  • 7 September 2020
    Wind Farm Update

    Van Oord has installed the first of the 89 monopiles at the Windpark Fryslân in the IJsselmeer Lake, the Netherlands. The remaining 88 foundations are expected to be installed by January 2021, Windpark Fryslân said. Unique Installation Approach – Sarens Soccer Pitch The 382.7 MW Windpark Fryslân is being built in the Frisian part of the IJsselmeer […]

  • 10 January 2020
    Ports & Logistics, Wind Farm Update

    Siemens Gamesa has selected TMA Logistics to provide the storage and transshipment of wind turbines for the Windpark Fryslân nearshore wind farm project at its terminal in the Port of Amsterdam. Located in the IJsselmeer and some six kilometres off the Frisian coast, the 382.7MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3MW wind turbines […]

  • 4 January 2021
    Wind Farm Update

    Van Oord has started installing inter-array cables at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake, the Netherlands. The installation work started in December, as planned, a spokesperson for Windpark Fryslân said. The inter-array cables will first come to shore at the wind farm’s own transformer station at Breezanddijk on the artificial island […]

  • 20 December 2019
    Contracts & Tenders, Wind Farm Update

    Van Oord has selected Tekmar Energy’s Cable Protection System (CPS) TekLink® Mechanical Latch for the Windpark Fryslân nearshore wind farm in the Netherlands. The 382.7MW Windpark Fryslân comprises 89 Siemens Gamesa 4.3MW wind turbines to be installed in the IJsselmeer some six kilometers off the Frisian coast. Tekmar Energy is providing 167 cable protection systems […]

  • 30 October 2020
    Contracts & Tenders, Grid Connection

    Visser & Smit Hanab has secured a contract by Van Oord to perform inter-array cable termination and testing work at the Windpark Fryslân nearshore wind farm in the Netherlands. The routing, termination and testing activities will commence as soon as the cable installation starts. Visser & Smit Hanab is also in charge of installing the […]

  • 17 January 2020
    Contracts & Tenders

    Bijlsma Constructies has won a contract to deliver 89 internal platforms for the Windpark Fryslân nearshore wind farm project in the Netherlands. The Dutch company will start production in March and is expected to complete all the platforms in July. Windpark Fryslân is being built by Zuiderzeewind, a consortium of Van Oord and Siemens Gamesa […]

  • 24 March 2021
    Wind Farm Update

    The first of the 89 Siemens Gamesa 4.3 MW wind turbines has been installed at Windpark Fryslân, the world’s largest wind farm in inland fresh waters. Located in the IJsselmeer Lake and some six kilometres off the Frisian coast, the Netherlands, the 382.7 MW Windpark Fryslân wind farm is being constructed by the Zuiderzeewind consortium […]

  • 10 December 2019
    Jobs & Recruitment, Wind Farm Update

    Ventolines has selected Marine Coordination Services to supply a range of support personnel for the construction phase of the 382.7MW Windpark Fryslân offshore wind farm in the Netherlands. The arrangement will include the supply of QA, QC inspectors, auditors, and client representatives. “We are glad to be able to offer our support to Windpark Fryslân,” […]

  • 1 November 2019
    Contracts & Tenders

    The operators of the Trianel Windpark Borkum and the Trianel Windpark Borkum II offshore wind farms in the German North Sea have issued a tender for the provision of the Helicopter Emergency Medical Services (HEMS). Infrastruktur Windkraftwerk Borkum, Trianel Windkraftwerk Borkum, and Trianel Windkraftwerk Borkum II are seeking rescue services in accordance with the regulatory […]

  • 4 March 2021
    Ports & Logistics, Wind Farm Update

    Spain’s Windar renovables is shipping out the first batch of pin-piles manufactured for the Saint-Brieuc offshore wind project in France. Tadarsa Logistics is assisting Windar renovables in loading out the first 15 pin-piles for the turbine jacket foundations and four pin-piles for the substation jacket foundation at the port of Avilés. The vessel and the […]

  • 21 November 2012
    Business & Finance

    SüdWestStrom Windpark GmbH &Co. KG is not buying the 400 MW offshore wind farm BARD Offshore 1. Delays in the completion of the wind farm and the modified risk assessment of offshore wind farms have led to a decision that the holding company SüdWestStrom Windpark GmbH &Co. KG and the project company SüdWestStrom StadtKraftWerk / […]

