2304 results found for 'baltic power'

2304 results found for 'baltic power'
Order results by

A list of search results

  • 13 October 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Steelwind Nordenham has loaded out the final three monopiles for Poland’s 1.2 GW Baltic Power offshore wind project at its port facility in Germany. Over the course of 26 shipments, all 78 monopiles that the company produced were successfully delivered. The first of the monopiles was installed offshore at the beginning of the year, followed […]

  • 17 November 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first nacelles from Vestas’ Polish production facility have been installed and are getting ready for commissioning at the 1.2 GW Baltic Power offshore wind farm. The first three V236-15 MW turbines, consisting of nacelles manufactured at Vestas’ facility in Szczecin, have been installed at the site 23 kilometres off the coast of the Choczewo […]

  • 18 February 2026
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    All monopiles have been installed at the site of the 1.2 GW Baltic Power offshore wind farm, being built by a joint venture between Orlen Group and Northland Power in the Polish sector of the Baltic Sea, 23 kilometres off the coast of the Choczewo municipality. The project comprises a total of 78 foundations, 76 wind […]

  • 29 October 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Both offshore substations, the first ever in Polish waters of the Baltic Sea, have been installed at the 1.2 GW Baltic Power offshore wind farm, developed by a joint venture between ORLEN Group and Northland Power. OSS West and OSS East are located approximately 20 kilometres from the shore of Choczewo. They gather energy generated […]

  • 20 October 2025
    Business & Finance, Infrastructure

    The Danish wind turbine manufacturer, Vestas, has decided to put on hold its plans to open its biggest factory in Poland, as European demand falters, according to Reuters. In 2024, Vestas announced that it would build a second offshore wind turbine manufacturing facility in Poland. The factory, which was expected to open in 2026, would […]

  • 7 January 2026
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Polish state-owned transmission system operator (TSO), Polskie Sieci Elektroenergetyczne (PSE), has confirmed the technical readiness of the transmission infrastructure to accept power from offshore wind farms. “The new Choczewo station and the expanded Żarnowiec station, as well as the 400 kV line connecting them, are ready to transmit energy from wind farms being built in […]

  • 19 September 2025
    Equipment, Manufacturing, Supply Chain, Wind Turbines

    The first offshore wind tower section has been produced at the new Baltic Towers facility in Gdańsk, Poland. The event was attended by Minister of Climate and Environment Paulina Hennig-Kloska, Pomeranian Voivode Beata Rutkiewicz, Marshal of the Pomeranian Voivodeship Mieczysław Struk, Mayor of the City of Gdańsk Aleksandra Dulkiewicz, and representatives of the Government of […]

  • 16 October 2025
    Authorities, Fixed-Bottom, Grid Connection, Offshore Platforms, Planning & Permitting, Project Updates, Wind Farm Update

    Poland’s Orlen Neptun has secured permits for the offshore transmission infrastructure for the 1 GW Baltic East offshore wind farm. The newly secured permits allow for the installation of artificial islands, structures, facilities, and submarine cables. The 1 GW Baltic East offshore wind farm is planned to be built within the 46.E site, located close […]

  • 27 February 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Wind Farm Update

    On 25 February, the President of the Polish Energy Regulatory Office (URE) published a formal update stating that the regulator has granted a “promise of concession” for the Baltica 2 offshore wind farm, which is jointly developed by Polish utility PGE and Danish energy company Ørsted. This is the second official concession promise issued for […]

  • 18 November 2025
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting

    Orlen Group has secured the environmental permit for its 1 GW Baltic East offshore wind farm in Poland from the Regional Directorate for Environmental Protection in Gdańsk. This milestone brings the project closer to participation in the first Polish offshore wind auction, scheduled for December this year, according to the developer. “During this auction, the […]

  • 13 January 2026
    Business & Finance, Operations & Maintenance

    SeaRenergy Offshore Holding has acquired 100 per cent of the shares in hemmerschütz Solution, an offshore maintenance and repair services provider based in Germany. SeaRenergy, which took over hemmerschütz Solution on 28 November 2025, says this enables the company to complement its established offerings in engineering, marine services, QHSE and offshore experts with the direct […]

  • 13 November 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    The slower-than-expected turbine commissioning at the Hai Long offshore wind farm in Taiwan could impact Northland Power’s pre-completion revenues by approximately CAD 150 million to CAD 200 million in 2026, the company announced in its third-quarter 2025 results. Over half of the turbines are now in place at the 1 GW Hai Long offshore wind […]

  • 5 February 2026
    Business & Finance, Supply Chain, Wind Turbines

    Vestas’s offshore wind turbine order backlog was worth EUR 10.1 billion as at 31 December 2025, according to the company’s annual report, which shows that for both onshore and offshore, the turbine order backlog amounted to 31,026 MW and a value of EUR 33.2 billion at the end of the year, EUR 1.6 billion more […]

