Search results for: seamade

1096 results

A list of search results

  • 26 March 2020
    Wind Farm Update

    The first two turbine towers destined for the SeaMade offshore wind project have arrived at the Port of Ostend, Belgium. According to Otary, the first six tower parts arrived in Belgium on 24 March from the port of Aviles in Spain onboard the special purpose vessel Rotra Vente. Over the coming months, Rotra Vente and […]

  • 13 March 2020
    Grid Connection, Wind Farm Update

    Scaldis Salvage & Marine Contractors is currently preparing for the installation of the second offshore substation at the SeaMade wind farm in Belgium. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. This second topside, which recently arrived in Vlissingen, the Netherlands, will be installed at the Seastar […]

  • 27 April 2020
    Wind Farm Update

    The first of the 58 turbine towers for the SeaMade offshore wind project has been upended at the Port of Ostend, Belgium. According to the project developer, the installation of the Siemens Gamesa 8.4 MW turbines will start on 15 June. The first tower parts arrived in Belgium in mid-March from the port of Aviles […]

  • 18 June 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Apollo has left the REBO terminal in Oostende loaded with the first set of turbine components to be installed on the 487 MW SeaMade wind farm offshore Belgium. Apollo arrived at the REBO heavy load terminal in the Port of Oostende on 14 June, after undergoing spudcan shoes extension at Damen Shiprepair […]

  • 6 April 2020
    Wind Farm Update

    Deugro has completed loading the second shipment of wind turbine towers for the SeaMade offshore wind farm at the Port of Avilés in Spain.

  • 19 November 2019
    Contracts & Tenders, Grid Connection

    JECS Offshore Services has secured a contract to provide support to Hellenic Cables during termination works on the export cables at the SeaMade offshore wind farm in Belgium. JECS Offshore will design, supply and erect the scaffolding access platforms required for technicians to prepare and position the cables and carry out the terminations of the […]

  • 27 September 2018
    Authorities, Business & Finance, Wind Farm Update

    The European Commission has approved under EU State aid rules Belgium’s support of a maximum of EUR 3.5 billion for three offshore wind projects in the Belgian North Sea.

  • 3 March 2020
    Grid Connection, Wind Farm Update

    The first of two offshore substations for the SeaMade offshore wind farm has left Engie Fabricom’s construction yard in Hoboken and is on its way towards the project site in the Belgian North Sea. The 487MW SeaMade wind farm is a combination of the 235MW Mermaid and the 252MW Seastar offshore wind projects. The 1,200t topside, […]

  • 7 January 2020
    Wind Farm Update

    DEME Group has completed the installation of 58 turbine foundations and two substation foundations at the SeaMade offshore wind project in Belgium. DEME’s jack-up vessel Innovation installed the last monopile foundation at the project site some 50km off the coast from Ostend on 2 January. According to the company, a new monopile gripper was deployed onboard […]

  • 3 August 2018
    Business & Finance

    The European Investment Bank (EIB) has agreed to provide an undisclosed amount of funding for the construction of the Seamade offshore wind farm in the Belgian North Sea.

  • 27 May 2020
    Grid Connection, Wind Farm Update

    DEME Group has completed inter-array cable laying works at the SeaMade offshore wind farm in Belgium. DEME’s DP3 cable installation vessel Living Stone laid 64 inter-array cables with a total length of 71.2km. According to the company, the vessel operated at peak production levels, laying up to three cables per day. To remind, the inter-array […]

  • 14 April 2020
    Wind Farm Update

    DEME’s cable installation vessel Living Stone has started the inter-array cabling work at the SeaMade offshore wind farm.

  • 6 November 2018
    Grid Connection, Vessels

    Seaway Heavy Lifting’s Oleg Strashnov has started installing the jacket foundation for Elia’s Offshore Switchyard Platform (OSY) in the Belgian North Sea.

