190 results found for 'Changhua 1 and 2a'

190 results found for 'Changhua 1 and 2a'
Order results by

A list of search results

  • 20 March 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    CSBC-DEME Wind Engineering (CDWE), using the vessel Sea Challenger, has installed the first of the 36 Siemens Gamesa SG 14-222 wind turbines at the Hai Long 3 project site offshore Taiwan. Hai Long 3 is the third phase of the 1+ GW offshore wind project that the consortium comprising Northland Power, Gentari, and Mitsui & […]

  • 9 October 2025
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Global Maritime (GM) has signed a framework agreement with Van Oord, under which the marine and engineering consultancy company will provide a range of services to support Van Oord’s work in the offshore wind sector. The framework covers consultancy and technical support for operations and maintenance (O&M) campaigns, as well as wind turbine and foundation […]

  • 16 October 2025
    Business & Finance, Contracts & Tenders, Operations & Maintenance, Supply Chain

    IOG Wind, formerly known as CWind Taiwan, has secured an operations and maintenance (O&M) contract for the Balance of Plant (BoP) for the 1 GW Hai Long offshore wind project in Taiwan. The scope will cover inspections of newly installed offshore substations, as well as performing inspection, maintenance, and troubleshooting of transition pieces, subsea foundations, […]

  • 8 September 2025
    Business & Finance, Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Ørsted’s Greater Changhua 2b offshore wind project in Taiwan will be commissioned in the third quarter of 2026 instead of later this year due to a damaged export cable. The 300 MW offshore wind farm is part of the 920 MW Greater Changhua 2b and 4 project, currently under construction 35-60 kilometres off the coast of Changhua […]

  • 23 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first turbine from the 920 MW Greater Changhua 2b and 4 offshore wind farms, owned by Ørsted, has delivered first power to the national grid of Taiwan. Being built 35-60 kilometres off the coast of Changhua County, the two offshore wind sites will together comprise 66 Siemens Gamesa 14-236 14 MW wind turbines, 32 […]

  • 11 July 2025

    Heerema Marine Contractors’ heavy-lift vessel Aegir has installed the final suction bucket jacket foundation at Ørsted’s 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. According to the company’s latest social media post, the crew onboard Aegir installed a total of 66 foundations at the site located 35-60 kilometres off the coast […]

  • 3 November 2021
    Wind Farm Update

    116 out of 165 Siemens Gamesa 8.4 MW wind turbines have been installed at Hornsea Two, soon to be the largest offshore wind farm in the world, Ørsted said. 142 inter-array cables have also been installed at the site some 89 kilometres off the Yorkshire coast, the UK. As reported earlier, both offshore substation topsides […]

  • 9 August 2019
    Contracts & Tenders

    Heerema Marine Contractors (HMC) has secured a contract for the transport and installation of turbine foundations and the installation of offshore substations at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. HMC will utilize its vessel Aegir for the transportation and installation of 111 turbine foundations and the installation of two offshore substations at […]

  • 25 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Greater Changhua 1 and 2a offshore wind project was officially inaugurated at an event in the Port of Taichung, Taiwan, on 25 April 2024. With a total installed capacity of 900 MW, the project is in operation and fully connected to the grid, making it the largest in Taiwan and the Asia-Pacific region, said […]

  • 30 January 2024
    Project Updates, Wind Farm Update

    107 out of 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at Ørsted’s Greater Changhua 1 and 2a offshore wind farm site in Taiwan, with nearly 85 per cent of them connected to the national grid. Offshore construction on the Greater Changhua 1 and 2a project started in the summer of 2021. […]

  • 3 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines at the 900 MW Greater Changhua 1 and 2a offshore wind farms have achieved first power and been connected to the Taiwanese national grid. Offshore construction at Ørsted’s Greater Changhua 1 and 2a commenced in the summer of 2021 with the installation of the first wind […]

  • 15 July 2019
    Contracts & Tenders

    Ørsted has awarded WSP with a contract to provide engineering services for the Changhua 1 and 2a offshore wind project in Taiwan. Located 35 to 50 kilometers off the coast of Changhua County, the Changhua 1 and 2a offshore wind farms will have a total capacity of approximately 900MW. The projects will be led by […]

  • 15 August 2022
    Ports & Logistics, Wind Farm Update

    Ørsted and Sing Da Marine Structure (SDMS) have loaded out the first batch of jacket foundations fully manufactured in Taiwan out of the Port of Kaohsiung. The first six jacket foundations will be transported to the 900 MW Changhua 1 and 2a wind farm in two shipments this week, Ørsted said. There, they will be […]

