494 results found for 'Hornsea Project Two'

494 results found for 'Hornsea Project Two'
Order results by

A list of search results

  • 23 June 2021

    World’s leading offshore wind developer Ørsted has installed its 1,000th offshore wind turbine in UK waters. The company’s 1,000th turbine was a Siemens Gamesa 8.4 MW unit installed at the 1,386 MW Hornsea Two offshore wind farm, the 16th wind turbine to be erected at the wind farm. Ørsted currently has 12 operational offshore wind […]

  • 15 November 2010

    SMart Wind, the consortium lead by Mainstream Renewable Power and Siemens Project Ventures, has appointed GL Garrad Hassan to act as Independent Engineer for the first two 500MW projects in the 4GW ‘Hornsea’ zone located off the coast of Yorkshire. Last month the consortium announced it has secured grid connection for the first two 500MW […]

  • 21 October 2021
    Wind Farm Update

    Ørsted’s 1,386 MW Hornsea Two offshore wind farm, soon to be the world’s largest, has reached several significant construction milestones, with more to come in the coming days. All of the wind farm’s turbine foundations have now been installed, as well as the project’s offshore substation at the North Sea site 89 kilometres off the […]

  • 20 December 2021
    Wind Farm Update

    Hornsea Two, soon to be the world’s largest offshore wind farm in operation, has generated its first power, Ørsted, the owner and developer of the project, said. When fully operational, Hornsea 2’s 165 8 MW Siemens Gamesa wind turbines will be capable of generating 1.32 GW of clean electricity – taking the title of ‘world’s […]

  • 19 October 2021
    Wind Farm Update

    Ørsted has submitted a Development Consent Order (DCO) application for its Hornsea Four offshore wind project to the UK Planning Inspectorate. The developer informed on 14 October that it had filed the DCO application on 29 September, after completing pre-application consultation. Ørsted started introducing early-stage proposals for the Hornsea Four offshore wind farm at local […]

  • 24 April 2023
    Grid Connection, Wind Farm Update

    Construction activities on the two offshore substations for the Hornsea Three offshore wind farm in the UK have kicked off at Aibel’s yard in Thailand. Ørsted, the developer of Hornsea Three, signed an EPCI contract with partners Aibel and Hitachi Energy for the two platforms in 2022. Under the contract, Hitachi Energy will supply two […]

  • 28 May 2021
    Wind Farm Update

    The first of the total 165 wind turbines has been installed on the Hornsea Two offshore wind farm in the UK, where the wind turbine installation phase began this week, as reported in our Premium news on 27 May. DEME’s installation vessel Sea Challenger, loaded with the first set of turbine components, arrived at the […]

  • 19 October 2020
    Grid Connection, Wind Farm Update

    Heerema Marine Contractors’ semi-submersible crane vessel Sleipnir has installed the jacket foundation for the reactive compensation station (RCS) at the Hornsea Two offshore wind project. Sleipnir installed the jacket foundation for the project’s offshore substation at the beginning of October. After the OSS foundation installation, the vessel moved to the shallow water to install the 1,500 metric […]

  • 30 November 2016
    Wind Farm Update

    DeepOcean has won a multi-million pound contract to transport and install cables for DONG Energy’s Hornsea Project One wind farm, located 120km off the Yorkshire Coast.  DeepOcean’s scope of work covers the installation and trenching of 93 inter-array cables with a combined length of 203km. The Hornsea Project One contract also includes the associated route engineering, […]

  • 30 September 2022
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50 per cent of its 1.3 GW Hornsea Two project, the world’s largest offshore wind farm in operation. The developer sold half of the project to a consortium comprising AXA IM Alts, acting on behalf of clients, and Crédit Agricole Assurances. Ørsted announced the Hornsea Two offshore farm-down in […]

  • 8 June 2021
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Sea Installer has arrived at the Port of Hull in the UK to load the first set of turbine components to be installed on the 1,386 MW Hornsea Two offshore wind farm. Sea Installer is joining her sister vessel Sea Challenger on the project which has already installed the first batch of […]

  • 8 October 2021
    Wind Farm Update

    DEME Offshore has installed 100 turbines on the Hornsea Two offshore wind farm, with 65 more of Siemens Gamesa 8.4 MW units left to be put into place. The jack-up vessel Sea Challenger installed the first wind turbine at the end of May and in less than three months later the project had 50 wind turbines installed […]

  • 18 March 2022
    Wind Farm Update

    Ørsted is set to kick off a geotechnical survey campaign at the Hornsea Three offshore wind project in the UK starting from April. The 90-meter long survey vessel Connector Express will start the survey on 1 April at the project site located off the coast of East Yorkshire, and works are expected to last for […]

