206 results found for 'Dogger Bank C'

206 results found for 'Dogger Bank C'
Order results by

A list of search results

  • 1 April 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Spain’s Navantia Seanergies has completed the load-out of the High Voltage Direct Current (HVDC) substation jacket for the 1.2 GW Dogger Bank C offshore wind platform in the UK. The load-out of the substation jacket, which will be installed at the Dogger Bank Wind Farm developed by SSE Renewables, Equinor, and Vårgrønn, was completed at […]

  • 7 May 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The installation of the offshore substation jacket foundation and topside for the third phase of the Dogger Bank Wind Farm, the world’s biggest offshore wind farm under construction, will commence soon. Heerema Marine Contractors’ semi-submersible crane vessel (SSCV) Sleipnir will install the offshore substation jacket and topside at the Dogger Bank C site in the […]

  • 27 May 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Heavy lift vessel (HLV) Seaway Alfa Lift, which recently completed the installation of transition pieces (TPs) at Dogger Bank B, has started the same work at the Dogger Bank C offshore wind site in the UK. According to the latest Notice of Operations for Dogger Bank C from Dogger Bank Wind Farm, the vessel has […]

  • 22 May 2025
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The jacket foundation and the topside for Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm, have been installed in the UK. According to the recent Notice to Mariners from the project, Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir installed the jacket foundation and the topside at the Dogger Bank […]

  • 23 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    After installing all 95 monopiles at Dogger Bank B, the offshore installation vessel Seaway Strashnov has moved on to the third phase of the UK’s Dogger Bank Wind Farm, where it has now begun foundation work at Dogger Bank C. Seaway Strashnov and Seaway Alfa Lift commenced the installation work at Dogger Bank B in the spring of […]

  • 20 May 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    All foundations, including the transition pieces (TPs), are now in place at Dogger Bank B, the second phase of the world’s largest offshore wind farm under construction, as the heavy-lift vessel (HLV) Seaway Alfa Lift recently installed the final TP. The vessel started installing the final five TPs earlier this month, after Seaway Strashnov installed the […]

  • 29 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    More than half of the wind turbines at Dogger Bank A, the first phase of the UK’s 3.6 GW Dogger Bank Wind Farm, have been installed. So far, 52 of the 95 GE Haliade-X 13 MW wind turbines that Dogger Bank A will feature are in place, according to a Notice to Mariners from the […]

  • 3 January 2025
    Fixed-Bottom, Foundations, Project Updates, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov has installed all but two monopile foundations at the Dogger Bank B offshore wind site in the UK and will return in the second quarter of 2025 to complete the installation. Five more transition pieces (TPs) are also left to be installed, according to the latest notices to mariners […]

  • 31 March 2025
    Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    The offshore installation vessel Seaway Strashnov will install the remaining two monopiles at the Dogger Bank B offshore wind farm site next month. According to a Notice to Mariners from the project, the work is planned to commence on 7 April and continue until approximately 30 April. The heavy lift vessel, owned by Seaway7, completed […]

  • 31 January 2025
    Business & Finance, Vessels

    UK-headquartered North Star has named and delivered its latest service operation vessel (SOV), completing its fleet of vessels chartered for long-term service at the 3.6 GW Dogger Bank offshore wind farm. The Grampian Tweed is the fourth SOV introduced ahead of schedule to support the Dogger Bank offshore wind farm, owned by a consortium of […]

  • 27 February 2025
    Authorities, Business & Finance, Fixed-Bottom, Grid Connection, Planning & Permitting

    Ofgem is inviting tenders to own and operate electricity transmission links worth GBP 4 billion (about EUR 4.8 billion), connecting the Sofia offshore wind farm to Great Britain’s mainland energy network. Ofgem has opened the Offshore Transmission Owner (OFTO) regime Tender Round 12, which invites investors to bid to own and operate infrastructure connecting RWE’s […]

  • 9 June 2025
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Statutory consultation for the Dogger Bank D offshore wind farm will open on 10 June, as the co-owners of the project, SSE Renewables and Equinor, are working towards applying for development consent. According to information on the UK Planning Inspectorate’s website, the application for a Development Consent Order (DCO) for the project is expected to […]

  • 9 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Proserv has been awarded a contract by DEME Offshore to de-risk offshore wind operations at Dogger Bank C, the third phase of the 3.6 GW Dogger Bank Wind Farm project in the UK. According to Proserv, the company will utilise its Electro Cable Guard (ECG) system to identify signs of transmission cable failure far earlier, […]

