402 results found for 'Coastal Virginia Offshore Wind'

402 results found for 'Coastal Virginia Offshore Wind'
Order results by

A list of search results

  • 20 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    CS Wind Offshore has loaded out the final batch of transition pieces (TPs) for Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, currently under construction in the US. The company signed a contract with Dominion Energy in November 2021 and started production at the Port of Aalborg, Denmark, in March 2023. In April […]

  • 22 January 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    Wind turbine installation on Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) has started with the first of the project’s 176 Siemens Gamesa 14 MW wind turbines currently being erected. Virginia-based broadcaster WAVY reported on 21 January that a wind turbine tower was being installed at the CVOW site, next to the two existing […]

  • 30 January 2026
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first wind turbine is now in place at the Coastal Virginia Offshore Wind (CVOW) site in the US. The 2.6 GW offshore wind farm, owned by Dominion Energy, will comprise 176 Siemens Gamesa 14 MW wind turbines and will be able to generate enough electricity to power over 900,000 homes once fully operational, according […]

  • 17 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US District Court for the Eastern District of Virginia has granted Dominion Energy’s request for a preliminary injunction allowing construction to resume on the Coastal Virginia Offshore Wind (CVOW) project while the company’s lawsuit challenging the stop-work order proceeds. “Our team will now focus on safely restarting work to ensure CVOW begins delivery of […]

  • 3 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    All monopiles and almost half of the transition pieces (TPs) have been installed at the Coastal Virginia Offshore Wind (CVOW) project site, with wind turbine installation expected to start this month and the project anticipated to produce first power at the beginning of next year. The offshore wind turbine installation vessel (WTIV) Charybdis arrived at […]

  • 12 February 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US government will fight the federal court decisions to grant preliminary injunctions in cases challenging the stop-work orders for offshore wind projects under construction, issued on 22 December 2025. The injunctions allowed the construction to resume while the underlying lawsuits are underway. The US Secretary of the Interior, Doug Burgum, told Bloomberg Television the […]

  • 3 November 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Dominion Energy said in its third-quarter 2025 results that recently imposed US tariffs have been incorporated into the updated cost estimate for the Coastal Virginia Offshore Wind (CVOW) project. The company now places total capital costs for the 2.6 GW offshore wind farm at approximately USD 11.2 billion (approximately EUR 9.7 billion), up from about […]

  • 3 February 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    All five US offshore wind farms under construction that received stop-work orders from the US government have been cleared to continue building, with Ørsted’s Sunrise Wind project the fifth project to be granted a preliminary injunction as part of a lawsuit challenging the order issued by the Director of the Department of the Interior’s Bureau […]

  • 23 December 2025
    Authorities, Planning & Permitting, Project Updates, Safety, Wind Farm Update

    The US Department of Interior has paused the leases and suspended construction at all large-scale offshore wind projects currently under construction in the United States, citing ”national security risks identified by the Department of War in recently completed classified reports.” The five projects have a combined capacity of 5.8 GW and include Coastal Virginia Offshore […]

  • 19 September 2025
    Vessels

    Charybdis, the first Jones Act-compliant offshore wind turbine installation vessel (WTIV), has arrived at Portsmouth Port ahead of its work at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the US. The vessel, built in the US, sailed into Portsmouth Port on 17 September, according to the ship’s AIS data available online. With […]

  • 16 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US District Court for the District of Columbia has granted a preliminary injunction sought by Equinor for its Empire Wind 1 offshore wind farm, allowing construction activities to resume on the project that was more than 60 per cent complete at the time when the US government issued a stop-work order in December 2025. […]

  • 29 December 2025
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Dominion Energy has filed a federal lawsuit challenging the Trump administration’s stop-work order issued on 22 December that directed all major US offshore wind projects under construction to pause while federal agencies review alleged national security risks, AP and US media report. In its complaint filed in the US District Court for the Eastern District […]

  • 2 January 2026
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    On New Year’s Day, Revolution Wind LLC, the 50/50 joint venture between Ørsted and Skyborn Renewables, filed a supplemental complaint in the US District Court for the District of Columbia and plans to move for a preliminary injunction to block the lease suspension order recently imposed by the US government that stopped construction on its […]

