  • 4 December 2020
    Wind Farm Update

    Ailes Marines reported on 2 December that all the inter-array cables at the Saint-Brieuc offshore wind farm will be buried to minimise the interference for navigation and fishing activities. According to the developer, due to extreme site conditions a commitment to bury half of the cables was made in 2016. Now it has been determined […]

  • 19 September 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 19 September, Iberdrola inaugurated the 496 MW Saint-Brieuc offshore wind project in France, the second largest in the country and the first in Brittany. The offshore wind farm is located 16 kilometres off the northwest coast of France in the Bay of Saint-Brieuc in the English Channel. The project, backed by a EUR 2.4 […]

  • 18 August 2023
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has installed 31 out of 62 Siemens Gamesa SG 8.0-167 DD wind turbines at the Saint-Brieuc offshore wind farm in France. The first wind turbine was installed in May on position number SB44, located in the northern part of the offshore construction site. The wind turbines are manufactured […]

  • 27 March 2023
    Wind Farm Update

    Ailes Marines, a subsidiary of Iberdrola, has announced that the construction works on the 496 MW Saint-Brieuc offshore wind farm are now resuming, saying the installation vessel Aeolus will be continuing pile and drilling installation operations on the remaining wind turbine positions. According to the AIS data, Van Oord’s jack-up vessel is en route to […]

  • 18 December 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 62 wind turbines have been installed at the Saint-Brieuc offshore wind farm in France, developed by Ailes Marines, a 100 per cent subsidiary of Iberdrola. The first wind turbine was installed in May on position number SB44, located in the northern part of the offshore construction site while the last SG 8.0-167 DD unit […]

  • 7 September 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Ailes Marines has selected Eiffage Métal and Engie Solutions to manufacture the offshore substation for the 496 MW wind farm in the Bay of Saint-Brieuc. Eiffage Métal will be in charge of the engineering and construction of the upper part of the substation, housing the transformers and electrical equipment. The company will also fabricate the […]

  • 27 December 2019
    Contracts & Tenders

    Réseau de Transport d’Electricité (RTE) has expanded a recently issued tender for cable storage services to include the Saint-Brieuc offshore wind project in France. In October, RTE issued a tender for storage services for the 225kV submarine power cables, and optionally junctions and accessories, for the Saint-Nazaire, Courseulles-sur-Mer and Fécamp offshore wind projects. According to the […]

  • 14 June 2022
    Wind Farm Update

    The offshore substation topside and jacket foundation for the Saint-Brieuc offshore wind farm have been loaded out onto vessels at their yards in Belgium and the Netherlands, respectively, and will soon be transported to France. The load-out of the 3,400-tonne topside took place on 11 June at the assembly yard of Smulders’s joint venture partner […]

  • 29 June 2020
    Contracts & Tenders, Vessels, Wind Farm Update

    French offshore wind developer Ailes Marines has awarded Specialist Marine Consultants (SMC) with a contract to provide vessel inspection services to support the construction of the Saint-Brieuc offshore wind farm. SMC will be providing up to three local Accredited Vessel Inspectors (AVIs) to the project. SMC’s French inspectors will be supported by the company’s back-office […]

  • 16 April 2020
    Contracts & Tenders, Wind Farm Update

    Van Oord has signed a preparatory works agreement with Iberdrola for the installation of 62 jacket foundations at the 496 MW Saint-Brieuc wind farm offshore France. Located approximately 16 kilometres off the coast of Brittany, the Saint-Brieuc offshore wind farm will comprise 62 Siemens Gamesa 8 MW wind turbines installed over an area covering 75 square […]

  • 25 July 2019
    Authorities, Wind Farm Update

    The French Council of State has rejected appeals opposing the construction of the Bay of Saint-Brieuc offshore wind project being developed by Ailes Marines. Environmental conservation organization Gardez les caps and Nass & Wind, who competed in the tender for developing the wind farm, submitted the appeal citing irregularity in the selection procedure and seeking an annulment. Despite […]

  • 4 July 2022
    Wind Farm Update

    The first wind turbine foundation at the Saint-Brieuc offshore wind farm has been installed, the developer Ailes Marines informed today, 4 July. Using Subsea 7’s Seven Borealis vessel, Van Oord installed the first jacket foundation, located in the northern part of the project site and has already started installing the second one in the same […]

  • 22 November 2023
    Business development, Innovation, Jobs & Recruitment, Operations & Maintenance

    Iberdrola France has launched its platform to identify and collaborate with companies committed to renewable energy and offshore wind for upcoming calls for tenders. According to Iberdrola, the company’s goal is to integrate new partners into the Iberdrola France network to facilitate collaboration on territories and future offshore wind projects. Iberdrola France is organising a […]

