579 results found for 'windanker'

579 results found for 'windanker'
Order results by

A list of search results

  • 10 March 2020
    Contracts & Tenders

    EWE Offshore Service & Solutions (OSS) has awarded contracts for the provision of helicopter services from Emden, Germany, to offshore wind farms. The selected parties will be responsible for the execution of helicopter transports for personnel and material from Emden to offshore wind projects, with possible stopovers on Borkum. Northern HeliCopter GmbH will provide a […]

  • 9 October 2015

    The Dutch National Museum of Dredging has opened an exhibition titled Offshore wind – Challenge at sea, which will run from October 8, 2015 to March 14, 2016. The exhibition is made possible through the contribution of photographs, films, models and information from Eneco, Van Oord, Boskalis, ECN, Royal IHC, Royal Dirkzwager VBMS, Sif, Wind Cats and Jan […]

  • 15 February 2016
    Vessels

    On 12 February, offshore wind installation vessel Aeolus left the Port of Esbjerg for the Gemini offshore wind farm, carrying six turbines to be installed at the site.  According to vessel’s AIS, the Aeolus has reached its destination, and is now in the company of Havila Phoenix and Acta Orion, which are also working at the site. The last of 150 […]

  • 30 March 2016
    Technology

    Bachmann Monitoring’s condition monitoring system (CMS) is covering 22 percent of German offshore wind turbines installed in 2015. The company is planning to equip further projects in 2016, said Ulrich Oertel, head of the Monitoring Technologies Development department at Bachmann. “This includes, for example, the extension of the conventional power train CMS and structure monitoring.” All 80 turbines at the Global Tech I […]

  • 20 November 2014
    Grid Connection, Technology, Wind Farm Update

    The Dutch grid operator TenneT has completed the last technical tests for the cable connection of Noordoostpolder wind farms. The work on the connection system included the construction of a high voltage substation at Westermeerdijk, the construction of a 110kV cable line that goes from Westermeerdijk via Emmeloord to Ens, adaptation of a high voltage substation Emmeloord Zuidervaart and […]

  • 4 March 2020
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Blue Tern is on its way to the Trianel Windpark Borkum II (TWBII) offshore wind farm loaded with the first batch of turbine components. Blue Tern was contracted to finish installing the remaining 11 Senvion turbines on the project offshore Germany, replacing Jan De Nul’s Taillevent which is reportedly on its way to start a […]

  • 13 June 2022
    Contracts & Tenders, Wind Farm Update

    Haizea Breizh, the French subsidiary of the Spanish wind turbine tower producer Haizea Wind Group, has contracted SPIE Industrie & Tertiaire for the assembly of internal components on the 62 towers for the Saint-Brieuc offshore wind farm at Haizea’s facilities in the Port of Brest. The wind turbine towers will be manufactured and painted at […]

  • 8 June 2010
    Business & Finance

    Ballast Nedam Offshore has signed a contract with Walney (UK) Offshore Windfarms Ltd (a joint venture between DONG Energy of Denmark and… [mappress] Source: ballast-nedam, June 08, 2010;

  • 22 May 2012

    Weighing nearly 570 tonnes, the first monopile for the offshore wind park project Meerwind Süd / Ost has left the AMBAU plant in Cuxhaven. AMBAU is producing 80 foundation sets for the wind park, comprising monopiles and transition pieces, on behalf of Bremerhaven-based WindMW GmbH. The monopiles for the 80 offshore wind energy units of […]

  • 16 August 2015

    ABB Installs World’s Most Powerful Substation ABB has installed DolWin beta, the world’s most powerful offshore converter station in the North Sea. Vattenfall Hiring for Horns Rev 3 Installation Vattenfall, a Swedish power company, is seeking a contractor for the transport and installation of turbines at Horns Rev 3. First Gemini Foundations Grouted with MasterFlow […]

  • 24 October 2011

    After a mere 17 weeks, Holland Shipyards has delivered offshore accommodation vessel “Vivaldi” to her owner Wagenborg Offshore BV. During a short ceremony, held on Holland Shipyards’ premises, an approximate 400 people witnessed the delivery from Holland Shipyards BV, represented by Mr. Cor Hoogendoorn, director and owner, to Mr. Johan Adriaanse, director of Wagenborg Offshore […]

  • 18 June 2015

    The joint venture Navantia-Windar has been awarded by Statoil’s subsidiary Hywind Scotland Ltd, the supply of 5 spar-type floating foundations for 6 MW turbines. This will be the world’s first commercial floating test park. Each foundation has a displacement of approximately 3,500 tonnes, dimensions approximately 90 meters x 14.5 meters diameter. The construction shall take […]

  • 28 October 2014
    Authorities, Grid Connection, Wind Farm Update

    In its first allocation of connection capacity process for wind farms at sea, the Federal Network Agency (BNA) has reviewed applications for capacity allocation process.  Eleven applications from operators of wind farms at sea were submitted by October 1, 2014. Eight of them were approved. Three were rejected because the application was not complete or the wind farm is located in […]

  • 4 May 2017
    Wind Farm Update

    Statoil has started assembling the Siemens 6MW turbines for the 30MW Hywind Scotland floating wind farm at the assembly base in Stord, Norway.

