  • 4 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has completed the installation of the 94 monopile foundations at the Borssele 1 & 2 offshore wind project. The installation, which began in mid-January in the Dutch North Sea, was completed on time despite the COVID-19 crisis, DEME said. Sif provided 47 monopiles for the project and EEW SPC, the parent […]

  • 12 August 2020
    Wind Farm Update

    78 out of 94 Siemens Gamesa 8 MW turbines have been installed at the Borssele 1 & 2 offshore wind project in the Netherlands. DEME’s jack-up tandem Sea Installer and Sea Challenger are in charge of installing the turbines at the site located 22km off the coast of the province of Zeeland. According to Ørsted, the […]

  • 16 October 2018
    Contracts & Tenders, Vessels, Wind Farm Update

    Ørsted has awarded DEME’s GeoSea with a contract for the transportation and installation of 94 foundations and wind turbines at the Borssele 1 & 2 offshore wind farm in the Netherlands. 

  • 28 October 2021
    Wind Farm Update

    One of the turbines at the Borssele 1 & 2 offshore wind farm in the Netherlands has malfunctioned, which subsequently led to a fire in the unit’s nacelle. No employees were present when the fire broke out and no one was injured, Ørsted said on 27 October, adding that the wind turbine manufacturer Siemens Gamesa […]

  • 2 September 2020
    Wind Farm Update

    DEME Offshore has completed the installation of the 94 Siemens Gamesa 8 MW turbines at the Borssele 1 & 2 offshore wind farm in the Netherlands. DEME’s jack-up tandem Sea Installer and Sea Challenger were in charge of the installation at the site located 22km off the coast of the province of Zeeland. The first turbine was […]

  • 9 January 2019
    Wind Farm Update

    EEW Offshore Structures (Britain) has commenced the production of the transition pieces for the Borssele 1 & 2 offshore wind farm in the Dutch North Sea. A ceremony was held to mark the cutting of the first steel at the company’s site at Haverton Hill in the UK. EEW OSB won the contract for the production of 35 transition pieces […]

  • 13 November 2018
    Contracts & Tenders, Jobs & Recruitment, Wind Farm Update

    UK-based recruitment company Light Source People has won a contract for the supply of temporary staff for Ørsted’s Borssele 1 + 2 offshore wind project in the Netherlands.

  • 22 January 2020
    Operations & Maintenance, Wind Farm Update

    Ørsted has opened the operations & maintenance (O&M) base for the Borssele 1 + 2 offshore wind farm in Vlissingen, the Netherlands. Located in Vlissingen-Buitenhaven at the North Sea Port, the 2,100m2 facility will provide employment to 50-100 persons. All construction work and maintenance will be coordinated from the new base. The Vlissingen-based Cordeel was […]

  • 27 November 2018
    Grid Connection, Operations & Maintenance, Vessels, Wind Farm Update

    SeaZip Offshore Service’s vessel SeaZip Fix is currently working on the export cable route at the Borssele 1 & 2 offshore wind farm in the Netherlands.

  • 28 January 2020
    Contracts & Tenders, Wind Farm Update

    Ørsted has contracted Manor Renewable Energy (MRE) to provide temporary power during the turbine commissioning phase at the Borssele 1 + 2 offshore wind project.

  • 17 March 2020
    Wind Farm Update

    30 monopile foundations and 14 inter-array cables have so far been installed on the 752MW Borssele 1 + 2 offshore wind farm in the Dutch North Sea, Ørsted said. Located some 23 kilometres off the coast of Zeeland, Borssele 1 + 2 will comprise 94 Siemens Gamesa 8MW wind turbines scheduled to be operational by […]

  • 27 February 2020
    Grid Connection, Wind Farm Update

    The first inter-array cable has been installed at the Borssele 1 & 2 offshore wind project in the Netherlands. Nexans is providing up to 190km of inter-array cable rated at a maximum operating capacity of 72.5kV for the 752MW project, while Van Oord is in charge of the transport and installation. Van Oord is deploying its […]

  • 13 February 2020
    Vessels, Wind Farm Update

    DEME Offshore’s jack-up Innovation has installed 18 out of 94 monopile foundations on the 752MW Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation is loading the monopiles and the transition pieces at Sif’s facility on Maasvlakte 2 in Rotterdam and installing them at the site some 22 kilometres off the coast of […]

