Kriegers Flak CGS UXO Client Representative Services Provider Wanted

Transmission system operators Energinet.dk and 50Hz Transmission are looking for a provider of client representative services during unexploded ordnance (UXO) activities along the cable routes at the Kriegers Flak Combined Grid Solution (CGS).

Source: Energinet.dk

The scope of work includes the provision of the client representative services during geophysical UXO survey, during inspection of possible UXO objects and during removal of identified UXO objects.

The contract is valued at DKK 700,000 (EUR 94,000) and the tender will remain open until 16 February, 2017.

The two TSOs are planning two high voltage alternating current (HVAC) cables between two offshore substations located at the 600MW Kriegers offshore wind farm in the Danish part of the Baltic Sea and the 288MW Baltic 2 offshore wind farm in the German part of the Baltic Sea.

The planned cable routes are approximately 25 kilometres long.

The Kriegers Flak CGS will connect the Danish region of Sjaelland and German Mecklenburg-Western Pomerania. The interconnector is planned to start operating by the end of 2018.

nkt cables awarded VBMS with a contract for the installation of approximately 50km of 150 kV AC high-voltage submarine cables for Kriegers Flak CGS, with the project scheduled to be carried out in Q2, 2018.