Search results for: hornsea two

458 results

A list of search results

  • 3 July 2020
    Vessels

    Spectrum Offshore has selected MHO-Co’s vessel MHO Grimsby to assist the construction survey support at the Hornsea Two offshore wind project. The vessel, which is equipped with special survey gear for the task, will be working on the project for the next two years, MHO-Co said. Last month, Spectrum secured a construction survey support contract […]

  • 26 April 2022
    Business & Finance, Grid Connection, Wind Farm Update

    NKT has commissioned the 220 kV HVAC export cable system connecting the 1.3 GW Hornsea Two offshore wind project to the UK grid. NKT manufactured the power cables for the project at its factory in Karlskrona, Sweden. The installation of the subsea cables was completed by the cable-laying vessel NKT Victoria. “Constructing a project of […]

  • 1 October 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has awarded the South Korean LS Cable & System with a contract to supply the onshore cable for the Hornsea Project Two offshore wind farm.

  • 14 September 2020
    Wind Farm Update

    Bladt Industries has loaded out the first six out of the 135 anode cages built for the 1.4 GW Hornsea Project Two offshore wind farm. The first six transition pieces will soon follow, Bladt Industries said. The Danish company is in charge of manufacturing and delivering 135 transition pieces for the project. The units are […]

  • 10 July 2020
    Contracts & Tenders

    UK-based wireless telecommunications provider Vilicom has been appointed to provide a mobile network during the construction, development and deployment of Ørsted’s Hornsea Two offshore wind project in the UK. Vilicom’s communication infrastructure will be built and tested in the UK prior to installation on the 1.4 GW wind farm. According to the company, the fully […]

  • 28 September 2020
    Wind Farm Update

    DEME Group’s jack-up vessel Innovation is set to begin the monopile installation at the Hornsea Two offshore wind project next month. In total, 165 monopiles and transition pieces will be installed at the offshore site in the UK in preparation for the Siemens Gamesa 8.4 MW turbines. With a height from sea level to blade […]

  • 25 February 2020
    Contracts & Tenders, Grid Connection

    Siemens Energy has selected Fussey Engineering to supply and install steel framework and cladding at the National Grid 400kV substation site adjacent to the Hornsea Two offshore wind project.

  • 6 August 2021
    Grid Connection, Ports & Logistics, Wind Farm Update

    The topsides for the Hornsea Two offshore substation and the reactive compensation station have been loaded onto Guangzhou Salvage’s vessel Hua Hai Long at Sembawang, Singapore. The topsides will soon be ready to start their journey to the UK, Guangzhou Salvage said. The topsides were manufactured by Sembcorp Marine. The jacket foundations for the offshore […]

  • 11 March 2020
    Contracts & Tenders, Wind Farm Update

    The Buss Terminal Eemshaven, in the Netherlands, has secured a contract to serve as a base port for installing the foundations of the Hornsea Two offshore wind project. Under the deal secured with DEME Offshore, the Buss Terminal is responsible for the handling, storage and terminal logistics of the 165 monopiles and transition pieces at […]

  • 26 June 2019
    Wind Farm Update

    Ørsted has placed an order with the Rostock-based EEW Special Pipe Constructions GmbH for 30 transition pieces for the 1,386MW Hornsea Two offshore wind project in the UK. The transition pieces will be manufactured at EEW Offshore Structures Britain (EEW OSB) in Teesside, the UK. Production will start in September 2019. According to Sascha Hofmeister, Managing […]

  • 16 August 2016

    RenewableUK has welcomed the news that DONG Energy’s Hornsea Two offshore wind farm has gained planning consent from the UK Business and Energy Secretary, Greg Clark.  Wind power is currently delivering over 12% of the UK’s electricity, which is expected to increase to 20% by 2020 with offshore wind alone providing 10%. Offshore wind’s costs have […]

  • 4 December 2017
    Contracts & Tenders, Wind Farm Update

    Ørsted has hired Semco Maritime as Electrical Engineering Consultant (EEC) to develop electrical and mechanical basic engineering design of the 1.4GW offshore substation and the reactive compensation station for Hornsea Project Two.

