  • 13 May 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted and TotalEnergies have joined forces to jointly submit bids for the two Dutch offshore wind tenders, Hollandse Kust West VI and VII, with the aim to achieve net positive impact on biodiversity and the Dutch energy system. The Hollandse Kust West (Holland Coast West) wind farms are located approximately 53 kilometres off the Dutch […]

  • 29 June 2022
    Business & Finance, R&D, Technology, Wind Farm Update

    A consortium of sellers, including Van Oord, has sold its shares in the Borssele V wind farm to Octopus Energy Generation, one of Europe’s largest investors in renewables. According to Van Oord, the sale confirms the success of innovations demonstrated in Borssele V, including the world’s first submerged slip joint, a new method for securing […]

  • 11 August 2022
    Business & Finance

    The world’s leading offshore wind developer Ørsted has increased its full-year operating profit (EBITDA) guidance and gross investment guidance following the release of the results for the second quarter of the Fiscal Year 2022. The company’s EBITDA for the first half of the year amounted to DKK 13.044 billion (EUR 1.75 billion), in line with […]

  • 3 August 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Octopus Energy Generation, through a joint venture with GLIL Infrastructure, has agreed to acquire a 12.5 per cent stake in the 1.2 GW Hornsea One offshore wind farm from Global Infrastructure Partners (GIP) for a total cash consideration of GBP 400 million (approximately EUR 480 million). Octopus Energy Generation’s fund management team made a GBP […]

  • 12 November 2021
    Business & Finance, Wind Farm Update

    Ørsted has signed a EUR 175 million, 8-year loan agreement with the Nordic Investment Bank (NIB) for co-financing its investment in the Borssele 1 & 2 offshore wind farm in the Netherlands. Together with the loan agreement closed with the European Investment Bank (EIB) on 6 September, the intended long-term financing of Ørsted’s investment in […]

  • 28 October 2021
    Wind Farm Update

    One of the turbines at the Borssele 1 & 2 offshore wind farm in the Netherlands has malfunctioned, which subsequently led to a fire in the unit’s nacelle. No employees were present when the fire broke out and no one was injured, Ørsted said on 27 October, adding that the wind turbine manufacturer Siemens Gamesa […]

  • 3 November 2021
    Business & Finance

    Ørsted has reported a 43 per cent increase in revenue in its Offshore segment for the third quarter and a 32 per cent increase for the first nine months of this year, both compared to the same periods of 2020. While the company’s operating profit (EBITDA) in the Offshore segment halved in the third quarter […]

  • 6 July 2017
    Business & Finance, Operations & Maintenance, Technology, Wind Farm Update

    Siemens Gamesa and DONG Energy have signed an agreement for the supply and maintenance of 94 8MW turbines at the 752MW Borssele 1 and 2 offshore wind farms being developed in Dutch waters.

  • 27 November 2020
    Wind Farm Update

    Ørsted’s first offshore wind farm in the Netherlands, Borssele 1 & 2, has been fully commissioned. Located 22 kilometres off the coast of the province of Zeeland, the 752 MW project has now become the largest offshore wind farm in the Netherlands and the second largest operating offshore wind farm in the world, providing enough […]

  • 29 April 2020
    Wind Farm Update

    Ørsted’s Borssele 1 & 2 offshore wind farm has delivered first power to the Dutch grid. According to the Danish company, the first Siemens Gamesa 8 MW turbine began producing electricity on 28 April. “This is a big milestone for Borssele 1 & 2. Ørsted is doing its utmost to allow the construction of the […]

  • 6 September 2021
    Wind Farm Update

    Ørsted is set to officially open the Borssele 1 & 2 offshore wind farm today (6 September), after postponing the project’s inauguration a number of times due to COVID-19. The developer of the 752 MW offshore wind farm in the Netherlands, which has been operational since the fourth quarter of 2020, will also celebrate the […]

  • 10 April 2020
    Wind Farm Update

    DEME has installed half of the 94 monopile foundations at the Borssele 1+2 offshore wind farm site.

