75 results found for 'kaskasi'

75 results found for 'kaskasi'
Order results by

A list of search results

  • 25 September 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    RWE has awarded Semco Maritime with a framework agreement for the maintenance of German offshore substations. The agreement, commencing in September 2025, will continue through 2027 and includes a two-year extension option. Semco Maritime’s scope of work includes scheduled and unscheduled maintenance above water and troubleshooting services of the auxiliary equipment at RWE’s offshore substations […]

  • 30 November 2020
    R&D, Technology, Wind Farm Update

    German energy company RWE will introduce the so-called ‘collared monopiles’ on the Kaskasi offshore wind farm in the German North Sea. Designed based on an RWE patent, the collars will be installed around three monopile foundations at seabed level. According to RWE, the new foundation technology will provide additional support for lateral loading, increase the […]

  • 27 May 2022
    Environment, R&D, Technology, Wind Farm Update

    Siemens Gamesa is currently producing the first recyclable blades to be installed on an offshore wind farm at its factory in Hull, the UK. The wind turbine manufacturer described the RecycleBlade as the world’s first wind turbine blade ready for commercial use offshore that can be recycled at the end of its lifecycle. The RecyclableBlade […]

  • 27 April 2018
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Germany’s Bundesnetzagentur has awarded innogy SE with the rights to build and operate the 325MW Kaskasi offshore wind farm in the German North Sea.

  • 22 November 2022
    Wind Farm Update

    The last of the total of 38 wind turbines at RWE’s Kaskasi offshore wind farm in Germany has been installed and more than two thirds of the turbines are now feeding electricity into the grid. Kaskasi is expected to be operational by the end of the year, as of when the 342 MW offshore wind […]

  • 28 March 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    The 1,400-tonne offshore substation topside has been installed on its monopile foundation at the 342 MW Kaskasi offshore wind farm in the German North Sea, RWE, the owner and developer of the project, said. The topside was installed by the heavy lift, DP 2 installation vessel Gulliver, operated by DEME’s subsidiary Scaldis Salvage & Marine […]

  • 9 February 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Tekmar Energy Limited has secured a contract award to supply its TekLink® Cable Protection Systems (CPS) for the Kaskasi offshore wind farm in Germany. Owned and developed by RWE, the Kaskasi offshore wind farm is a 342 MW wind project located in the German North Sea. Construction work will start in the third quarter of […]

  • 15 June 2021
    Grid Connection, Wind Farm Update

    A 1,400-ton Kaskasi offshore substation topside has arrived from Poland to Bladt Industry’s site in Aalborg, Denmark for further outfitting with the electrical equipment. Energomontaż-Północ Gdynia (EPG) shipped out the topside from the Port of Gdynia on 1 June. The unit arrived in Aalborg last week, Bladt Industries said. RWE’s Kaskasi offshore wind farm, also […]

  • 18 December 2020
    Authorities, Wind Farm Update

    German Federal Maritime and Hydrographic Agency (BSH) has granted planning permission for the 342 MW Kaskasi offshore wind farm (officially known as Kaskasi II). Kaskasi II is the first offshore wind farm in Germany to receive planning permission under the new offshore wind law (WindSeeG), following participation in the auction held under the so-called interim […]

  • 8 June 2022
    R&D, Technology, Wind Farm Update

    For the first time ever in the renewables industry, special collars were installed around the monopile foundation at the seabed level on RWE’s Kaskasi wind farm offshore Germany. The ‘collared monopile’ is a design based on a RWE patent. The new technology is expected to provide additional support for lateral loading, increase the bearing capacity […]

  • 10 April 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dutch cable manufacturer Twentsche Kabel Fabriek (TKF) has revealed further details about the company’s scope of work on the 342 MW Kaskasi offshore wind project. As reported earlier, Seaway 7 awarded TKF with a contract to deliver 33 kV inter-array cables for the wind farm. Under the contract, TKF will manufacture and deliver 52 kilometres […]

  • 14 July 2022
    Grid Connection, Wind Farm Update

    TenneT has connected RWE’s Kaskasi II offshore wind farm to the HelWin Beta platfrom, the heart of the HelWin2 high-voltage direct current (HVDC) offshore grid connection in the German North Sea. Kaskasi II, located 35 kilometres north of the island of Heligoland, is currently under construction with the wind turbine installation work to commence soon. […]

  • 5 April 2023
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Lidl and Kaufland, the retail divisions of the German Schwarz Group, have signed a long-term power purchase agreement (PPA) with RWE Supply & Trading for the Kaskasi offshore wind farm, located in the German North Sea. Under the ten-year agreement, Lidl and Kaufland will be offtaking approximately 250 GWh of renewable electricity produced by Kaskasi […]