  • 16 August 2021
    Grid Connection, Wind Farm Update

    The Hornsea Two offshore substation (OSS) and the reactive compensation station (RCS) topsides have left the Sembcorp Marine Admiralty Yard in Singapore and are en route to the UK, Sembcorp Marine said. The two topsides departed on 15 August and are expected to reach their destination at the end of September for the integration with […]

  • 7 May 2019
    Business & Finance

    Ørsted A/S plans to issue green senior bonds in the UK-market to finance its green growth ambition towards 2025 including the investments in 1,386MW Hornsea Two offshore wind farm. With the bond issuance, Ørsted targets a multi-tranche senior unsecured GBP-Sterling green bond, subject to market conditions. Tranches may include benchmark 8-year and 14-year nominal fixed […]

  • 21 October 2020
    Business & Finance, Vessels, Wind Farm Update

    Cadeler, formerly known as Swire Blue Ocean, is ready to send its Pacific Orca vessel in early 2021 to support foundation installation at the Hornsea Two offshore wind farm in the UK. The company has been subcontracted by DEME to deliver a vessel which will support the installation of the wind farm’s 165 monopile foundations, and Pacific […]

  • 14 August 2020
    Wind Farm Update

    The jacket foundations for the Hornsea Two offshore substation and reactive compensation station (RCS) have set sail from Indonesia towards the project site in the UK. The structures weighing over 10,000 tons departed Batam on 13 August onboard heavy transport vessel (HTV) Big Lift Barentsz. The journey will take approximately 50 days via the Indian […]

  • 28 March 2022
    Business & Finance, Wind Farm Update

    Ørsted has signed an agreement to divest 50 per cent of its 1.3 GW Hornsea Two offshore wind farm in the UK to a consortium comprising AXA IM Alts and Crédit Agricole Assurances for GBP 3 billion (approximately EUR 3.6 billion). The transaction is expected to close in the second half of 2022, once the […]

  • 8 June 2021
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Sea Installer has arrived at the Port of Hull in the UK to load the first set of turbine components to be installed on the 1,386 MW Hornsea Two offshore wind farm. Sea Installer is joining her sister vessel Sea Challenger on the project which has already installed the first batch of […]

  • 15 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK’s Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved an increase in the total works area for the Hornsea Project Two onshore substation site.

  • 9 August 2021
    Ports & Logistics, Wind Farm Update

    The Rostock-based EEW Special Pipe Constructions GmbH has loaded out the last five monopiles for Ørsted’s Hornsea Two offshore wind farm. The final five monopiles were loaded out at EEW SPC’s quay on 30 July. In the past eleven months, a total of 165 monopiles was loaded for the project by two self-geared vessels. The […]

  • 8 October 2021
    Wind Farm Update

    DEME Offshore has installed 100 turbines on the Hornsea Two offshore wind farm, with 65 more of Siemens Gamesa 8.4 MW units left to be put into place. The jack-up vessel Sea Challenger installed the first wind turbine at the end of May and in less than three months later the project had 50 wind turbines installed […]

  • 11 February 2021
    Wind Farm Update

    Around 20 per cent of foundations has been installed at the 1.4 GW Hornsea Two, which is soon to become the world’s largest offshore wind farm, Ørsted said. The export cable installation works are on schedule and turbine installation is set to commence in the second half of this year, the project’s owner and developer […]

  • 21 October 2021
    Wind Farm Update

    Ørsted’s 1,386 MW Hornsea Two offshore wind farm, soon to be the world’s largest, has reached several significant construction milestones, with more to come in the coming days. All of the wind farm’s turbine foundations have now been installed, as well as the project’s offshore substation at the North Sea site 89 kilometres off the […]

  • 5 August 2020
    Wind Farm Update

    Per Aarsleff A/S has produced 89 out of the 165 concrete working platforms (CWPs) for Ørsted’s 1.4 GW Hornsea Project Two offshore wind farm. The CWPs are being built at Per Aarsleff’s concrete precast factory in Poland, Aarsleff BIZ, for Bladt Industries and EEW OSB, which are producing 135 and 30 transition pieces for the […]

  • 12 September 2018
    Business & Finance

    Ørsted is holding a supply chain event for the Hornsea Project Two offshore wind project in the UK North Sea.

  • 2 April 2019
    Contracts & Tenders

    Ørsted has contracted AMS Trenchless Specialists to conduct part of the onshore cable works for the Hornsea Project Two offshore wind farm in the UK. AMS Trenchless Specialists will conduct Horizontal Directional Drilling (HDD) at the landfall site in Horseshoe Point where the offshore cables meet the onshore cables under the more than GBP 1 million worth contract. Using […]