  • 11 March 2016
    Jobs & Recruitment

    Atlas Professionals’ Offshore Wind office, based in Bristol, will be looking for experienced onshore and offshore professionals for the entire lifecycle of the Hornsea Project One wind farm, from the planning stage through to the construction and O&M phase.   In 2014, Atlas signed a five-year framework agreement with DONG to supply temporary personnel for […]

  • 6 August 2021
    Grid Connection, Ports & Logistics, Wind Farm Update

    The topsides for the Hornsea Two offshore substation and the reactive compensation station have been loaded onto Guangzhou Salvage’s vessel Hua Hai Long at Sembawang, Singapore. The topsides will soon be ready to start their journey to the UK, Guangzhou Salvage said. The topsides were manufactured by Sembcorp Marine. The jacket foundations for the offshore […]

  • 4 January 2021
    Grid Connection, Wind Farm Update

    VolkerInfra has completed the onshore cable installation for the Hornsea Two offshore wind project in the UK. VolkerInfra installed a total of 350 km of cable over 39 km of Lincolnshire land, reaching from the wind farm’s landfall point at Horseshoe Point to North Killingholme. Reinstatement works are expected to continue on the ground until […]

  • 10 September 2021
    Contracts & Tenders, Operations & Maintenance

    Manor Renewable Energy (MRE) has signed a contract to charter a new build crew transfer vessel from WEM Marine LTD to support its work supplying temporary power solution at the 1.4 GW Hornsea Two offshore wind farm. WEM Marine LTD’s vessel, the WEM3, joined MRE on Hornsea Two in July 2021. The WEM3 is a […]

  • 18 May 2020
    Business & Finance

    Siemens Gamesa has signed a bank guarantee line for up to EUR 600 million to cover the construction of components for the 1.4 GW Hornsea Two offshore wind farm. Located in the North Sea and owned by Danish utility company Ørsted, the farm will consist of 165 Siemens Gamesa wind turbines. BNP Paribas lead managed […]

  • 17 February 2022
    Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Fugro has won a contract by Ørsted to carry out geotechnical site investigations at the Hornsea Three and Hornsea Four offshore wind projects in the UK. The site investigations will include downhole cone penetration testing (CPT), seismic cone penetration testing (SCPT), downhole sampling and high-quality rock coring, as well as borehole geophysical logging. Fugro will mobilize multiple […]

  • 24 September 2021
    Contracts & Tenders, Wind Farm Update

    Aberdeen-based Swire Energy Services (SES) has signed a contract with Ørsted for the provision of helideck services and helicopter refuelling system services for the Hornsea One wind farm in the UK Southern North Sea. According to Swire Energy Services, the two-year contract, with the option of two one-year extensions, covers the provision of helideck services […]

  • 21 September 2020
    Vessels

    Louis Dreyfus Armateurs’ (LDA’s) new service operations vessel (SOV), which will be working at Ørsted’s Hornsea Two offshore wind farm, was launched on 21 September at Cemre Shipyard in Turkey. The Wind of Hope SOV, ordered in 2018, is expected to arrive at Ørsted’s operations and maintenance (O&M) facility at the port of Grimsby in […]

  • 5 July 2021
    Wind Farm Update

    DEME Offshore has installed the 100th monopile foundation at the 165-turbine Hornsea Two wind farm offshore the UK. DEME installed the first foundation at the site some 89 kilometres north-east of Grimsby in early October 2020. The monopile foundations are being loaded at and transported from the Buss Terminal Eemshaven in the Netherlands and installed at the […]

  • 9 August 2021
    Ports & Logistics, Wind Farm Update

    The Rostock-based EEW Special Pipe Constructions GmbH has loaded out the last five monopiles for Ørsted’s Hornsea Two offshore wind farm. The final five monopiles were loaded out at EEW SPC’s quay on 30 July. In the past eleven months, a total of 165 monopiles was loaded for the project by two self-geared vessels. The […]

  • 17 March 2022
    Authorities, Wind Farm Update

    Ørsted and BP have submitted position statements to the UK Planning Inspectorate with regard to their offshore wind and carbon capture, usage and storage (CCUS) projects in the UK, with Ørsted saying BP is trying to force exclusion so that the offshore wind developer cannot locate its Hornsea Four turbines in an overlapping seabed area. Namely, […]

  • 8 September 2020
    Wind Farm Update

    The first six transition pieces for the Hornsea Two offshore wind project have arrived from the UK at the Buss Terminal in Eemshaven, Netherlands. Over the next months, Buss will receive a total of 165 foundation sets, which will be handled and stored at the terminal. The foundations will then be loaded onto DEME Group’s […]

  • 3 November 2020
    Contracts & Tenders, Vessels

    Solstad Offshore has been awarded a contract by Ørsted to deploy its offshore support vessel (OSV) Normand Jarstein on the Hornsea Two offshore wind farm in the UK. The contract has been signed for a period of four months, starting in the third quarter of 2021, when the vessel will support operations at the 1.4 […]