184 results found for 'Changhua 1 and 2a'

184 results found for 'Changhua 1 and 2a'
Order results by

A list of search results

  • 24 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installation of the substation was carried out by […]

  • 19 March 2025
    Vessels

    Cadeler’s recently delivered wind turbine installation vessel, Wind Maker, has arrived in Taichung, Taiwan, from where it will sail out to the Greater Changhua 2b and 4 offshore wind project sites. Wind Maker set sail from Singapore and has arrived in Taichung, marking an important milestone for the Greater Changhua 2b and 4 offshore wind […]

  • 16 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 66 Siemens Gamesa 14 MW wind turbines that will make up the Greater Changhua 2b & 4 offshore wind farm in Taiwan has been installed. The major milestone for Ørsted’s 920 MW offshore wind project also marks a milestone for Siemens Gamesa, whose SG 14-236 DD wind turbine model is installed offshore […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 11 April 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first suction bucket jacket (SBJ) foundation has been installed at the Greater Changhua 2b and 4 offshore wind farm site in Taiwan, where wind turbine installation is also set to begin soon. The foundations are being installed by Heerema Marine Contractors’ heavy lift vessel Aegir, which was also used to install the project’s substation […]

  • 18 February 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has commenced the offshore construction for the 920 MW Greater Changhua 2b and 4 offshore wind farms, located 35-60 kilometres off the coast of Changhua County, Taiwan. Greater Changhua 2b and 4 were awarded in June 2018 as part of Taiwan’s first competitive price-based auction, which had no mandatory local content requirements. In July […]

  • 6 February 2025
    Business & Finance, Fixed-Bottom

    Ørsted has reported 2024 earnings from its operational offshore wind farms of DKK 23.8 billion (approximately EUR 3.2 billion), up by 20 per cent compared to 2023. The global offshore wind developer said on 6 February the increase was mainly due to the ramp-up of generation at Greater Changhua 1 and 2a offshore wind project […]

  • 21 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa 14-222 DD turbine has been installed at the Hai Long 2A offshore wind farm in Taiwan, which is being developed by a joint venture between Northland Power, Mitsui & Co., and Gentari. The Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW […]

  • 11 December 2024
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Ørsted has sold a 50 per cent ownership share in the Greater Changhua 4 offshore wind farm to Taiwanese insurance company Cathay Life Insurance, and its affiliate Cathay Wind Power Holdings, for approximately DKK 11.6 billion (around EUR 1.55 billion). The 583 MW Greater Changhua 4 is part of the 920 MW offshore wind project […]

  • 7 March 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is […]

  • 2 December 2024
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first batch of four jacket foundations, manufactured by Petrovietnam Technical Services Corporation (PTSC), has set sail from Vietnam. The units will be installed at Ørsted’s Greater Changhua 2b & 4 offshore wind farms in Taiwan. To celebrate this milestone, PTSC and others held a special ceremony on 1 December, with Vietnam’s Prime Minister Phạm […]

  • 13 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first batch of suction bucket jacket foundations, which will be installed at the Greater Changhua 2b and 4 offshore wind farms, have arrived at the Port of Taichung in Taiwan. The initial batch of foundations has arrived from HSG Sungdong in South Korea, the supplier of 33 units for the 920 MW Greater Changhua […]

  • 15 November 2024
    Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Wind Farm Update

    Poseidon Cables, a UK-based company specialised in subsea cable installation, termination and testing, has secured a contract with Norwegian subsea services provider NCT Offshore for work on Ørsted’s 920 MW Greater Changhua 2b & 4 offshore wind farms in Taiwan. Last year, NCT Offshore was awarded the installation contract for the 66 kV inter-array cables […]

  • 3 November 2021
    Wind Farm Update

    116 out of 165 Siemens Gamesa 8.4 MW wind turbines have been installed at Hornsea Two, soon to be the largest offshore wind farm in the world, Ørsted said. 142 inter-array cables have also been installed at the site some 89 kilometres off the Yorkshire coast, the UK. As reported earlier, both offshore substation topsides […]

