Search results for: windanker

535 results

A list of search results

  • 10 May 2016
    Vessels, Wind Farm Update

    Dutch maritime contractor Van Oord installed the 50th turbine at the 600MW Gemini offshore wind farm off the coast of the Netherlands over the last weekend, according to Gemini Windpark.  The installation of the 150 4MW Siemens turbines started in February 2016 when Van Oord’s offshore installation vessel, Aeolus, transported the first six turbines from the […]

  • 2 March 2017

    Siem Offshore Contractors has awarded Seaproof Solutions with a contract for the design and supply of cable protection systems for the inter-array subsea cables at the Trianel Windpark Borkum II offshore wind farm in Germany.

  • 24 August 2011
    Operations & Maintenance, Wind Farm Update

      Nexans, a worldwide leading expert in the cable industry, has been awarded a contract by the project developer Offshore-Windpark RIFFGAT GmbH & Co. KG, which is owned by Enova and EWE ENERGIE, to supply and install the infield submarine power cables and ancillary equipment for the Riffgat offshore wind farm currently under construction 15 […]

  • 6 May 2012

    Tim Kittelhake, up to April 30, 2012 General Manager of Global Tech 1, will take over the general management of Global Tech 1. With this position, Kittelhake assumes the responsibility for the 400 MW Offshore Wind Park MEG 1. With this, Kittelhake takes over the responsibility for a further important milestone in the successful implementation […]

  • 16 August 2015

    ABB Installs World’s Most Powerful Substation ABB has installed DolWin beta, the world’s most powerful offshore converter station in the North Sea. Vattenfall Hiring for Horns Rev 3 Installation Vattenfall, a Swedish power company, is seeking a contractor for the transport and installation of turbines at Horns Rev 3. First Gemini Foundations Grouted with MasterFlow […]

  • 22 May 2012

    Weighing nearly 570 tonnes, the first monopile for the offshore wind park project Meerwind Süd / Ost has left the AMBAU plant in Cuxhaven. AMBAU is producing 80 foundation sets for the wind park, comprising monopiles and transition pieces, on behalf of Bremerhaven-based WindMW GmbH. The monopiles for the 80 offshore wind energy units of […]

  • 29 August 2019
    R&D

    German Federal Ministry for Economic Affairs and Energy (BMWi) is looking for an operator for the FINO 1 research platform in the German North Sea. BMWi is extending the operational life of the FINO1 platform until 31 July 2023, with an optional one-year extension. The future operator must ensure the continuous and trouble-free operation as well […]

  • 8 July 2016

    Heavy-lifting specialists ALE today reported that it had performed the first load-out of jacket foundations for the Wikinger offshore wind farm. The first jacket, weighing 625t, was loaded-out using self-propelled modular transporters (SPMTs) and a CC8800 crawler crane in Ferrol, Spain. ALE has been contracted to perform a total of 58 land transportations (two per jacket) using SPMTs and […]

  • 6 September 2017
    Contracts & Tenders, Vessels, Wind Farm Update

    Lamprell Energy Ltd. has awarded Dockwise, a wholly-owned subsidiary of Royal Boskalis Westminster N.V., with a contract to transport jacket foundations for the 714MW East Anglia ONE offshore wind farm from the United Arab Emirates to the Netherlands. 

  • 10 January 2017
    Contracts & Tenders, Wind Farm Update

    Siemens has chosen the Navantia-Windar joint venture for the supply of three-legged jacket foundations and accompanying piles for four 7MW offshore wind turbines to be installed as part of the Nissum Bredning Vind demo project in Denmark. The Spanish companies will carry out the project in parallel to the construction of 42 jackets for East Anglia One at […]

  • 28 October 2015
    Vessels

    Uptime International has entered into three new contracts for motion compensated gangways during summertime. One of the involved companies in this transactions is the Dutch company C-bed. C-bed will mount the gangway inclusive a stepless adjustable pedestal on their new build accommodation vessel “M/S Wind Innovation” which is customized to operate as walk to work […]

  • 30 June 2016

    STX France has cut the first steel for the Arkona electrical offshore substation, thus launching the first production works for the project after a year of detailed design phase. The structure will be built by the end of 2016, followed by upending and painting, with hundred people mobilized for the works. Under the EPCI contract signed with AWE Arkona Windpark Entwicklungs GmbH (50% E.ON and […]

  • 1 November 2017
    Grid Connection, Wind Farm Update

    Norddeutsche Seekabelwerke GmbH (NSW) has contracted Vos Prodect Innovations BV to design and deliver inter-array cable hang-off systems for the Trianel Windpark Borkum II (TWB II) offshore wind project in the German North Sea.

