, located 27 kilometres off Scotland’s Angus coastline. According to the supplier, the system offers significant benefits during installation and continuous operation of the 66 kV inter-array cabling. […]