  • 29 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at the Greater Changhua 1 and 2a offshore wind farms in Taiwan, according to an update shared on social media by Per Mejnert Kristensen, President of Ørsted Asia Pacific. Offshore construction on the Greater Changhua 1 and 2a wind farms started in the summer of […]

  • 5 May 2021
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ (HMC) vessel Aegir has started installing jacket foundations at Ørsted’s Greater Changhua offshore wind project site in Taiwan. The vessel is currently installing the jacket for one of the two offshore substations of the Greater Changhua 1 and 2a offshore wind farms. Aegir, which had been undergoing an upgrade at Sembcorp in Singapore […]

  • 10 April 2024
    Operations & Maintenance

    In February 2024, Global Maritime completed its task of providing marine warranty services (MWS) for the installation of 111 wind turbines on Ørsted’s Greater Changhua 1 and 2a offshore wind farms in Taiwan. Ørsted awarded the MWS contract to Global Maritime Singapore in March 2021. The Greater Changhua 1 and 2a offshore wind project is […]

  • 16 July 2021
    Ports & Logistics, Vessels, Wind Farm Update

    Offshore construction is in full swing at Ørsted’s 900 MW Changhua 1 and 2a wind farm off Changhua County, Taiwan. The second of the two offshore substation jacket foundations has now been installed at the site. The first substation jacket was installed by Heerema Marine Contractors’ (HMC) vessel Aegir in early May. Ørsted has also […]

  • 31 January 2019
    Authorities, Wind Farm Update

    Taiwan’s Bureau of Energy has granted Ørsted the establishment permit for the 900MW Changhua 1 and 2a offshore wind project. In the coming weeks, Ørsted will work with the Taiwanese authorities and local stakeholders to reach other outstanding key project milestones, such as completing the supply chain plan and signing the power purchase agreement (PPA), […]

  • 11 June 2019
    Contracts & Tenders, Wind Farm Update

    Danish offshore wind developer Ørsted has signed contracts with South Korea’s Samkang M&T and Hyundai Steel Industries for the supply of jacket foundations for the 900MW Changhua 1 and 2a offshore wind project in Taiwan. Samkang M&T will manufacture and deliver 28 jacket foundations, and Hyundai Engineering & Steel Industries 27 units, according to Korean media. […]

  • 30 April 2019
    Business & Finance, Wind Farm Update

    Ørsted has taken the final investment decision (FID) on the Changhua 1 and 2a offshore wind farm in Taiwan. Prior to the FID, Taiwan’s Ministry of Economic Affairs approved Ørsted’s local supply chain plan, and subsequently Ørsted has signed a power purchase agreement (PPA) with Taipower at the feed-in-tariff level announced on 30 January 2019. […]

  • 18 September 2019
    Contracts & Tenders, Wind Farm Update

    Van Oord has been awarded the contract by Ørsted for the cable installation works at the Greater Changhua 1 & 2a offshore wind farms in Taiwan. The wind farms have a capacity of 900MW and are located between 35 and 60 kilometres off the west coast of Changhua County. Van Oord is responsible for the […]

  • 10 September 2020
    Business & Finance

    Ørsted has appointed BNP Paribas, Cathay United Bank and CTBC Bank as Mandate Lead Arranger’s for a potential TWD denominated green bond issuance in Taiwan. The green bond, set to be issued in Q4 2020, represents Ørsted’s second green bond offering in Taiwan. Ørsted intends to issue the new green bonds for the purpose of […]

  • 9 February 2022
    Operations & Maintenance, Vessels, Wind Farm Update

    The first service operation vessel (SOV) built for the Asian offshore wind market completed six days of sea trials offshore Vietnam back in January. The SOV, to be named TSS Pioneer, is being built by Vard at the Vung Tau shipyard in Vietnam. The vessel will soon be delivered to Ta San Shang Marine, a […]

  • 3 January 2019
    Authorities, Business & Finance, Contracts & Tenders, Wind Farm Update

    Ørsted will pause and revisit its project activities, the project timelines, and local commitments in Taiwan after not receiving an establishment permit in time to sign a 2018 power purchase agreement (PPA) with Taipower for the Changhua 1 and 2a projects.

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seajacks International has won a contract by Ørsted for the transport and installation of turbines at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. Seajacks is planning to use its jack-up vessel Seajacks Scylla for the transport and installation of 111 Siemens Gamesa 8MW turbines at the project site located 35-50km off the coast of […]

  • 27 August 2021
    Wind Farm Update

    The first wind turbine jacket foundation has been installed at the construction site of the Greater Changhua 1 and 2a offshore wind project, being built by Ørsted in the Taiwan Strait, some 35 to 50 kilometres off the coast of Changhua County. According to earlier information, Heerema Marine Contractors’ (HMC) vessel Aegir, which recently installed the two jackets […]