189 results found for 'Changhua 1 and 2a'

189 results found for 'Changhua 1 and 2a'
Order results by

A list of search results

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seajacks International has won a contract by Ørsted for the transport and installation of turbines at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. Seajacks is planning to use its jack-up vessel Seajacks Scylla for the transport and installation of 111 Siemens Gamesa 8MW turbines at the project site located 35-50km off the coast of […]

  • 27 August 2021
    Wind Farm Update

    The first wind turbine jacket foundation has been installed at the construction site of the Greater Changhua 1 and 2a offshore wind project, being built by Ørsted in the Taiwan Strait, some 35 to 50 kilometres off the coast of Changhua County. According to earlier information, Heerema Marine Contractors’ (HMC) vessel Aegir, which recently installed the two jackets […]

  • 16 April 2020
    Contracts & Tenders

    China Shipbuilding Corporation Taiwan (CSBC) will manufacture 20 transition piece steel structures for Changhua 1 and 2a offshore wind project.

  • 28 January 2022
    Ports & Logistics, Vessels, Wind Farm Update

    The jack-up vessel Seajacks Scylla has arrived in the Port of Taichung in Taiwan in preparation for the turbine installation work on the 900 MW Changhua 1 and 2a offshore wind farms. The installation work is expected to start as soon as a favourable window opens. Seajacks Scylla will transport and install 111 Siemens Gamesa 8MW turbines at […]

  • 11 August 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    The commissioning of the 900 MW Greater Changhua 1 & 2a has been delayed to 2023, according to Ørsted’s interim report for the first half of 2022. The project was initially scheduled to be fully operational by the end of the year, but due to COVID-19-related delays, the commissioning of the wind farm is being […]

  • 24 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installation of the substation was carried out by […]

  • 27 January 2021
    Contracts & Tenders, Wind Farm Update

    Master Builders Solutions has won the grout supply contracts for the Formosa 2, the Changfang and Xidao, and the Greater Changhua 1 and 2a offshore wind projects in Taiwan. In total, Master Builders Solutions will be supplying MasterFlow 9500 and MasterFlow 9800 to 222 offshore foundations over the next three years. “2020 has been a […]

  • 21 January 2019
    Business & Finance, Contracts & Tenders

    Ørsted has suspended the execution of contracts with Taiwan Cogeneration Corporation, China Steel Corporation (CSC) and Century Iron and Steel Industrial (CISI) for the developer’s offshore wind projects in Taiwan, Taiwanese media reports. OffshoreWIND.biz has contacted Ørsted to confirm this, with the company yet to respond. The suspended contracts were already ongoing, while for those that […]

  • 2 October 2020
    Vessels

    Vard Electro has selected Corvus Energy to supply lithium-ion battery-based Energy Storage System (ESS) for the service operations vessel (SOV) being built for Ørsted’s Greater Changhua 1 and 2a wind farms in Taiwan. The SOV is of VARD 4 19 design developed for the complicated and harsh environment in the Taiwan Strait. Currently under construction […]

  • 5 May 2021
    Operations & Maintenance, Training & Education

    Ten wind turbine generator (WTG) technicians Ørsted Taiwan recently recruited have departed for training in the UK, the company reported on 5 May. The team of ten technicians, who will be on their training secondment in the UK until the end of the year, were recruited in January, when the offshore wind developer hired 22 […]

  • 9 May 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ørsted has appointed energy and marine consultancy, ABL, to provide marine warranty survey services (MWS) for the offshore transportation and installation (T&I) of wind turbines and cables package for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. ABL’s scope of work includes reviewing, surveying, and approving all operations relating to the transportation […]

  • 3 August 2021
    Ports & Logistics

    Siemens Gamesa’s offshore wind nacelle assembly facility in Taichung, Taiwan has assembled its first nacelle. This marks the first time a Siemens Gamesa offshore turbine nacelle has been assembled outside Europe. The construction work on Siemens Gamesa’s assembly facility in Taichung Harbor started in March 2020. The parcel of land being developed in Taiwan measures […]

  • 19 March 2025
    Vessels

    Cadeler’s recently delivered wind turbine installation vessel, Wind Maker, has arrived in Taichung, Taiwan, from where it will sail out to the Greater Changhua 2b and 4 offshore wind project sites. Wind Maker set sail from Singapore and has arrived in Taichung, marking an important milestone for the Greater Changhua 2b and 4 offshore wind […]

  • 11 September 2019
    Business & Finance

    Ørsted is preparing for a potential Taiwan New Dollar (TWD) denominated green bond issuance in Taiwan towards the end of this year to finance the Greater Changhua offshore wind projects. The company has selected BNP Paribas, Bank of Taiwan, CTBC Bank, and Deutsche Bank as arrangers. In April 2019, Ørsted made the final investment decision […]