  • 24 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    A short geotechnical survey is scheduled to begin at the Dogger Bank D offshore wind farm site in the UK this month. The offshore supply vessel (OSV) Connector will be deployed to carry out the work within the array area and the export cable route. The works will be performed in a single campaign, expected […]

  • 12 December 2024
    Business & Finance, Contracts & Tenders, Supply Chain, Wind Turbines

    Dogger Bank Wind Farm, a joint venture between SSE Renewables, Equinor, and Vårgrønn, has signed a vessel reservation agreement with Seaway7 to charter a second turbine installation vessel to support the ongoing delivery of the offshore wind farm off the coast of England. Starting in 2026, the Seaway Ventus jack-up installation vessel is planned to […]

  • 8 November 2024
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Production of the last transition piece (TP) for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, is underway at Smulders facility in Hoboken, Belgium. The consortium comprising Sif and Smulders was awarded contracts for the manufacture of all monopiles and transition pieces for the three-phased Dogger Bank Wind […]

  • 12 August 2024
    Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    A multibeam echosounder (MBES) geophysical survey of the Dogger Bank D offshore wind site, using several uncrewed surface vessels (USVs), is scheduled to start on 13 August. According to information in the project’s Notice to Mariners, XOCEAN will deploy multiple USVs to survey the wind turbine array site and the export cable route. The USVs will […]

  • 12 November 2021
    Contracts & Tenders, Wind Farm Update

    A consortium between Sif and Smulders has signed a contract for the manufacture of all 87 monopiles and transition pieces for Dogger Bank C, the third and final phase of what will become the world’s largest offshore wind farm. The contract follows the same work awarded to the Sif-Smulders consortium a year ago, when the […]

  • 30 June 2021
    Grid Connection, Wind Farm Update

    NKT has secured a contract to deliver and install the HVDC onshore and offshore export cables at the Dogger Bank C offshore wind farm in the UK. The scope of work includes the manufacture, delivery and installation of more than 2×250 kilometres total system length of 320 kV DC offshore export power cables and accessories. […]

  • 18 December 2020
    Contracts & Tenders, Wind Farm Update

    GE Renewable Energy has secured a preferred turbine supplier contract to provide its 14 MW Haliade-X turbine for the third phase of the Dogger Bank offshore wind project. The 14 MW Haliade-X is an upscaled version of the 13 MW unit which will be installed at Dogger Bank A & B, and Dogger Bank C […]

  • 21 April 2022
    Grid Connection, Wind Farm Update

    Aibel has started the construction of the offshore converter platform for the third phase of the 3.6 GW Dogger Bank offshore wind farm – Dogger Bank C. The first steel for the platform was cut at Aibel’s Laem Chabang yard in Thailand. In keeping with the tradition, the steel was blessed by Thai monks prior […]

  • 18 May 2021
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm and GE Renewable Energy have finalised contracts for the supply of 87 Haliade-X 14 MW turbines and a five-year service and warranty agreement for Dogger Bank C, the third and final phase of what will become the world’s largest offshore wind farm. GE Renewable Energy secured a preferred turbine supplier agreement […]

  • 24 November 2021
    Business & Finance, Wind Farm Update

    15-year offtake Power Purchase Agreements (PPAs) have been signed for the third phase of the 3.6 GW Dogger Bank, the world’s largest offshore wind farm, SSE Renewables and Equinor said. Dogger Bank Wind Farm will be constructed over 130 kilometres out to sea off the north-east coast of England and is expected to be fully […]

  • 16 December 2021
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    DEME Offshore has won the engineering, procurement, construction and installation (EPCI) contract for the inter-array cables at the Dogger Bank C offshore wind farm in the UK.

  • 8 February 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dogger Bank C will become the first UK offshore wind farm to use the functionality of its transmission assets to help stabilise voltage on the grid and support multi-million-pound consumer savings, according to National Grid ESO, which selected Dogger Bank C following a competitive tender process. The 1.2 GW project, which is the third phase […]

  • 17 February 2021
    Contracts & Tenders, Grid Connection

    Aibel and Hitachi ABB Power Grids have been awarded contracts for the third phase of the 3.6 GW Dogger Bank Wind Farm development, Dogger Bank C. Under an EPC contract, Aibel will deliver a third converter platform for the world’s largest offshore wind farm. In October 2019, the company was selected to deliver two platforms for the […]