  • 9 August 2019
    Contracts & Tenders

    Heerema Marine Contractors (HMC) has secured a contract for the transport and installation of turbine foundations and the installation of offshore substations at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. HMC will utilize its vessel Aegir for the transportation and installation of 111 turbine foundations and the installation of two offshore substations at […]

  • 25 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Greater Changhua 1 and 2a offshore wind project was officially inaugurated at an event in the Port of Taichung, Taiwan, on 25 April 2024. With a total installed capacity of 900 MW, the project is in operation and fully connected to the grid, making it the largest in Taiwan and the Asia-Pacific region, said […]

  • 30 January 2024
    Project Updates, Wind Farm Update

    107 out of 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at Ørsted’s Greater Changhua 1 and 2a offshore wind farm site in Taiwan, with nearly 85 per cent of them connected to the national grid. Offshore construction on the Greater Changhua 1 and 2a project started in the summer of 2021. […]

  • 3 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines at the 900 MW Greater Changhua 1 and 2a offshore wind farms have achieved first power and been connected to the Taiwanese national grid. Offshore construction at Ørsted’s Greater Changhua 1 and 2a commenced in the summer of 2021 with the installation of the first wind […]

  • 15 July 2019
    Contracts & Tenders

    Ørsted has awarded WSP with a contract to provide engineering services for the Changhua 1 and 2a offshore wind project in Taiwan. Located 35 to 50 kilometers off the coast of Changhua County, the Changhua 1 and 2a offshore wind farms will have a total capacity of approximately 900MW. The projects will be led by […]

  • 29 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at the Greater Changhua 1 and 2a offshore wind farms in Taiwan, according to an update shared on social media by Per Mejnert Kristensen, President of Ørsted Asia Pacific. Offshore construction on the Greater Changhua 1 and 2a wind farms started in the summer of […]

  • 5 May 2021
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ (HMC) vessel Aegir has started installing jacket foundations at Ørsted’s Greater Changhua offshore wind project site in Taiwan. The vessel is currently installing the jacket for one of the two offshore substations of the Greater Changhua 1 and 2a offshore wind farms. Aegir, which had been undergoing an upgrade at Sembcorp in Singapore […]

  • 15 August 2022
    Ports & Logistics, Wind Farm Update

    Ørsted and Sing Da Marine Structure (SDMS) have loaded out the first batch of jacket foundations fully manufactured in Taiwan out of the Port of Kaohsiung. The first six jacket foundations will be transported to the 900 MW Changhua 1 and 2a wind farm in two shipments this week, Ørsted said. There, they will be […]

  • 10 April 2024
    Operations & Maintenance

    In February 2024, Global Maritime completed its task of providing marine warranty services (MWS) for the installation of 111 wind turbines on Ørsted’s Greater Changhua 1 and 2a offshore wind farms in Taiwan. Ørsted awarded the MWS contract to Global Maritime Singapore in March 2021. The Greater Changhua 1 and 2a offshore wind project is […]

  • 16 July 2021
    Ports & Logistics, Vessels, Wind Farm Update

    Offshore construction is in full swing at Ørsted’s 900 MW Changhua 1 and 2a wind farm off Changhua County, Taiwan. The second of the two offshore substation jacket foundations has now been installed at the site. The first substation jacket was installed by Heerema Marine Contractors’ (HMC) vessel Aegir in early May. Ørsted has also […]

  • 31 January 2019
    Authorities, Wind Farm Update

    Taiwan’s Bureau of Energy has granted Ørsted the establishment permit for the 900MW Changhua 1 and 2a offshore wind project. In the coming weeks, Ørsted will work with the Taiwanese authorities and local stakeholders to reach other outstanding key project milestones, such as completing the supply chain plan and signing the power purchase agreement (PPA), […]

  • 11 June 2019
    Contracts & Tenders, Wind Farm Update

    Danish offshore wind developer Ørsted has signed contracts with South Korea’s Samkang M&T and Hyundai Steel Industries for the supply of jacket foundations for the 900MW Changhua 1 and 2a offshore wind project in Taiwan. Samkang M&T will manufacture and deliver 28 jacket foundations, and Hyundai Engineering & Steel Industries 27 units, according to Korean media. […]