288 results found for 'Seagreen'

288 results found for 'Seagreen'
Order results by

A list of search results

  • 27 May 2020
    Grid Connection, Wind Farm Update

    SSE Renewables has reached a voluntary land agreement for the development of the underground cable route for the Seagreen offshore wind project in Scotland. The deal was reached with Angus Council, Carnoustie Golf Links Management Committee (CGLMC), and other key landowners to allow the development of the underground cable route to the Tealing substation. “We’re […]

  • 28 February 2018
    Authorities, Business & Finance, Environment, Wind Farm Update

    Seagreen Wind Energy Limited will apply to Scottish Ministers to vary the existing Seagreen Alpha and Seagreen Bravo consents that would allow the combined maximum capacity of the two wind farms to be increased from 1,050MW to 1,500MW.

  • 5 July 2017
    Authorities, Wind Farm Update

    Seagreen Wind Energy Ltd has requested a scoping opinion from Marine Scotland Licensing Operations Team, on behalf of Scottish Ministers, for the proposed 1.05GW Seagreen Phase 1 wind farm project.

  • 3 November 2021

    Marshalling operations for wind turbine parts are underway at Able Seaton Port in Hartlepool for what will be Scotland’s biggest, and the world’s deepest fixed bottom offshore wind farm – the 1.1 GW Seagreen. In the last few weeks, SSE Renewables and joint-venture partner TotalEnergies announced that the installation of turbine foundations has commenced at […]

  • 12 March 2024
    Business development, Fixed-Bottom, Project Updates, Research & Development, Wind Farm Update

    The first geotechnical seabed surveys for TotalEnergies and SSE Renewables’ 500 MW Seagreen 1A offshore wind farm in Scotland have been completed. Phase two of the geotechnical works is expected to commence later this year and should take around two weeks to complete. Seagreen 1A lies adjacent to the existing 1,075 MW Seagreen project and […]

  • 20 July 2020
    Contracts & Tenders, Wind Farm Update

    Swire Blue Ocean (SBO) has secured a contract with MHI Vestas for the transportation and installation of turbines at the Seagreen offshore wind project in Scotland. Seagreen will comprise 114 MHI Vestas V164-10 MW turbines located some 27 kilometers off the Angus coast. SBO expects to commence the installation of the units in the second […]

  • 4 November 2019
    Grid Connection, Wind Farm Update

    SSE has chosen Nexans as the preferred supplier of export cables for the first phase of the Seagreen offshore wind project in Scotland, which comprises the Seagreen Alpha and Bravo offshore wind farms. Nexans will design, manufacture and install three 65km offshore export cables and three 20km onshore export cables for Seagreen Phase 1. “We […]

  • 5 October 2020
    Grid Connection, Wind Farm Update

    The next phase of the onshore cable works for the Seagreen offshore wind farm in Scotland is set to start at Carnoustie Golf Links in the coming days, according to Angus Council. In August, the Seagreen team begun preparatory works for the onshore cabling project with early compound set up works at Carnoustie. The following […]

  • 21 October 2021
    Wind Farm Update

    The jacket foundation and the accompanying pin piles for the Seagreen offshore substation have left the United Arab Emirates and are en route to Scotland, Petrofac said. Petrofac is in charge of designing, supplying, and installing the High Voltage Alternating Current (HVAC) onshore and offshore substations for the 1,075 MW Seagreen offshore wind farm. The […]

  • 17 June 2022
    Grid Connection, Wind Farm Update

    The 1.1 GW Seagreen offshore wind farm has reached a significant milestone with the installation of approximately 19 kilometres of onshore cabling that will connect the GBP 3 billion project to the Scottish national grid. The onshore cable route runs between landfall at the coast of Carnoustie and the wind farm’s new substation at Tealing […]

  • 21 June 2018
    Contracts & Tenders, Wind Farm Update

    Seagreen Wind Energy Limited is preparing to bid in the next UK Contracts for Difference (CfD) auction for the Seagreen Alpha and Seagreen Bravo wind farms, which is scheduled for Spring 2019.