  • 15 October 2019
    Operations & Maintenance

    Deutsche Windtechnik has received an order to provide maintenance for the 32 Senvion 6.3M 152 turbines at the Trianel Windpark Borkum II wind farm in the German North Sea. The main service tasks include troubleshooting the wind turbines, including guaranteed availability, remote fault elimination, spare parts management, and logistics from Borkum or Emden. “We are […]

  • 24 May 2021
    Grid Connection, Wind Farm Update

    The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands. The inter-array cables will undergo tests in the coming days, Windpark Fryslân said. The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbines with the wind farm’s own transformer station […]

  • 19 June 2017

    Wood Group’s clean energy business, previously known as SgurrEnergy, supported Trianel Windpark Borkum II (TWB II) to financial close, as it had been appointed by Trianel Windkraftwerk Borkum II GmbH & Co. KG to act as lender’s technical adviser.

  • 17 March 2021
    Wind Farm Update

    EMS Maritime Offshore’s (EMO) VENTUSmarine control center has assumed coordination of the Trianel Windpark Borkum project in Germany. In November last year, EMO signed a five-year contract with Trianel Windpark Borkum GmbH & Co. to handle maritime, flight and emergency coordination for the project until the end of 2025. EMO currently transports personnel and freight […]

  • 30 January 2020
    Contracts & Tenders

    Van Oord has awarded Vos Prodect Innovations with a contract to deliver cable hang-off systems for the Windpark Fryslân nearshore wind project in the Netherlands.

  • 28 February 2018
    Contracts & Tenders, Wind Farm Update

    Senvion has contracted TÜV Rheinland to oversee the production of wind turbine blades for the Trianel Windpark Borkum II offshore wind farm.

  • 5 December 2019
    Wind Farm Update

    The Trianel Windpark Borkum II (TWBII) offshore wind project has reached the halfway turbine installation point as 16 out of 32 units have been erected. Jan De Nul’s jack-up vessel Taillevent installed the 16 Senvion 6.2M152 turbines in the northeastern part of the project site offshore Germany, with the installation of the remaining 16 units […]

  • 20 January 2020
    Vessels, Wind Farm Update

    Van Oord’s crane vessel Werkendam has arrived at the IJsselmeer to start working on the Windpark Fryslân nearshore wind farm project. The vessel will be involved in the construction of an artificial island off the Frisian coast, Windpark Fryslân said. With a land area of 2ha and a submerged, shallow water area of 25ha, the […]

  • 18 March 2016
    Wind Farm Update

    The Navantia-Windar joint venture has erected the first block for the first of five spar-type floating foundations for Statoil’s Hywind Scotland project.  The block weighs approximately 70t, and has a diameter of 14.4m. Five blocks with maximum weight of 800t will be assembled and moved onto the slipways for assembly of 90m long spar units and […]

  • 29 June 2018
    Grid Connection

    Jan De Nul has completed the export cable installation works at the Trianel Windpark Borkum II and the Borkum Riffgrund 2 offshore wind farms in the German North Sea.

  • 11 July 2018
    Authorities, Wind Farm Update

    The Council of State dismissed eight objections filed against the final permits for Windpark Fryslân and thus cleared the way for the construction of the project in the Frisian part of the IJsselmeer near Breezanddijk in the Netherlands.

  • 2 July 2021
    Business & Finance, Contracts & Tenders

    Navantia and Windar announced today (2 July) that they will build a factory for XXL monopiles on the grounds of the Fene shipyard in Spain after Iberdrola closed a framework agreement with the partnered companies for future offshore wind farms, valued at EUR 400 million. The framework agreement between Iberdrola and Navantia-Windar involves the manufacture […]

  • 24 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island of Borkum in Germany. Taillevent loaded the first three towers, blades […]

  • 15 November 2018
    Ports & Logistics, Wind Farm Update

    The Buss Terminal Eemshaven has received the first shipment of wind turbine tower sections for the Trianel Windpark Borkum II offshore wind project.

  • 9 November 2018
    Wind Farm Update

    27 out of the 32 monopile foundations have been installed on the 200MW Trianel Windpark Borkum II (TWB II) offshore wind farm in the German North Sea.