Search results for: hornsea two

492 results

A list of search results

  • 17 August 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has loaded out its first batch of transition pieces (TPs) for the Hornsea Project Two offshore wind farm in the UK. The company will deliver 30 transition pieces for the project. Hornsea Two will comprise 165 Siemens Gamesa 8 MW turbines on monopile foundations, and an offshore substation and a reactive […]

  • 30 April 2020
    Grid Connection, Wind Farm Update

    ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from Horseshoe Point, east of Tetney, to the […]

  • 15 February 2018
    Authorities, Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has sent an application to the UK’s Planning Inspectorate to reduce the maximum number of offshore HVAC collector substations permitted under the Hornsea Project Two Development Consent Order (DCO).

  • 26 April 2022
    Business & Finance, Grid Connection, Wind Farm Update

    NKT has commissioned the 220 kV HVAC export cable system connecting the 1.3 GW Hornsea Two offshore wind project to the UK grid. NKT manufactured the power cables for the project at its factory in Karlskrona, Sweden. The installation of the subsea cables was completed by the cable-laying vessel NKT Victoria. “Constructing a project of […]

  • 21 August 2015
    Business & Finance, Wind Farm Update

    Today, DONG Energy acquired the Hornsea Zone and the project rights to Hornsea Project Two and Three, which have the potential of 3 gigawatts (GW) of offshore wind capacity. This follows DONG Energy’s acquisition of Hornsea Project One, a 1,200 megawatt (MW) offshore wind project in the Round 3, which was announced in February 2015. […]

  • 5 December 2018

    Semco Maritime and ISC Consulting Engineers have completed the design of the offshore substation and the Reactive Compensation Station (RCS) for the Hornsea Project Two offshore wind farm.

  • 11 August 2022
    Business & Finance, Wind Farm Update

    All wind turbines have been fully commissioned and are commercially operational at the 1.3 GW Hornsea Two in the UK which will soon become the world’s biggest single operational offshore wind farm. The project’s owner and developer, Ørsted, expects the wind farm to be fully commissioned later this month, after the remaining reliability runs are […]

  • 24 July 2019
    Contracts & Tenders, Grid Connection

    Seaway 7, a unit of Subsea 7, has won a contract for the installation of the inter-array grid cable system at the Hornsea Project Two offshore wind farm in the UK. In addition to the submarine cable installation works, Seaway 7 will undertake a pre-installation submarine cable route survey, perform pre-installation boulder clearance activities and […]

  • 9 August 2021
    Ports & Logistics, Wind Farm Update

    The Rostock-based EEW Special Pipe Constructions GmbH has loaded out the last five monopiles for Ørsted’s Hornsea Two offshore wind farm. The final five monopiles were loaded out at EEW SPC’s quay on 30 July. In the past eleven months, a total of 165 monopiles was loaded for the project by two self-geared vessels. The […]

  • 8 June 2020
    Contracts & Tenders

    Spectrum Geosurvey has secured a construction survey support contract for Ørsted’s Hornsea Two offshore wind project in the UK. Under the two-year contract, Spectrum will provide on-demand geophysical survey capacity for the wind farm. “We are delighted to secure another long-term contract allowing us to further invest in new technology and our highly skilled workforce,” […]

  • 9 August 2021
    Operations & Maintenance, Ports & Logistics, Vessels, Wind Farm Update

    Ørsted’s new service operations vessel (SOV) Wind of Hope has arrived in the Port of Grimsby in the UK to prepare for working out at sea on the world’s largest offshore wind farms. Up to 60 of Ørsted’s wind turbine technicians will call the 84-metre vessel home for two weeks at a time, whilst they […]

  • 6 November 2019
    Contracts & Tenders

    Ørsted has contracted LOC Group to carry out Marine Warranty Surveyor (MWS) services for the Hornsea Project Two offshore wind farm in the UK. Under the 18-month agreement, LOC London and LOC Singapore will execute all MWS work on the project’s substations. “Hornsea Two is a game-changing renewable energy project in terms of both scale […]

  • 20 May 2020
    Technology

    Boskalis has taken delivery of a purpose-built pre-lay plough from Soil Machine Dynamics Ltd (SMD) for use at Ørsted’s Hornsea Two offshore wind project in the UK. Boskalis will use the Megalodon plough to install 380km of export cables which will connect the project’s offshore substation to the onshore substation in Killingholme, Lincolnshire. According to […]

  • 18 January 2019
    Business & Finance

    Ørsted is holding a series of community information events about the onshore cable route for the Hornsea Project Two offshore wind project in the UK. According to the Danish company, the aim of the events is that local people in North East Lincolnshire and East Lindsey find our more about the onshore cabling works for the […]

  • 11 July 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    ABB has won orders worth over USD 150 million from Danish energy company Ørsted to supply a range of technologies that will help integrate and transmit energy from the Hornsea Project Two offshore wind farm to the UK grid.