  • 13 October 2014
    Authorities

    Seagreen Wind Energy Ltd (Seagreen), a 50 / 50 joint venture partnership formed between Fluor Ltd and SSE Renewables, welcomes decision by Scottish Government to grant consent to Projects Alpha and Bravo; Phase 1 of the Firth of Forth offshore wind farm development Zone. The announcement marks another positive step in the Zone’s development following […]

  • 11 April 2022
    Business & Finance, Contracts & Tenders

    Danish wind turbine manufacturer Vestas has selected integrated logistics and materials management company ASCO to provide shipping services on the Seagreen offshore wind farm in Scotland. The deal will see ASCO’s ship agency Seletar provide services including crew transfer to the operations of the project, initially during the construction phase, from Montrose port. The project […]

  • 21 December 2020
    Grid Connection, Wind Farm Update

    Nexans has begun onshore work for the installation of underground cable that will connect the Seagreen offshore wind project to the grid in Angus, Scotland. Once finished, the 19 km cable will reach from where the project makes landfall in Carnoustie to a new substation currently under construction in Tealing. Installation is expected to be […]

  • 11 October 2021
    Ports & Logistics, Wind Farm Update

    The first wind turbine jacket foundation has been installed at the 1.1 GW Seagreen, Scotland’s largest and the world’s deepest, fixed bottom offshore wind farm, SSE Renewables said. Two jackets operated by main contractor Seaway 7 made their way on a barge from Global Energy Group’s Port of Nigg in the Highlands of Scotland to […]

  • 21 September 2018
    Authorities, Grid Connection, Wind Farm Update

    Seagreen Wind Energy Limited has submitted an application to Marine Scotland for Section 36 consents and Marine Licences for the optimised Seagreen Alpha and Seagreen Bravo offshore wind farms.

  • 16 February 2023
    Wind Farm Update

    Seagreen offshore wind farm has entered the final phases of work after the remaining eight three-legged jacket foundations were loaded onto barges at Global Energy Group’s Port of Nigg in the Highlands of Scotland. Global Port Services, part of Global Energy Group, fulfilled the storage, marshalling, and logistics contracts for the 114 95-metre tall jacket […]

  • 2 June 2021
    Wind Farm Update

    Vestas will manufacture 99 out of the 114 V164 wind turbine blade sets for the Seagreen offshore wind project in the United Kingdom. 297 blades in total will be produced by Vestas in the UK for installation at the 1,075 Seagreen off the Angus coast by the end of 2022. Production is currently underway for […]

  • 8 December 2022
    Contracts & Tenders, Wind Farm Update

    Global Port Services, owned by Global Energy Group alongside the Port of Nigg, has secured multiple contracts to support Seagreen Wind Energy Limited (SWEL) with site-enabling works for the pre-assembly construction of wind turbine components at its Port of Nigg facility. The news comes as the final turbine foundations for the Seagreen offshore wind project […]

  • 12 April 2023
    Wind Farm Update

    The world’s deepest fixed-bottom wind turbine foundation has been installed at what will be Scotland’s largest offshore wind farm – Seagreen – off the coast of Angus. On Friday, 7 April, the jacket foundation was transported to the project site on a barge operated by the main contractor, Seaway 7, where it was met by […]

  • 8 July 2020
    Business & Finance, Wind Farm Update

    Statkraft has signed a long-term power purchase agreement (PPA) to purchase 50% of the output from the 1,075 MW Seagreen offshore wind project in Scotland. Statkraft said that the deal is the largest in its UK PPA portfolio, which now stands at 10TWhs. “As part of our project financing we required an off-taker with a […]

  • 13 December 2021
    Authorities, Wind Farm Update

    Scottish Government Ministers have approved the Marine Licence application for the 36-turbine Seagreen 1A offshore wind proposal being brought forward by SSE Renewables and TotalEnergies. The Marine Licence covers the offshore elements of the project, including an export cable approximately 110 kilometres in length, to connect the project to the grid at Cockenzie in East […]

  • 16 June 2020
    Contracts & Tenders, Wind Farm Update

    Seagreen Wind Energy has finalised the wind turbine supply contract with MHI Vestas Offshore Wind, following the preferred supplier agreement signed at the beginning of June. Under the contract, MHI Vestas is in charge of manufacturing and installing 114 of its V164-10 MW turbines for the Seagreen 1 offshore wind project, which will be built […]

  • 21 November 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    The 1.5GW Seagreen Phase 1 offshore wind project is entering into May 2019’s Contracts for Difference (CfD) auctions, SSE plc, the owner and developer of the project in Scotland, said. 

  • 22 June 2023
    Wind Farm Update

    The final turbine has been installed at Scotland’s largest offshore wind farm, Seagreen, off the coast of Angus. The work was carried out by Cadeler’s wind farm installation vessel Wind Orca, which replaced its sister vessel Wind Osprey in April 2022. Many of the wind turbines are installed in a water depth of more than […]

  • 5 September 2022
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Over 50 jacket foundations have been installed at the 1,075 MW Seagreen wind farm offshore Scotland, according to the latest press release from SSE Renewables. The three-legged jacket foundations, each weighing around 2,000 tonnes, will play a critical role in safely supporting the wind turbines during Seagreen’s 25-year operational lifespan. Installation of the foundations is […]