  • 17 March 2021
    Ports & Logistics, Wind Farm Update

    The first wind turbine tower section built for the 900 MW Greater Changhua 1 and 2a offshore wind farm has arrived at the Port of Taichung, Taiwan, Ørsted, the developer of the project, said. This is the first of 333 tower sections in total that are being manufactured locally by the consortium of CS Wind […]

  • 15 January 2020
    Business & Finance

    Steel fabricator CSBC Corporation has inaugurated its pin-pile production line at its factory near the Port of Kaohsiung in Taiwan. CSBC also plans to add a line for the production of transition pieces to the facility. The production line will be used to manufacture pin-piles for Ørsted’s Changhua 1 and 2a offshore wind farm. CSBC […]

  • 7 September 2020
    Contracts & Tenders, Vessels

    Solstad Offshore has signed an agreement with Ørsted to deploy construction support vessel (CSV) Normand Jarl on the Greater Changhua 1 & 2a offshore wind project in Taiwan. Normand Jarl is scheduled to begin working offshore Taiwan in the second quarter of 2021. The firm period on the contract is 15 months with options to […]

  • 21 April 2020
    Wind Farm Update

    Heerema Fabrication Group is set to manufacture the pre-piling template for the Greater Changhua offshore wind project in Taiwan. The template, which will enable Heerema Marine Contractors to install the piles accurately, consists of three pile sleeves connected by framing, including hydraulically adjustable pile guides and mudmats. Heerema Vlissingen will fabricate the steel structure and […]

  • 21 December 2020
    Contracts & Tenders

    Heerema Marine Contractors (HMC) has awarded the Dutch offshore transfer equipment specialist Safeway with a contract to supply a Safeway Seagull type motion compensated gangway system for installation on the CSV Normand Baltic. This is Safeway’s first contract for HMC, and it is also the first time the Safeway Seagull system with 3D crane function […]

  • 20 May 2020
    Contracts & Tenders

    LOC Group has secured a contract with Ørsted to provide marine warranty survey services (MWS) for the Greater Changhua 1 & 2a offshore wind farms in Taiwan. Under the agreement, LOC will provide MWS services for the transportation and installation of the inter-array and export cables. Technical document review and operational approvals will be undertaken […]

  • 26 November 2019
    Grid Connection

    Ørsted has contracted Trelleborg to provide the NjordGuard cable protection system (CPS) for the Greater Changhua 1 & 2a offshore wind project in Taiwan. Trelleborg will provide 235 NjordGuard cable protection systems and bellmouths, which will protect all inter-array and export cables on the wind farms. Production will be carried out at Trelleborg’s manufacturing facility […]

  • 23 July 2019
    Contracts & Tenders, Grid Connection

    LS Cable & System has secured a contract by Jan De Nul to supply submarine cables for an offshore wind project in Taiwan. Under the contract, the Korean cable manufacturer will supply 130km of submarine cable for the project located in Miaoli County, west Taiwan, by 2021. To remind, Jan De Nul is responsible for the design, […]

  • 3 May 2023
    Business & Finance

    World’s leading offshore wind developer, Ørsted, has reported DKK 6.9 billion (EUR 926 million) operating profit (EBITDA) for the first quarter of 2023, DKK 2.5 billion less compared to the same period a year earlier. EBITDA excluding new partnerships in Q1 2023 was DKK 0.9 billion lower than Q1 2022, as Q1 2022 was positively […]

  • 30 January 2019
    Authorities, Contracts & Tenders, Wind Farm Update

    The 900MW Changhua 1 and 2a offshore wind projects will move forward, Ørsted said in response to the announced 6% Feed-in-Tariff reduction, but the final investment decision depends on the outcome of supply contract renegotiations and relevant project milestones being achieved in time to keep the projects on track for commissioning in 2021. Developers who sign their […]

  • 1 April 2022
    Ports & Logistics, Vessels, Wind Farm Update

    The first of the 111 Siemens Gamesa SG 8.0-167DD wind turbines has been installed at the 900 MW Greater Changhua 1 & 2a wind farm project offshore Taiwan. The first batch of turbine components was transported from the Port of Taichung, and the first turbine was installed at the site by Seajack Scylla, a wind […]

  • 12 March 2021
    Vessels, Wind Farm Update

    Subsea construction vessel Topaz Tangaroa has left the Netherlands and is on her way to Taiwan to join Van Oord’s cable laying vessel Nexus on the Greater Changhua 1 and 2a offshore wind project. Prior to leaving the Netherlands, Topaz Tangaroa was equipped with Van Oord’s trencher Dig-It, and a walk-to-work system. AIS data shows […]