  • 9 July 2014

    Currently two offshore platforms are protruding from the 426 x 89 m dimensioned dry dock No. 8 in Kiel-Gaarden. With the lately finished sixth and last level the electric power substation for the offshore-windpark EnBW Baltic 2 can clearly be recognized from the other side of the Kiel Fjord. While the yard has already fulfilled its building part here […]

  • 14 March 2018
    Wind Farm Update

    On 12 March, SeaTerra detonated the last buoyant mine found at the Trianel Windpark Borkum II (TWB II) site as part of an unexploded ordnance (UXO) campaign that had been running over the recent months, thus marking the completion of the project.

  • 24 May 2019
    Vessels

    Norwegian ship operator Olympic Subsea has entered into an agreement with Adwen GmbH, a subsidiary of Siemens Gamesa, for the vessel Olympic Orion. The contract period is firm for six months with further options. The contract commencement is in the second quarter of 2019. Olympic Subsea did not disclose any further contract details. ”We see it […]

  • 14 February 2018
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Jan De Nul has won a contract by Senvion for the installation of wind turbine generators (WTG) at the 203MW Trianel Borkum II (TWB II) offshore wind farm in Germany.

  • 27 July 2016
    Wind Farm Update

    Heavy transportation and lifting contractor ALE loaded-out the first of two 3,000-tonne jackets built for the Wikinger offshore substations, in Cadiz, Spain, last week. The jacket was built by Navantia shipyard in Puerto Real for Iberdrola’s 350MW Wikinger offshore wind farm currently under construction in the German Baltic Sea. In December 2014, Iberdrola awarded a EUR 160 million contract to […]

  • 15 February 2018
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    RollDock is currently transporting the transition pieces (TPs) for the Merkur offshore wind farm from Aviles, Spain, to the Buss Orange Blue Terminal in the Eemshaven port, the Netherlands.

  • 16 April 2021
    Wind Farm Update

    The first batch of foundation components for the Saint-Brieuc offshore wind project has arrived from France to Navantia’s Fene shipyard in Spain for final assembly. The vessel BBC Belem left the port of Brest, France, on 2 April carrying the components for two jacket foundations set to be installed at the French 496 MW project. […]

  • 13 September 2012
    Technology

    Mita-Teknik will be presenting new additions to their already extensive product portfolio at HUSUM WindEnergy 2012 at booth 7A11. Through several product seminars held at their booth, new insights to the company’s latest advances in Making Wind Competitive will be granted. The company will present the new Retrofit Concept, which focuses on prolonging the life-time […]

  • 11 July 2012
    Operations & Maintenance

    On 22 June 2012, Braveheart Shipping baptized its Javelin 22.22 “Guardian”. Guardian is the first Javelin built and developed by Javelin International by order of Braveheart Shipping. With this ship, especially being used for survey activities, Braveheart is further expanding its fleet and consequently extending its working area to Sea Area A3. The ship is […]

  • 24 August 2011
    R&D

      STX announces that it has commissioned the first offshore direct drive wind turbine and has completed a successful test run on Monday August 1st. STX’s first offshore direct drive wind turbine was installed under the project called ‘The demonstrative offshore windpark of Jeju island’. It sets a starting point for the future of the […]

  • 13 July 2023
    Contracts & Tenders, Operations & Maintenance

    SeaRenergy has been awarded a contract by Iberdrola to provide inspection services, maintenance, and repair works on monopiles and transition pieces (TPs) as well as client representatives for all phases of the installation of the Baltic Eagle offshore wind farm in Germany. SeaRenergy’s client representatives are involved in the installation of the monopiles and TPs, […]

  • 5 January 2018
    Business & Finance, Contracts & Tenders

    German wind turbine manufacturer Senvion reported a firm order intake of EUR 306 million in its offshore wind segment in 2017, compared to no firm orders recorded a year earlier.

  • 8 February 2013

    The load-out of the topside for the Riffgat offshore substation was successfully completed. This is an important milestone in this project, which enables our customer to supply renewable energy to its customers before this summer. Offshore-Windpark RIFFGAT GmbH & Co. KG, a company owned by EWE Energie AG and Enova Energiesysteme GmbH & Co KG, […]