494 results found for 'Hornsea Project Two'

494 results found for 'Hornsea Project Two'
Order results by

A list of search results

  • 24 April 2023
    Grid Connection, Wind Farm Update

    Construction activities on the two offshore substations for the Hornsea Three offshore wind farm in the UK have kicked off at Aibel’s yard in Thailand. Ørsted, the developer of Hornsea Three, signed an EPCI contract with partners Aibel and Hitachi Energy for the two platforms in 2022. Under the contract, Hitachi Energy will supply two […]

  • 23 June 2023
    Contracts & Tenders, Wind Farm Update

    Hellenic Cables has signed a contract with Ørsted for the supply of inter-array cables for the 2.85 GW Hornsea Three offshore wind farm in the UK. The company will deliver some 262 kilometres of cables, which covers approximately 50 per cent of the overall wind farm requirements. Under the contract, the Greek cable manufacturer will […]

  • 10 February 2023
    Authorities, Wind Farm Update

    The UK’s Planning Inspectorate has delayed a final decision on granting approval for Ørsted’s 2.6 GW Hornsea Four offshore wind farm by nearly five months. Ørsted submitted a Development Consent Order (DCO) application for Hornsea Four to the UK Planning Inspectorate in September 2021. The Examining Authority issued a Recommendation Report related to the project […]

  • 30 November 2016
    Wind Farm Update

    DeepOcean has won a multi-million pound contract to transport and install cables for DONG Energy’s Hornsea Project One wind farm, located 120km off the Yorkshire Coast.  DeepOcean’s scope of work covers the installation and trenching of 93 inter-array cables with a combined length of 203km. The Hornsea Project One contract also includes the associated route engineering, […]

  • 28 September 2023
    Business & Finance

    London-based international investor and manager, John Laing Group, has acquired a stake in the transmission assets for the 1.3 GW Hornsea Two offshore wind farm in the UK, as part of a portfolio acquisition from HICL Infrastructure. John Laing Group has agreed to acquire HICL Infrastructure’s entire equity interest in four UK public-private partnership projects, […]

  • 25 April 2023
    Contracts & Tenders, Wind Farm Update

    Cadeler and Ørsted signed two contracts for the 2.9 GW Hornsea Three offshore wind farm in the UK today, 25 April, at the WindEurope Exhibition in Bella Centre, Copenhagen: one for the installation of monopile foundations and one for the installation of around half of the project’s wind turbines. In a press release issued today, […]

  • 21 October 2020
    Business & Finance, Vessels, Wind Farm Update

    Cadeler, formerly known as Swire Blue Ocean, is ready to send its Pacific Orca vessel in early 2021 to support foundation installation at the Hornsea Two offshore wind farm in the UK. The company has been subcontracted by DEME to deliver a vessel which will support the installation of the wind farm’s 165 monopile foundations, and Pacific […]

  • 8 October 2021
    Wind Farm Update

    DEME Offshore has installed 100 turbines on the Hornsea Two offshore wind farm, with 65 more of Siemens Gamesa 8.4 MW units left to be put into place. The jack-up vessel Sea Challenger installed the first wind turbine at the end of May and in less than three months later the project had 50 wind turbines installed […]

  • 31 March 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ørsted has awarded NKT with a supply contract for the delivery of the high-voltage DC on- and offshore export cable system for the Hornsea 3 wind farm offshore the UK. For NKT, the final order has an estimated contract value of approximately EUR 500 million in market prices. The contract will comprise the design, manufacturing, […]

  • 28 September 2020
    Wind Farm Update

    DEME Group’s jack-up vessel Innovation is set to begin the monopile installation at the Hornsea Two offshore wind project next month. In total, 165 monopiles and transition pieces will be installed at the offshore site in the UK in preparation for the Siemens Gamesa 8.4 MW turbines. With a height from sea level to blade […]

  • 3 July 2023
    Contracts & Tenders, Wind Farm Update

    Prysmian Group has been awarded a contract by Ørsted Wind Power A/S to supply inter-array submarine cables for the 2.9 GW Hornsea 3 offshore wind farm in the UK. Under the contract, subject to Ørsted taking a Final Investment Decision on Hornsea 3, Prysmian Group will be responsible for the design, manufacture, supply, termination, and […]

  • 24 August 2015

    Team Humber Marine Alliance (THMA) has welcomed DONG Energy taking full control of the Hornsea Round 3 wind zone, one of the world’s biggest offshore wind development schemes. Mark O’Reilly, CEO and chairman of THMA, one of the UK’s offshore and marine business development organisations, said: “THMA is delighted that DONG Energy has progressed its […]

  • 5 May 2016
    Business & Finance, Wind Farm Update

    International law firm Pinsent Masons has been appointed to advise DONG Energy on the Hornsea Project Three offshore wind farm. The Pinsent Masons’ multidisciplinary team, led by energy and planning partner, Gareth Phillips, has been instructed to assist DONG Energy in securing development consent, with construction expected to take place between 2022 and 2025. “We […]