  • 1 December 2020
    Contracts & Tenders

    A consortium led by Atos has secured a contract to implement mission-critical communication solutions for the Saint-Brieuc offshore wind project in France. Atos will implement a full operational marine coordination center located in Pleudaniel, Brittany, to coordinate, monitor and document all traffic in and around the project construction area. The center will enable Ailes Marines teams to […]

  • 2 July 2024
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    Iberdrola has contracted DNV for power curve verification at the recently commissioned 496 MW Saint-Brieuc offshore wind farm in France so the developer could align actual energy production with initial projections and improve the accuracy of economic models for the wind farm. DNV will perform the work by employing advanced nacelle lidar technology, the global […]

  • 3 February 2025
    Operations & Maintenance, Ports & Logistics

    Iberdrola has inaugurated the operation and maintenance (O&M) base for the 496 MW Saint-Brieuc offshore wind farm in France. According to Iberdrola, 80 people will work in the O&M centre located in Binic-Établesm. The base controls and manages the electricity production and maintenance of the wind farm, playing a crucial role in its performance to […]

  • 15 June 2022
    Contracts & Tenders, Operations & Maintenance, Wind Farm Update

    Equans has picked Miros’ dry-mounted Wavex virtual sensor to collect operation-critical wave and current data on the offshore substation for the Saint-Brieuc offshore wind farm, located around 16 kilometres off the coast of Brittany, France. Wavex is designed for highly accurate wave and current measurements that can calculate and display directional wave and surface current […]

  • 8 February 2021
    Business & Finance, Wind Farm Update

    Iberdrola has launched a green hybrid bond amounting to EUR 2 billion and will use the raised funds to finance and refinance the Saint-Brieuc and Baltic Eagle offshore wind farms in France and Germany, respectively. The company said that this was the largest green hybrid bond issue in its history and that, in just one month, […]

  • 28 August 2023
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    The installation of the jacket foundation piles at the Saint-Brieuc offshore wind farm in France has been completed and Van Oord’s vessel Aeolus, which was being used to perform the work, has now left the project site, Ailes Marines, the project development company wholly owned by Iberdrola, said on 28 August. All locations that (will) […]

  • 26 August 2022
    R&D, Wind Farm Update

    Van Oord has installed 24 out of 62 jacket foundations for the 496 MW Saint-Brieuc wind farm offshore France. The installation of the jackets started on 1 July, while the first four units were placed on the seabed a few weeks later. Meanwhile, Van Oord’s vessel Aeolus continues with pre-piling work at the remaining foundation locations. To […]

  • 6 May 2020
    Business & Finance

    Van Oord is set to start its offshore operations at the French Saint-Brieuc offshore wind farm in 2021 with the installation of pin piles. The Dutch company will use its installation vessel Aeolus, which will in 2022 be assisted by a second vessel to install the jackets foundations. In April, Van Oord revealed it had […]

  • 19 July 2022
    Wind Farm Update

    The installation of the first four jacket foundations has been completed at the Saint-Brieuc offshore wind farm in France. The installation of the foundations started at the beginning of this month, with the first jacket installed on 4 July by Van Oord using Subsea 7’s Seven Borealis vessel. The jackets have been installed on drilled […]

  • 19 May 2021
    Grid Connection, Wind Farm Update

    Offshore substation (OSS) topsides for the French Saint-Brieuc and Scottish Neart na Gaoithe offshore wind farms have been moved out of Engie Solutions and HSM Offshore’s factories in Belgium and the Netherlands, respectively. Ailes Marines selected a joint venture between Engie Solutions and Iemants (a subsidiary of Smulders) to manufacture the offshore substation for the […]

  • 7 May 2021
    Wind Farm Update

    Local fishermen have taken their protests against the construction of the French Saint-Brieuc offshore wind farm from land to the offshore project site on 7 May, when 70 fishing boats surrounded the Aeolus installation vessel in the Bay of Saint-Brieuc. To voice their opposition to the project, the fishermen have also fired distress flares while […]

  • 29 May 2020
    Contracts & Tenders, Wind Farm Update

    Iberdrola’s Ailes Marines and Siemens Gamesa have signed a contract for the supply of 62 Siemens Gamesa 8 MW wind turbines for the Saint-Brieuc offshore wind project. The contract marks the final investment decision on the EUR 2.4 billion project, Ailes Marines said. The Saint-Brieuc wind turbines will be built in France, at Siemens Gamesa’s […]

  • 19 September 2023
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The Navantia-Windar consortium has loaded out and shipped the last three jacket foundations for the Saint-Brieuc offshore wind farm from Navantia’s yard in Fene, Spain. In April 2021, the assembly of the first jacket foundation was completed at the Navantia Seanergies shipyard in Fene. Just over a year later, in June 2022, the first four […]