    Registration is now open for organisations and individuals who wish to become registered parties in relation to the Dogger Bank Creyke Beck development consent order application. The Planning Inspectorate accepted Forewind’s application for the first stage of offshore wind energy development on the Dogger Bank Zone – Dogger Bank Creyke Beck – on September 25 […]

  • 22 September 2022
    Contracts & Tenders, Wind Farm Update

    Jones Bros Civil Engineering has installed approximately 117 kilometres of onshore high voltage direct current (HVDC) cables for the 3.6 GW Dogger Bank offshore wind farm. The Dogger Bank project, which is being built in three phases A, B, and C, is the first offshore wind farm in the UK to use HVDC technology, which […]

  • 25 April 2022
    Business & Finance, Wind Farm Update

    UK-based marine consultant Waves Group Ltd (Waves Group) has secured the Marine Warranty Surveyor (MWS) contract for the construction of the 1.2 GW Dogger Bank C wind farm offshore England. This is the company’s third win of the three project phases as they’re currently providing MWS services for Dogger Bank A and B. The third […]

  • 21 July 2021
    Operations & Maintenance, Wind Farm Update

    South Tyneside Council’s Planning Committee has granted permission for the construction of Dogger Bank Wind Farm’s operations and maintenance (O&M) base in the Port of Tyne. Equinor submitted an application with the accompanying planning documents to the Planning Committee in February, requesting permission to build the O&M base and warehouse with associated access, parking, landscaping […]

  • 30 April 2015
    Wind Farm Update

    Through the undertaken surveys as part of its environmental impact assessment process, Forewind has extended the depth of knowledge about the geology of Dogger Bank. Geological maps used prior to Forewind’s work in the area were based on sparse data, gathered tens of kilometres apart in the late 1960s and 1970s. But since a far greater […]

  • 5 May 2016
    Operations & Maintenance, Technology, Vessels, Wind Farm Update

    Forewind has used its latest operations and maintenance trip to the meteorological masts on Dogger Bank to trial new technology and methodology. The trip enabled aerial inspection and survey contractor Cyberhawk to utilise a new advanced camera technology to inspect the overall status of the met masts and condition of bolts along with the structure of the lattice […]

  • 10 August 2017
    Business & Finance, Wind Farm Update

    Statoil has signed a swap agreement with innogy and SSE for equity interests in the Dogger Bank offshore wind development project.

  • 8 February 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Dogger Bank C will become the first UK offshore wind farm to use the functionality of its transmission assets to help stabilise voltage on the grid and support multi-million-pound consumer savings, according to National Grid ESO, which selected Dogger Bank C following a competitive tender process. The 1.2 GW project, which is the third phase […]

  • 26 December 2022
    Contracts & Tenders

    DEME Offshore has picked Tekmar Group to supply Cable Protection Systems (CPS) for the third phase of Dogger Bank Wind Farm in the UK. Under the contract signed with DEME Offshore, Tekmar will design, manufacture, and supply 172 CPS for Dogger Bank C. The first systems for the project’s third phase are expected to be […]

  • 24 August 2021
    Contracts & Tenders, Vessels, Wind Farm Update

    North Star Renewables has secured a loan of GBP 96 million (approximately EUR 112 million) from Allianz Global Investors (AllianzGI) to build the three Service Operations Vessels (SOVs) that will serve the Dogger Bank offshore wind farm.  The vessel owner said the loan added to its own balance sheet and equity commitments from its 100 per cent shareholder, […]

  • 24 September 2019
    Business & Finance, Ports & Logistics

    The Port of Sunderland has declared itself “ready, willing and able to deliver” for the Dogger Bank offshore wind project selected in the UK Government’s third Contracts for Difference (CfD) allocation round. The port, owned and operated by Sunderland City Council, said it expects to see strong interest in its facilities and services, after the Government’s decision to approve the […]

  • 14 October 2020
    Contracts & Tenders

    Waves Group has secured a contract to provide marine warranty surveyor services for the Dogger Bank offshore wind project in the UK. Waves Group is providing the services for Dogger Bank A, which involves the installation of foundations, infield cables, turbines, export cables and one offshore substation and the foundation for Dogger Bank B.  Operations […]

  • 15 March 2023
    Wind Farm Update

    RWE is performing a benthic survey off the northeast coast of the UK, where the company plans to build its 3 GW Dogger Bank South (DBS) Offshore Wind Farm. According to a Notice to Mariners from the project, the developer has contracted Ocean Ecology to carry out a seabed habitat survey at the offshore wind […]