  • 11 December 2025
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    Ocean Winds, a 50-50 joint venture between EDP Renewables and ENGIE, has contracted DEME for the installation of monopile foundations, inter-array cables, and the export cable at the BC-Wind offshore wind farm in Poland. While the value of the three contracts was not disclosed, DEME noted in a press release on 10 December that they […]

  • 19 December 2025
    Authorities, Contracts & Tenders, Fixed-Bottom, Planning & Permitting

    PGE Polska Grupa Energetyczna (PGE), Orlen Group, and a consortium of Equinor and Polenergia have secured more than 3.4 GW of capacity in Poland’s first-ever offshore wind auction held on 17 December. The projects the Polish government awarded Contracts for Difference (CfDs) are Baltica 9 (PGE), Baltic East (Orlen Group), and Bałtyk 1 (Equinor and […]

  • 19 December 2025
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Four transformers and other high-voltage power equipment necessary for power transfer to the Polish national grid have been delivered to the construction site of the onshore substation for the Baltica 2 offshore wind farm, being built by a joint venture of PGE and Ørsted in the Polish Baltic Sea. The onshore infrastructure for the offshore […]

  • 1 January 2026
    Business & Finance, Supply Chain, Technology, Wind Turbines

    In offshoreWIND.biz‘s 2024 annual wind turbine overview, you could have read about the first 16 MW floating wind platform installed offshore and a 26 MW prototype under construction, both in China, and a 21 MW prototype being assembled in Europe. Wind turbine generator (WTG) technology did not stop progressing in 2025, with Chinese OEMs still leading capacity-wise, […]

  • 8 August 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Five of the 76 planned Vestas V236-15.0 MW turbines have been installed at Baltic Power, the first Polish offshore wind farm, jointly developed by Orlen and Canada’s Northland Power. The installation of each turbine is preceded by the deployment of monopile foundations and transition pieces, a stage of the project that is now nearing its […]

  • 27 January 2026
    Fixed-Bottom, Operations & Maintenance, Ports & Logistics, Project Updates, Wind Farm Update

    Orlen Neptun has entered into a land reservation agreement with the Kołobrzeg Sea Port Authority for a site that will later house an operations and maintenance (O&M) base for its Baltic West offshore wind farm. The Kołobrzeg Sea Port is closest to the project location among all ports available in this part of the Baltic […]

  • 11 February 2026
    Fixed-Bottom, Grid Connection, Wind Farm Update

    Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind farms contributing 106.5 TWh […]

  • 10 December 2025
    Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update

    Energy and marine consultancy ABL has been appointed to provide marine warranty survey (MWS) services to support Ocean Winds with the construction of Poland’s BC-Wind offshore wind farm. The BC-Wind offshore wind farm is to be constructed over an area of approximately 90 square kilometres, located within Poland’s Baltic Sea Exclusive Economic Zone, approximately 23 […]

  • 13 October 2025
    Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Njord Survey has signed a long-term framework agreement with 50Hertz for survey services that will support offshore wind development in the German Baltic Sea. Under the agreement, the Sweden-based offshore survey provider will deliver geophysical and remotely operated vehicle (ROV) seabed surveys, with biofuel to be used by all vessels, which will minimise emissions. Philip […]

  • 23 September 2025
    Business & Finance, Contracts & Tenders, Grid Connection, Offshore Platforms, Supply Chain

    Next Geosolutions (NextGeo) has entered into an eight-year framework agreement with the German transmission system operator (TSO) 50Hertz to provide geotechnical seabed survey services for offshore substation development. Under the agreement, valued at multiple million euros annually over eight years, NextGeo will provide geotechnical seabed survey services to support the development of offshore substations, which […]

  • 7 January 2026
    Business & Finance, Floating Wind, Foundations, Manufacturing, Supply Chain

    Switzerland-headquartered Holcim has taken a minority equity ownership in the floating offshore wind technology developer BW Ideol. “This investment sends a powerful message to the floating offshore wind industry, confirming the maturity and deliverability of concrete foundation solutions. With Holcim by our side, we’re making significant strides in our large-scale, concrete serial fabrication strategy“, said […]

  • 2 December 2025
    Business development, Energy Islands, Grid Connection, Power-to-X, Research & Development, Vessels

    Stillstrom and Port of Roenne have teamed up on a study looking into integrating offshore wind energy with maritime electrification. Maersk’s offshore power and charging solutions developer and the Danish port have initiated a joint white paper to explore how Energy Island Bornholm could serve as a blueprint for this kind of integration. The study, […]

  • 5 December 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The HSI consortium, comprising HSM Offshore Energy, Smulders, and Iv, has sent off the Jasmund offshore substation (OSS), which will connect the Windanker offshore wind farm in the Baltic Sea to the German electricity grid. The 4,500-tonne OSS topside, measuring 48 metres in length, 33 metres in width, 17.5 metres in height, has sailed out […]