10000 results found for 'first'

10000 results found for 'first'
Order results by

A list of search results

  • 4 July 2025
    Vessels

    The second wind turbine installation vessel (WTIV), built by Yantai CIMC Raffles Offshore for DEME Group, has been launched. Norse Energi, like its sister vessel Norse Wind, is engineered to install turbines with rotor diameters over 300 metres and XXL monopiles up to 3,000 tonnes, even in water depths of 70 metres. The first steel […]

  • 4 June 2025
    Project Updates, Wind Farm Update

    The 488 MW Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm has started supplying green electricity to the French grid, only a few weeks after the installation of the first turbine. Following a successful initial testing phase that began on 23 May, the wind farm’s first Siemens Gamesa 8 MW turbines are now connected to […]

  • 27 June 2025
    Business development, Collaboration, Infrastructure, Outlook & Strategy, Project Updates, Technology, Wind Farm Update

    What is described as the “world’s first” offshore solar farm integrated within a wind farm has completed assembly at the Port of Amsterdam and is ready for deployment at the Hollandse Kust Noord (HKN) offshore wind farm in the North Sea. Dutch company Oceans of Energy assembled the floating solar farm in three days. The system will […]

  • 11 July 2025
    Environment, Fixed-Bottom, Project Updates, Wind Farm Update

    RWE and marine nature-inclusive design specialist ARC Marine have launched a pilot project to install ARC Marine’s reef cubes at the Rampion offshore wind farm in the UK. The reef cubes are designed to both protect the wind turbine foundations and enhance marine biodiversity, according to the two companies. The companies last year installed 180 […]

  • 19 May 2025
    Authorities, Contracts & Tenders, Floating Wind, Planning & Permitting

    The Norwegian Ministry of Energy has invited applications for three floating wind sites within the Utsira Nord area. The deadline for submitting proposals is set for 15 September 2025. The government is offering a project capacity of 500 MW at each site through the tendering process, which will be carried out in two stages: the […]

  • 3 June 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The Danish Energy Agency (DEA) has extended the electricity production permit for the 23 MW Samsø offshore wind farm by ten years, the first such extension for an older offshore wind farm in Denmark. The electricity production permit for the Samsø offshore wind farm, built in 2002, was limited to 25 years. However, the owner, […]

  • 30 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Equinor and Polenergia’s Bałtyk 2 and Bałtyk 3 offshore wind farms in Poland have entered the construction phase, with work on the onshore infrastructure now underway. After the final investment decisions were made in May this year, Bałtyk 2 and Bałtyk 3 offshore wind farms have entered the implementation phase. Almost 200 people took part […]

  • 21 May 2025
    Operations & Maintenance

    Baltic Power, a joint venture between Orlen and Northland Power, has launched Poland’s first operations and maintenance (O&M) base dedicated to offshore wind projects. The facility will support the 1.2 GW Baltic Power offshore wind farm for its entire lifecycle of approximately 30 years. Construction of the Łeba base began in January 2024 and was completed […]

  • 30 April 2025
    Energy Islands, Grid Connection, Infrastructure, Offshore Platforms

    Construction has begun on the Princess Elisabeth Island, the world’s first energy island, in the Belgian North Sea, with the first two of 23 caissons already submerged at their final location. The work is being carried out on behalf of grid operator Elia Transmission Belgium by TM Edison, a joint venture between DEME and Jan De […]

  • 7 July 2025
    Authorities, Planning & Permitting, Project Updates, Wind Farm Update

    The Mona offshore wind farm, being developed by a joint venture between EnBW and BP, has been granted development consent by the UK’s Secretary of State for Energy Security and Net Zero, Ed Miliband. Located in the Irish Sea, the 1.5 GW Mona is the first offshore wind project from the UK’s Round 4 leasing […]

  • 21 November 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first Siemens Gamesa 11 MW wind turbine has been installed at the South Fork Wind Farm offshore New York. The first of South Fork Wind’s twelve Siemens Gamesa wind turbines was hoisted into place by the offshore construction team at the project site 35 miles off Montauk, New York. First approved by the Long Island […]

  • 15 September 2020
    Wind Farm Update

    GE Renewable Energy has produced the first turbine nacelle for the 480 MW Saint-Nazaire – France’s first offshore wind farm. This nacelle, which contains the generator, is the first in a series of 80 Haliade 150-6 MW wind turbines produced for the Saint-Nazaire offshore wind farm to be assembled by GE Renewable Energy at the […]