  • 28 May 2019
    Wind Farm Update

    EEW Offshore Structures Britain has produced the first transition piece for the Borssele 1&2 offshore wind farm in the Dutch North Sea. The Teesside-based company rolled out the first of 35 transition pieces destined for Ørsted’s Borssele 1&2 project at the beginning of April. EEW SPC, the parent company of EEW OSB, is in charge of manufacturing 47 monopiles […]

  • 3 December 2019
    Wind Farm Update

    SAL Heavy Lift’s multi-purpose cargo ship Svenja has arrived at the Redcar Bulk Terminal, the UK, to pick up the third batch of transition pieces for the Borssele 1+2 offshore wind project. Svenja is picking up six transition pieces, which were produced by EEW Offshore Structures Britain (OSB) and barged down to the Redcar terminal […]

  • 7 April 2021
    Business & Finance, Wind Farm Update

    Ørsted has signed an agreement with Norges Bank Investment Management (NBIM) to divest a 50% ownership share in its Borssele 1 & 2 offshore wind farm in the Netherlands. As part of the deal, Ørsted will continue to provide long-term operations and maintenance services from its O&M base at the Port of Vlissingen, as well as provide […]

  • 30 May 2018
    Grid Connection, Wind Farm Update

    Work on the jacket foundation for the 700MW Borssele Alpha offshore transformer station is in full swing at HSM Offshore’s yard in Schiedam, the Netherlands, as this photo shared by Ørsted shows.

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 2 November 2018
    Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    Ørsted has selected ERSG to supply temporary specialist staff for the Borssele 1+2 offshore wind project in the Dutch North Sea.

  • 25 August 2020
    Vessels, Wind Farm Update

    Sea Challenger has left the port of Esbjerg with one of the last batches of turbines for the Borssele 1 & 2 offshore wind farm. DEME’s vessel is working in tandem with its sister vessel Sea Installer on the installation of 94 Siemens Gamesa 8 MW turbines at the site in the Dutch part of […]

  • 29 November 2018
    Contracts & Tenders

    Ørsted has awarded Atlas Professionals with a contract to supply personnel for the Borssele 1 & 2 offshore wind farm in the Netherlands.

  • 4 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has completed the installation of the 94 monopile foundations at the Borssele 1 & 2 offshore wind project. The installation, which began in mid-January in the Dutch North Sea, was completed on time despite the COVID-19 crisis, DEME said. Sif provided 47 monopiles for the project and EEW SPC, the parent […]

  • 6 August 2020
    Business & Finance, Wind Farm Update

    The European Investment Bank (EIB) has approved a EUR 500 million financing for the Borssele 1 & 2 offshore wind project in the Netherlands. At the beginning of the year, Ørsted applied for a loan with the EIB which will finance the construction and the operation of the 752 MW wind farm. The estimated value […]

  • 1 May 2020
    Operations & Maintenance

    NHV Group has started carrying out its helicopter services for the Borssele 1 & 2 offshore wind farm in the Netherlands. The flights depart from NHV’s recently installed base in Arnemuiden, Midden-Zeeland, to the project site located 23km from Westkapelle. The company stated it had taken delivery of a new H145 aircraft for the Midden-Zeeland […]

  • 16 October 2018
    Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Van Oord has won a contract to install inter-array cables on Ørsted’s Borssele 1 + 2 offshore wind farm in the Dutch North Sea.

  • 23 October 2020
    Wind Farm Update

    The 752 MW Borssele 1 and 2 offshore wind farm is nearly fully commissioned with the last of the turbines currently undergoing tests before they start feeding the electricity to the Dutch grid. Once fully commissioned, the 94-turbine wind farm will surpass the 600 MW Gemini to become the largest operating offshore wind farm in […]

  • 30 January 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has installed 13 of the 94 monopile foundations on the 752MW Borssele 1&2 offshore wind farm in the Dutch North Sea, Ørsted said. Innovation is loading the monopiles and transition pieces at Sif’s Maasvlakte 2 facility before transporting and installing them at the site located some 22 kilometres off the […]