  • 3 March 2021
    Contracts & Tenders, Wind Farm Update

    Dutch cable manufacturer Twentsche Kabel Fabriek (TKF) has awarded Vos Prodect Innovations with a contract to deliver Cable Hang-Off Systems for the Kaskasi offshore wind farm in the German North Sea. VPI’s Cable Hang-Off System (HOS) will be used in the installation of 38 Siemens Gamesa SG 8.0-167 DD Flex offshore wind turbines on the […]

  • 14 February 2020
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for the turnkey construction of two AC grid connection systems to connect the 342MW Kaskasi II and the 242MW Gode Wind 3 wind farms in the German North Sea to the associated HVDC sea stations. The scope comprises all works, from design, to manufacturing, delivery, and installation, up […]

  • 12 August 2020
    Contracts & Tenders

    Bladt Industries has selected Energomontaż-Północ Gdynia (EPG) as a subcontractor for the prefabrication of the offshore substation topside and sea fastening for the Kaskasi offshore wind project in Germany. The Polish company started the production of steel structure in July in Gdynia. Bladt is in charge of the construction of the offshore substation, including the […]

  • 6 May 2021
    R&D, Technology, Wind Farm Update

    RWE Renewables, itap, BioConsult SH, the University of Stuttgart, and Technische Universität Berlin are to research an innovative vibratory pile driving technique at RWE’s Kaskasi offshore wind farm. The new method for installing foundations is said to have the potential to significantly reduce underwater noise emissions and installation times. The research project is funded by […]

  • 28 April 2022
    Wind Farm Update

    Seaway 7 has installed all of the monopile foundations within its scope of work for the Kaskasi offshore wind farm and DEME Offshore just announced that its part of the project is progressing and that 22 monopiles are now installed at the 38-turbine offshore wind farm. “Seaway Strashnov completed the monopile installation on the Kaskasi […]

  • 30 March 2022
    Contracts & Tenders, Wind Farm Update

    RWE has awarded a contract to DHSS for logistics at the Port of Eemshaven during the installation phase of its 342 MW Kaskasi offshore wind farm in the German North Sea. Under the contract, DHSS will support RWE with regard to vessel agency services, port logistics, and storage. Services will be managed from the DHSS […]

  • 6 July 2022
    Contracts & Tenders, Wind Farm Update

    Endiprev has started working on the 342 MW Kaskasi offshore wind farm in Germany under a contract with Siemens Gamesa, the project’s wind turbine supplier. Throughout the next six months, Endiprev will perform installation and finishing works for Siemens Gamesa on the Kaskasi offshore wind farm, located in the German North Sea, 35 kilometres north of […]

  • 19 February 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    RWE has signed six new Power Purchase Agreements (PPAs) with major German industrial customers for the supply of around 1,000 GW/h of green energy per year from its Kaskasi offshore wind farm, starting from 2026. PPAs have been signed between RWE Supply & Trading and DHL Group, Ensinger, Evonik, Infraserv Höchst, thyssenkrupp Steel Europe, and […]

  • 10 November 2022
    Wind Farm Update

    Two thirds of the Siemens Gamesa wind turbines at the Kaskasi offshore wind farm are now feeding electricity into the German grid, with the installation of the remaining turbines underway. RWE plans to have all 38 units installed and ready for operation before the end of the year. Offshore construction at the project site, located […]

  • 1 August 2022
    Technology, Wind Farm Update

    The first Siemens Gamesa wind turbine equipped with the company’s RecyclableBlades has generated first power at the Kaskasi offshore wind farm in Germany. This marks the first commercial installation of Siemens Gamesa’s recyclable wind turbine technology and the first time a wind turbine with recyclable blades is installed worldwide, according to the wind turbine manufacturer […]

  • 3 April 2020
    Contracts & Tenders, Wind Farm Update

    German energy company innogy SE has reached a Final Investment Decision (FID) on the 342 MW Kaskasi offshore wind farm project in the German North Sea. In preparation for the construction, contracts for all major components have been signed, innogy said. Located 35 kilometres north of the island of Heligoland, Kaskasi will feature 38 Siemens […]

  • 6 April 2020
    Contracts & Tenders

    Following innogy’s news on reaching the Final Investment Decision (FID) for the Kaskasi project and Bladt Industries being awarded contracts for monopile foundations and offshore substation (OSS), Bladt informed that it will execute the EPCI contract for the OSS in cooperation with Semco Maritime and ISC Engineering.

  • 29 January 2024
    Business & Finance, Project Updates, Wind Farm Update

    German logistics company DHL Group has signed a long-term power purchase agreement (PPA) with RWE Supply & Trading for electricity generated at the 342 MW Kaskasi offshore wind farm, located in the German North Sea. Under the ten-year agreement, DHL will be offtaking around 104 GWh of electricity produced by Kaskasi per year, starting in […]