  • 26 April 2019
    Contracts & Tenders, Wind Farm Update

    Siemens Gamesa has selected Denmark’s Welcon to manufacture 80 turbine towers for the Borssele 1+2 offshore wind farm in the Dutch North Sea. The towers are scheduled for delivery from mid-November 2019 to mid-June 2020. This order brings Welcon’s order backlog for turbine towers to more than DKK 1 billion, the largest order backlog in the […]

  • 6 February 2020
    Business & Finance, Wind Farm Update

    Ørsted has applied for a loan with the European Investment Bank (EIB) for the 752MW Borssele 1 + 2 offshore wind farm in the Netherlands. The project will finance the construction and the operation of the wind farm. The proposed EIB financing is about EUR 500 million, and the estimated value of the project is […]

  • 30 March 2020
    Business & Finance

    Dutch offshore foundations manufacturer Sif has reached a milestone with the production of its 2,000th monopile. This special monopile was made for Ørsted’s Borssele 1&2 offshore wind farm in the Netherlands. Sif stated it is currently in the final phase of the project and is planning to complete the works in early April. The company produced its […]

  • 9 December 2019
    Wind Farm Update

    Bladt has completed the second load out of transition pieces for the Borssele 1+2 offshore wind project in the Netherlands. According to the company, the second load out of the 26m tall transition pieces took place last week. Ørsted’s Borssele 1+2 will comprise 94 Siemens Gamesa 8MW turbines installed some 23km off the coast of […]

  • 31 October 2017
    Contracts & Tenders

    DONG Energy has issued a call for tenders looking for certification bodies for the assessment of the site conditions at its Borssele 1 & 2 sites. The contracted party will evaluate whether a site conditions assessment has been carried out and documented adequately.

  • 7 July 2017
    Business & Finance, Contracts & Tenders, Grid Connection, R&D, Wind Farm Update

    TSO TenneT and DONG Energy have signed a grid connection agreement for the  Borssele 1 & 2 wind farm off the coast of the Dutch province Zeeland.

  • 8 April 2020
    Vessels, Wind Farm Update

    DEME Group’s installation vessel Sea Challenger has started loading the first wind turbine components for the Borssele 1 + 2 offshore wind farm at the Port of Esbjerg in Denmark. Located some 23 kilometres off the coast of Zeeland in the Netherlands, the 752 MW Borssele 1 + 2 wind farm will feature 94 Siemens […]

  • 28 July 2020
    Wind Farm Update

    Ørsted plans to officially commission the 752 MW Borssele 1 and 2 wind farm in the Dutch North Sea on 5 October, barring any negative effects from the COVID-19 pandemic. The wind farm comprises 94 Siemens Gamesa’s wind turbines, over two-thirds of which have now been installed at the site located 22 kilometres off the […]

  • 30 April 2019
    Grid Connection, Wind Farm Update

    HSM Offshore has loaded out the Borssele Alpha substation topside onto a barge at its yard in Schiedam, the Netherlands. The 700MW Borssele Alpha will collect the electricity generated by Ørsted’s Borssele 1 + 2 offshore wind farm and feed it into the Dutch grid. The substation’s jacket foundation was installed in August 2018. The platform […]

  • 9 January 2020
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has loaded the first set of monopiles to be installed on the Borssele 1+2 offshore wind farm in the Dutch North Sea. Innovation loaded the first set of monopiles at Sif’s facility on Maasvlakte 2 in the Port of Rotterdam. DEME is in charge of transporting and installing the 94 monopile […]

  • 1 June 2020
    Wind Farm Update

    DEME Offshore’s jack-up vessel Innovation has arrived at the Borssele 1+2 offshore wind farm in the Dutch North Sea with the final monopiles. Innovation picked up the monopiles last night at Sif Rotterdam, a spokesperson from DEME Offshore said. Sif was in charge of providing 47 monopiles for the project, with EEW SPC, the parent […]

  • 18 May 2020
    Wind Farm Update

    Haizea Wind Group has delivered the first batch of wind turbine towers produced at its facility in Spain for the Dutch Borssele 1+2 offshore wind farm. The company dispatched the tower sections from Bilbao around 13 May. The first shipment contained three bottom sections, three middle sections and two top sections, loaded onto the Rotra […]

  • 13 March 2018
    Contracts & Tenders, Wind Farm Update

    Ørsted has awarded DNV GL Danmark A/S with a contract to provide project certification services and evaluate whether the assessment of the site conditions at the Borssele 1 and 2 offshore wind zone has been carried out and documented adequately.