Second Batch of Hornsea One Turbines Going for Installation

Fred. Olsen Windcarrier’s jack-up Bold Tern has departed from Hull, the UK, carrying the second batch of turbines for the Hornsea Project One offshore wind project.

Second Batch of Hornsea One Turbines Going for Installation
Bold Tern carrying the first batch of turbines to the project. (Source: Fred. Olsen Windcarrier)

The vessel installed the first Siemens Gamesa 7MW turbine at the site some 120km off the Yorkshire coast in early February.

Bold Tern is in charge of transporting and installing half of the 174 turbines. The remainder is set to be installed by A2SEA’s installation vessel Sea Challenger, which recently commenced the works.

Hornsea Project One comprises three offshore substations and the world’s first reactive compensation substation (RCS).

The 1.2GW project will become the largest offshore wind farm in the world when fully operational in 2020.

Related news

List of related news articles

Posted: 8 months ago

Hornsea One Nears Turbine Installation

[…]

Categories:
  • Wind Farm Update
Posted: 8 months ago
Posted: 8 months ago

Bold Tern Begins Hornsea One Turbine Installation

[…]

Categories:
  • Wind Farm Update
Posted: 8 months ago
Posted: 8 months ago

First Turbine Up at Hornsea Project One

[…]

Categories:
  • Wind Farm Update
Posted: 8 months ago
Posted: 8 months ago

EEW OSB Completes Hornsea Project One Work

[…]

Categories:
  • Wind Farm Update
Posted: 8 months ago