  • 31 March 2020
    Contracts & Tenders, Ports & Logistics, Wind Farm Update

    Siemens Gamesa has hired Muehlhan Wind Service (MWS) to provide pre-assembly and ground logistics for the SeaMade offshore wind farm project in Belgium. Under the contract, MWS will pre-assemble 58 Siemens Gamesa 8.4MW wind turbines prior to their transportation and installation at the site located 38-50 kilometres off the coast of Oostende. The turbine pre-assembly […]

  • 28 August 2019
    Vessels

    DEME Group’s jack-up vessel Innovation is undergoing a final stage of a maintenance and repair program at the Damen Verolme yard in Rotterdam, the Netherlands. The photo shows the vessel during full height jacking trials at the yard. Following the jacking trials and final tests, Innovation will head to ”a full schedule of work”, which […]

  • 11 December 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Eneco has concluded a long-term power purchase agreement (PPA) for the SeaMade offshore wind project in Belgium.

  • 20 October 2021
    Wind Farm Update

    The 487 MW SeaMade offshore wind farm was officially inaugurated at an event in the Hippodrome in Ostend, Belgium, on Wednesday, 20 October 2021. SeaMade NV, a joint venture between Otary, Ocean Winds, and Eneco, is responsible for the simultaneous development of both the Mermaid and Seastar offshore wind farms, resulting in the largest wind […]

  • 14 May 2020
    Wind Farm Update

    Manor Renewable Energy (MRE) has signed a contract with Siemens Gamesa to provide temporary power provision during the turbine commissioning phase at the SeaMade offshore wind farm. “Following several successful European temporary power provision projects over the recent past, we are looking forward to once again working with Siemens Gamesa; it’s a combination that works,” […]

  • 14 May 2020
    Grid Connection, Operations & Maintenance, Wind Farm Update

    EDS HV Group has completed the termination and testing of the export cables at the SeaMade offshore wind farm in Belgium. The first phase of the work was completed at the Mermaid concession 54 kilometers off the coast on behalf of Hellenic Cables. EDS HV said it had secured the contract prior to the coronavirus […]

  • 4 January 2019

    Offshore WIND’s ten most read news in December 2018.

  • 3 May 2019
    Business & Finance

    Dutch offshore foundations manufacturer Sif has begun work for the SeaMade offshore wind farm in Belgium, according to the company’s latest report. Sif is responsible for producing the monopiles for the 487MW project and, in a joint venture with Smulders, for the manufacture of transition pieces. The Dutch company said it plans to begin works […]

  • 12 January 2022
    Business & Finance, Wind Farm Update

    Chemical company INEOS has signed a long-term corporate power purchase agreement (cPPA) with Eneco to source renewable electricity from SeaMade, Belgium’s largest offshore wind farm. The agreement entails the purchase and supply of over 65.5 MW of wind power over the next decade, with delivery set to begin in January 2022. This is the largest […]

  • 11 July 2023
    Wind Farm Update

    Seaway7 has completed the full engineering, procurement, construction, and installation (EPCI) cables scope on the Seagreen wind farm offshore Scotland, a joint venture project between SSE Renewables and TotalEnergies. The inter-array cable team completed the termination and testing last weekend and the trenching was completed yesterday, said Seaway7. This follows less than six weeks after […]

  • 24 October 2018
    Grid Connection, Ports & Logistics

    Heerema Fabrication Group (HFG) has loaded the jacket foundation for Elia’s Offshore SwitchYard (OSY) platform onto a barge at the Vlissingen yard.

  • 3 February 2022
    Business & Finance

    Belgian materials technology and recycling group Umicore will buy electricity generated by 28 MW of offshore wind capacity at Engie’s offshore wind farm in the Belgian sector of the North Sea. Umicore informed on the signing of a Power Purchase Agreement (PPA) with Engie on 3 February. Under the agreement, Engie will be providing Umicore […]

  • 7 November 2018
    Grid Connection

    Belgian utility Elia has shared a video showing the installation of the jacket foundation for the Offshore Switchyard Platform (OSY) in the Belgian North Sea.