  • 8 September 2020
    Wind Farm Update

    The first six transition pieces for the Hornsea Two offshore wind project have arrived from the UK at the Buss Terminal in Eemshaven, Netherlands. Over the next months, Buss will receive a total of 165 foundation sets, which will be handled and stored at the terminal. The foundations will then be loaded onto DEME Group’s […]

  • 26 January 2021
    Vessels, Wind Farm Update

    Ørsted is set to welcome three new hybrid crew transfer vessels (CTVs) to assist with the construction at the Hornsea Two offshore wind farm. Northern Offshore Services (N-O-S) will take delivery of its 39m Energizer in the spring and MHO-Co is due to deliver its two 35m CTVs in the summer. The vessels will be […]

  • 3 September 2019
    Ports & Logistics, Wind Farm Update

    Ørsted has officially opened the Hornsea Two Offshore Construction Base (HTOCB) at Humberside Airport in Lincolnshire. The building, formerly a police station at the airport, will now house around 30 Ørsted employees who will be working around the clock to construct the 1.4GW wind farm. Hornsea Two, located 89 kilometres off the Yorkshire Coast, will […]

  • 28 April 2020
    Vessels

    Louis Dreyfus Armateurs (LDA) has selected SCHOTTEL to supply a range of propulsion systems for its service operations vessel (SOV) Wind of Hope. The propulsion system of Wind of Hope is powered by four diesel generators, which drive the electric motors of the SCHOTTEL propulsion package. Two SCHOTTEL Rudderpropellers type SRP 430 FP, each with […]

  • 31 December 2021
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Sea Installer has left the Port of Hull loaded with the last batch of turbine components to be installed at the 1.32 GW Hornsea Two – soon to be the world’s largest offshore wind farm in operation. Sea Installer and Sea Challenger have been transporting the wind farm’s 165 Siemens Gamesa 8.4 […]

  • 26 June 2023
    Wind Farm Update

    Ørsted and BP have reached an agreement on the previously disputed overlap area between the Hornsea Four offshore wind farm and the Endurance carbon storage site, developed by the Northern Endurance Partnership (NEP) that gathers BP, Equinor and TotalEnergies. Quick overview: Ørsted submitted an application for the development consent order (DCO) for the 2.6 GW […]

  • 19 October 2021
    Ports & Logistics, Wind Farm Update

    Buss Terminal in Eemshaven, the Netherlands, has completed the handling and load-out of the 165 monopile foundations for the 1,386 MW Hornsea Two offshore wind farm. Over the last 15 months, Eemshaven served as the base port for the handling and load-out of the 165 monopiles and transition pieces. The Buss Terminal in Eemshaven was […]

  • 10 January 2019
    Authorities, Wind Farm Update

    Ørsted’s subsidiary Optimus Wind Limited has applied to the UK Marine Management Organisation for a marine license to undertake offshore unexploded ordnance (UXO) inspection and clearance works for the Hornsea Project Two offshore wind farm. In preparation for offshore construction which is due to commence in 2020, there is a requirement to carry out inspections and, […]

  • 5 July 2023
    Infrastructure, Vessels

    A keel laying ceremony was held for Cadeler’s first X-class wind turbine installation vessel at COSCO Shipping Heavy Industries’ shipyard in Qidong, China. The vessel is the first of two that Cadeler has ordered from COSCO Shipping Heavy Industry under a contract signed with the company in June 2021. The vessels will be equipped with […]

  • 11 September 2019
    Contracts & Tenders, Wind Farm Update

    Offshore foundations manufacturer EEW has signed a contract with Denmark’s ProCon Wind Energy for the electrical construction of 30 transition pieces for the Hornsea Project Two offshore wind farm. The electrical construction work will take place at EEW Offshore Structures (Britain) Ltd.’s site in the United Kingdom in the first half of 2020. ”We are extremely […]

  • 28 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK governmental agencies, conservation organisations and companies have responded positively to Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.