  • 8 July 2025
    Business & Finance, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Haesong Offshore Wind Company has signed a grid interconnection agreement with Korea Electric Power Corporation (KEPCO) for the Haesong Offshore Wind 1 and Haesong Offshore Wind 3 projects. Haesong Offshore Wind 1 and 3 projects are managed and funded by Copenhagen Infrastructure Partners (CIP), while project development, including implementation, permitting, and technical development, is carried […]

  • 23 June 2023
    Wind Farm Update

    The first monopile foundation has been installed at the South Fork Wind site offshore New York, the state’s first offshore wind farm. The foundation will support the project’s offshore substation, which will also be installed in the coming days. Boskalis’s offshore installation vessel Bokalift 2 is transporting and installing the foundations, including the one for […]

  • 15 May 2018
    Ports & Logistics, Vessels, Wind Farm Update

    A2Sea’s jack-up Sea Installer has installed the first sets of Siemens Gamesa D7-type turbines on the Rentel offshore wind farm in the Belgian North Sea.

  • 10 September 2015
    Wind Farm Update

    Westermeerwind has reached another milestone with the installation of the first set of wind turbine blades. The wind turbine blades arrived on Tuesday evening from Oude Zeug where they were preassembled via vessel LD27. The installation was completed the following day via ‘De Schelde’ pontoon fitted with the 11350 Liebherr crane, owned by Van Oord/Mammoet. […]

  • 2 July 2015
    Vessels, Wind Farm Update

    Northland Power has installed the first monopile at the 600MW Gemini wind farm offshore Dutch coast. The job was completed by Van Oord’s offshore installation vessel, Aeolus, which is install a total of 150 foundations together with Pacific Osprey of Swire Blue Ocean. Located 85 kilometers off the coast of Groningen the project will feature Siemens 4MW […]

  • 17 May 2017
    Vessels, Wind Farm Update

    Siemens team onboard the wind turbine installation vessel (WTIV) Pacific Orca has installed the first of the fifty-six 6MW Siemens turbines on the 336MW Galloper wind farm off Suffolk.

  • 14 August 2018
    Ports & Logistics, Vessels

    GeoSea’s Apollo has left Pula, Croatia, and is headed to Vlissingen, the Netherlands, where this multi-purpose, self-propelled jack-up vessel will undergo mobilisation ahead of its first assignments.

  • 19 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    DEME’s jack-up Sea Installer has installed the first GE Haliade-X 13 MW wind turbine at the Vineyard Wind 1 offshore wind project in the US. The completed turbine is comprised of one tower, three 351-foot-long blades (about 107 metres), and a nacelle. The fully assembled unit represents the largest turbine in the western world, with […]

  • 5 July 2022
    Wind Farm Update

    The first of the total of 33 Vestas 4.2 MW wind turbines has been installed at the Akita Noshiro offshore wind farm in Japan, the country’s first commercial-size, fixed-bottom wind project. After the installation vessel Seajacks Zaratan finished placing all the 33 monopile foundations at their respective locations is September last year, the same vessel […]

  • 20 June 2025
    Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The construction of the high-voltage alternating current (HVAC) infrastructure has begun with a first steel cut ceremony at the HSM Offshore Energy yard in Schiedam, the Netherlands. The HVAC modules will be directly installed on the Princess Elisabeth offshore energy hub (MOG2) in Belgium. The HVAC substations will house essential components such as power transformers […]

  • 16 May 2025
    Authorities, Business development, Planning & Permitting, Research & Development

    The Estonian government has approved a draft bill granting the first building permit for the construction of an offshore wind farm in the country. The permit will be granted to Saare Wind Energy OÜ, which plans to build a wind farm on the west coast of Saaremaa. The company seeks to build an offshore wind […]

  • 27 June 2023
    Business development, R&D, Research & Development, Technology

    The offshore hydrogen production platform that Lhyfe is testing in France, named Sealhyfe, began producing its first kilograms of hydrogen on 20 June after it was towed last month to the SEM-REV offshore test site which is connected to BW Ideol’s floating wind turbine Floatgen. Sealhyfe is capable of producing up to 400 kilograms of […]

  • 19 November 2014
    R&D, Technology

    WavePOD prototype produced its first power in laboratory tests this week. The tenth-scale WavePOD was officially switched on by David Waldron, Bosch Rexroth’s UK Business Manager for Machinery Applications and Renewables, to mark the start of the test programme at the world-leading Institute for Fluid Power Drives and Controls (IFAS) at RWTH Aachen University, Germany. […]

  • 9 November 2015
    Wind Farm Update

    The Dutch 144MW Westermeerwind offshore wind farm has produced first electricity. The milestone was achieved last week using the 44km of electricity cables installed by VBMS. Also, Siemens has installed a total of 17 out of 48 of its 3 MW turbines. When completed the 144MW wind farm will be able to produce electricity for […]