A photo of Trianel Windpark Borkum in sunset

CTVs Sought for Trianel Windpark Borkum

Trianel Windkraftwerk Borkum has issued a tender for the provision of two crew transfer vessels (CTVs) to service the 200MW Trianel Windpark Borkum I in the German North Sea and nearby offshore wind farms.

Trianel-Borkum

The wind farm operator is looking for a provider or providers of two CTVs, one with a capacity of at least twelve persons and a weather-related crossing of at least two meters, and the other with a capacity of at least 24 persons and a weather-related crossing of at least two and a half meters.

The charter will start on 15 January, and end on 31 December 2020, with two 12-month options to renew.

The time limit for receipt of tenders or requests to participate is 6 November.

The first Trianel Windpark Borkum phase comprises 40 5MW Adwen turbines which have been operational since 2015.

Trianel Windpark Borkum II, currently under construction, will add 32 Senvion 6.2M152 turbines scheduled to be completed next year.