  • 21 April 2021
    Ports & Logistics, Vessels, Wind Farm Update

    Well over a third out of the 165 monopile foundations have been installed at the 1,386 MW Hornsea Two offshore wind farm located some 89 kilometres north-east of Grimsby, the U.K. The monopile foundations are being loaded at and transported from the Buss Terminal Eemshaven in the Netherlands and installed at the site by DEME […]

  • 21 December 2023
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on what the company says is the world’s single largest offshore wind farm, the 2.9 GW Hornsea 3, which is expected to be completed around the end of 2027. In July 2022, Ørsted was awarded a contract for difference (CfD) for Hornsea 3 at an inflation-indexed strike price of […]

  • 11 August 2022
    Business & Finance, Wind Farm Update

    All wind turbines have been fully commissioned and are commercially operational at the 1.3 GW Hornsea Two in the UK which will soon become the world’s biggest single operational offshore wind farm. The project’s owner and developer, Ørsted, expects the wind farm to be fully commissioned later this month, after the remaining reliability runs are […]

  • 18 April 2018
    Grid Connection, Vessels, Wind Farm Update

    Tideway BV, part of DEME Group, has laid the first offshore export cable section at Hornsea Project One, Ørsted’s 1.2GW wind farm offshore Yorkshire, UK.

  • 15 October 2020
    Operations & Maintenance, Technology, Wind Farm Update

    The wind turbines at the Hornsea Two offshore wind farm in the UK do not feature the usual setup including boat landing structures and ladders, as its developer Ørsted purchased a novel lifting system. The 1.4 GW project is the first-ever offshore wind farm to deploy the Get Up Safe (GUS) motion-compensated lifting system from […]

  • 17 March 2022
    Authorities, Wind Farm Update

    Ørsted and BP have submitted position statements to the UK Planning Inspectorate with regard to their offshore wind and carbon capture, usage and storage (CCUS) projects in the UK, with Ørsted saying BP is trying to force exclusion so that the offshore wind developer cannot locate its Hornsea Four turbines in an overlapping seabed area. Namely, […]

  • 26 June 2023
    Wind Farm Update

    Ørsted and BP have reached an agreement on the previously disputed overlap area between the Hornsea Four offshore wind farm and the Endurance carbon storage site, developed by the Northern Endurance Partnership (NEP) that gathers BP, Equinor and TotalEnergies. Quick overview: Ørsted submitted an application for the development consent order (DCO) for the 2.6 GW […]

  • 26 January 2021
    Vessels, Wind Farm Update

    Ørsted is set to welcome three new hybrid crew transfer vessels (CTVs) to assist with the construction at the Hornsea Two offshore wind farm. Northern Offshore Services (N-O-S) will take delivery of its 39m Energizer in the spring and MHO-Co is due to deliver its two 35m CTVs in the summer. The vessels will be […]

  • 3 September 2024
    Authorities, Planning & Permitting

    Offshore wind developers have been awarded contracts for approximately 5.3 GW of capacity in the UK’s latest Contract for Difference (CfD) Allocation Round 6 (AR6). Ørsted received the largest CfD for offshore wind, securing 2.4 GW for the Hornsea 4 offshore wind project. The offshore wind farms awarded CfDs are the 288 MW Inch Cape […]

  • 3 March 2020
    Contracts & Tenders, Wind Farm Update

    Jumbo Shipping has secured a contract with DEME Offshore for the transport of foundations for the Hornsea Two offshore wind project. Jumbo will transport 165 monopiles from Rostock, Germany, and 135 transition pieces from Aalborg, Denmark, to Eemshaven, the Netherlands, with a K3000 class vessel. Additionally, the company will undertake the project management for the […]

  • 3 June 2019
    Operations & Maintenance, Wind Farm Update

    Ørsted has officially started operations on the 1,214MW Hornsea One, the largest offshore wind farm in the world. The project’s first operational team of 32 set sail from Grimsby Royal Docks to the wind farm located 120 kilometres out to sea on 31 May. They are part of two shift-based teams that are responsible for […]

  • 12 December 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Ørsted has awarded several contracts totalling between GBP 75 million and GBP 100 million to companies in the north of England to provide components for the 2.9 GW Hornsea 3 offshore wind farm. JDR Cable Systems, Severfield, and Smulders, all based in the north of England, will produce integral components and services for the Hornsea […]

  • 25 January 2024
    Cables, Contracts & Tenders, Grid Connection, Supply Chain

    Ørsted and Jan De Nul Group have signed the offshore export cable installation contract for the 2.9 GW Hornsea 3 offshore wind farm in the UK. This is the first offshore HVDC installation contract awarded by Ørsted in the UK, the company said. Belgium-headquartered Jan De Nul Group will be responsible for the seabed preparation, […]