  • 9 May 2022
    Contracts & Tenders, Vessels

    North Star has awarded the Netherlands-based MO4 with a 10-year contract to supply the company’s four service operations vessels (SOVs) with a digital twin and artificial intelligence (AI) decision support software package. According to MO4, the technology will provide operational data analytics and forecasting support to help drive efficiencies across the fleet including low carbon […]

  • 29 April 2022
    Wind Farm Update

    Offshore construction work has now officially started on what will become the world’s largest offshore wind farm with the installation of the first length of the HVDC export cable off the Yorkshire coast. NKT has commenced work on the laying of the nearshore cable for Dogger Bank A, the first of the three 1.2 GW […]

  • 3 August 2020
    Contracts & Tenders

    Offshore Heavy Transport (OHT) has signed a contract for transport and installation of foundations for the Dogger Bank A offshore wind farm, after being chosen as the preferred supplier for the work in 2019. The contract is subject to the project’s final investment decision, according to OHT, which expects a contract for the second phase, […]

  • 20 November 2014
    Authorities, Wind Farm Update

    The UK Planning Inspectorate issued a report of recommendation for Dogger Bank Creyke Beck to the Secretary of State on November 17, 2014. The Secretary of State has 3 months in which to issue a decision. The decision letter and report of recommendation will be published on the Planning Inspectorate’s website once a decision has been made. […]

  • 15 March 2023
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    The Operations & Maintenance (O&M) base for the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction, has officially been opened at the Port of Tyne, the UK. The O&M base also houses the control room that will monitor and manage five per cent of the UK’s electricity generating capacity, […]

  • 10 June 2021
    Contracts & Tenders, Technology, Wind Farm Update

    ABB will deliver 95 units of medium voltage converters for wind turbines to GE Renewable Energy for the first phase of the Dogger Bank offshore wind project. This is ABB’s first major order under its Long-Term Supply Agreement (LTSA) with GE Renewable Energy and the largest order of its kind to date. The 95 PCS6000 […]

  • 6 August 2015
    Authorities

    The Crown Estate has welcomed the UK Government’s approval of Dogger Bank Teesside A & B offshore wind project. Head of Offshore Wind for The Crown Estate, Huub den Rooijen said: “Today’s announcement marks a great success for the future of the UK’s infrastructure development and is testimony to the hard work of Forewind and the […]

  • 10 November 2022
    Vessels

    The Norwegian company Integrated Wind Solutions (IWS) has launched IWS Skywalker, the first Commissioning Service Operation Vessel (CSOV) in the Skywalker series, chartered for the Dogger Bank Wind Farm in the UK. The vessel will now continue outfitting alongside the yard’s quay to be ready for operations next year, IWS said on social media. The […]

  • 13 June 2022
    Vessels, Wind Farm Update

    Seaway Strashnov will be deployed on Dogger Bank Wind Farm for a full 2023 campaign as the company’s new vessel Seaway Alfa Lift, which suffered a crane incident in 2021, is now scheduled to be delivered in the second half of 2023. As reported last year, the vessel had an incident with the A-frame on […]

  • 24 November 2020
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Dogger Bank Wind Farm developers, SSE Renewables and Equinor, have signed four agreements for power offtake for the entire output of the first two phases of the world’s largest offshore wind farm, Dogger Bank A and B. Ørsted and Shell Energy Europe have inked 15-year Power Purchase Agreements (PPAs) for 40 per cent and 20 […]

  • 21 March 2022
    Vessels, Wind Farm Update

    IWS Fleet, a fully owned subsidiary of the Norwegian company Integrated Wind Solutions (IWS), has been notified by Dogger Bank Wind Farm that they intend to sign a charter contract for one of its Skywalker class walk-to-work commissioning service operation vessels (CSOVs) for the third phase of the offshore wind farm, Dogger Bank C. The […]

  • 30 October 2019
    Grid Connection, Wind Farm Update

    ABB has secured a contract to supply its high-voltage direct current (HVDC) Light® converter systems to connect the Dogger Bank offshore wind project to the UK transmission network. In the first-ever use of the HVDC technology in the UK’s offshore wind market, ABB will supply technology with one of the smallest environmental footprints, due to the […]

  • 26 September 2013
    Authorities

    The Planning Inspectorate accepted Forewind’s development consent order application for the first stage of offshore wind energy development on the Dogger Bank Zone. The application for Dogger Bank Creyke Beck, comprising two offshore wind farms with a total installed capacity of up to 2.4 gigawatts (GW), was submitted in August after more than three years […]