  • 3 July 2023
    Contracts & Tenders, Grid Connection, Wind Farm Update

    The PGE and Ørsted joint venture has signed contracts with Navantia-Windar and Orient Cable (NBO) for delivery of foundations and array cables for Baltica 2, which is the first stage of the Baltic Offshore Wind Farm in the Polish Baltic Sea. Navantia-Windar will be supplying monopile foundations, the largest exceeding 100 metres and weighing over […]

  • 11 July 2012
    Operations & Maintenance

    On 22 June 2012, Braveheart Shipping baptized its Javelin 22.22 “Guardian”. Guardian is the first Javelin built and developed by Javelin International by order of Braveheart Shipping. With this ship, especially being used for survey activities, Braveheart is further expanding its fleet and consequently extending its working area to Sea Area A3. The ship is […]

  • 1 November 2017
    Grid Connection, Wind Farm Update

    Norddeutsche Seekabelwerke GmbH (NSW) has contracted Vos Prodect Innovations BV to design and deliver inter-array cable hang-off systems for the Trianel Windpark Borkum II (TWB II) offshore wind project in the German North Sea.

  • 30 June 2016

    STX France has cut the first steel for the Arkona electrical offshore substation, thus launching the first production works for the project after a year of detailed design phase. The structure will be built by the end of 2016, followed by upending and painting, with hundred people mobilized for the works. Under the EPCI contract signed with AWE Arkona Windpark Entwicklungs GmbH (50% E.ON and […]

  • 24 August 2011
    Operations & Maintenance, Wind Farm Update

      Nexans, a worldwide leading expert in the cable industry, has been awarded a contract by the project developer Offshore-Windpark RIFFGAT GmbH & Co. KG, which is owned by Enova and EWE ENERGIE, to supply and install the infield submarine power cables and ancillary equipment for the Riffgat offshore wind farm currently under construction 15 […]

  • 2 March 2017

    Siem Offshore Contractors has awarded Seaproof Solutions with a contract for the design and supply of cable protection systems for the inter-array subsea cables at the Trianel Windpark Borkum II offshore wind farm in Germany.

  • 6 May 2012

    Tim Kittelhake, up to April 30, 2012 General Manager of Global Tech 1, will take over the general management of Global Tech 1. With this position, Kittelhake assumes the responsibility for the 400 MW Offshore Wind Park MEG 1. With this, Kittelhake takes over the responsibility for a further important milestone in the successful implementation […]

  • 13 September 2012
    Technology

    Mita-Teknik will be presenting new additions to their already extensive product portfolio at HUSUM WindEnergy 2012 at booth 7A11. Through several product seminars held at their booth, new insights to the company’s latest advances in Making Wind Competitive will be granted. The company will present the new Retrofit Concept, which focuses on prolonging the life-time […]

  • 14 March 2018
    Wind Farm Update

    On 12 March, SeaTerra detonated the last buoyant mine found at the Trianel Windpark Borkum II (TWB II) site as part of an unexploded ordnance (UXO) campaign that had been running over the recent months, thus marking the completion of the project.

  • 26 March 2020
    Contracts & Tenders

    EWE Offshore Service & Solutions (OSS) has awarded Reederei Norden–Frisia with a contract to provide crew transfer services for offshore wind projects in Germany. The contractor is in charge of providing transport for personnel and material from the base port in Borkum and the Riffgat and Alpha Ventus offshore wind farms, and possibly other projects. […]

  • 16 July 2020
    Contracts & Tenders, Operations & Maintenance

    Siemens Gamesa will service the offshore wind turbines at the Trianel Windpark Borkum II (TWB II) in Germany, which comprises 32 Senvion 6.33-MW turbines. The contract, signed in late June, is effective as of 1 August and covers full scope maintenance for five years, including extension options. The operational base for the service campaigns will […]

  • 10 January 2017
    Contracts & Tenders, Wind Farm Update

    Siemens has chosen the Navantia-Windar joint venture for the supply of three-legged jacket foundations and accompanying piles for four 7MW offshore wind turbines to be installed as part of the Nissum Bredning Vind demo project in Denmark. The Spanish companies will carry out the project in parallel to the construction of 42 jackets for East Anglia One at […]