  • 13 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The US District Court for the District of Columbia has granted the preliminary injunction sought by the joint venture between Ørsted and Skyborn Renewables for the Revolution Wind project, which was ordered to pause construction by the US government. When the stop-work order was issued on 22 December 2025, the 704 MW project had seven […]

  • 16 January 2026
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    All five developers with offshore wind farms under construction in the US are now fighting the suspension order issued by the US Department of the Interior (DOI) in December 2025, as Vineyard Wind, a company owned 50:50 by Avangrid and Copenhagen Infrastructure Partners (CIP), said on 15 January that it filed for a temporary restraining […]

  • 5 January 2026
    Authorities, Business & Finance, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Equinor has filed a civil suit in the US District Court for the District of Columbia against the order that suspended construction on five offshore wind projects, including its Empire Wind 1, which is now more than 60 per cent complete. As part of the case, Empire Offshore Wind LLC, an Equinor subsidiary that filed the civil suit on […]

  • 19 February 2026
    Authorities, Business & Finance, Fixed-Bottom, Floating Wind, Planning & Permitting

    The US Department of Justice, Environment & Natural Resources Division, filed a Notice of Appeal on 17 February in the case in which a federal judge ruled in favour of 18 states that sued the Trump administration over the sweeping ban on wind energy projects. In May 2025, seventeen US states and the District of […]

  • 12 September 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    US Interior Secretary Doug Burgum said at a press conference on 10 September that offshore wind has no future in the US under the Trump administration and that the government was reviewing five offshore wind projects that are now under construction. Speaking to the press at the Gastech event in Milan, Italy, Burgum said offshore […]

  • 15 July 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Vessels, Wind Farm Update

    The new cable-laying vessel (CLV) that joined Prysmian’s fleet earlier this year, Monna Lisa, has begun installing its first submarine cable at the Coastal Virginia Offshore Wind (CVOW) project site in the US, where Dominion Energy is building the country’s largest offshore wind farm. Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant […]

  • 15 May 2025
    Business & Finance, Foundations, Industry, Manufacturing, Supply Chain

    Spain-based wind turbine tower supplier, Windar Renovables, has joined the Offshore Wind Foundation Alliance (OWFA), expanding the alliance to seven members. “We believe offshore wind energy stands as a proven and vital component in Europe’s path towards net zero, and European foundation manufacturers provide a crucial part of the wind supply chain. We view OWFA […]

  • 13 August 2024
    Fixed-Bottom, Foundations, Project Updates, Wind Farm Update

    The 50th monopile foundation has been installed at the Coastal Virginia Offshore Wind (CVOW) project site off Virginia Beach in the US, according to Dominion Energy. The developer said on 12 August the 176-turbine project was on schedule to reach the goal of having 70-100 monopiles installed during the first installation season that runs through […]

  • 15 October 2019
    Authorities, Wind Farm Update

    Virginia-based Dominion Energy has received two key determinations from the US Bureau of Ocean Energy Management (BOEM) regarding the design, fabrication and installation of the Coastal Virginia Offshore Wind (CVOW) project. Dominion submitted its Facility Design Report (FDR) and Fabrication and Installation Report (FIR) in partnership with Ørsted, a global offshore wind developer contracted for […]

  • 28 March 2023
    Contracts & Tenders

    Dominion Energy has signed a four-year contract with K2 Management (K2M) for Quality Oversight services for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the United States. The Denmark-headquartered company will serve as Dominion Energy’s Owner’s Quality Assurance (QA) Representative and, among other services, will provide Quality Oversight at suppliers’ manufacturing facilities for […]

  • 16 February 2021
    Business & Finance, Vessels

    Atlantic Wind Transfers’ new crew transfer vessel (CTV) Atlantic Endeavor has begun working at the Coastal Virginia Offshore Wind (CVOW) project. Blount Boats launched the Chartwell 24 CTV the day after Christmas, after which the vessel spent three days going through sea trials and USCG inspections. At the CVOW project, Atlantic Endeavor is providing marine […]

  • 29 June 2020
    Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has installed the second and final turbine at the Coastal Virginia Offshore Wind (CVOW) pilot project in the U.S. The two Siemens Gamesa SWT-6.0-154 units, which are the first wind turbines installed in U.S. federal waters, will now undergo acceptance testing before being energized later this summer. According […]

  • 26 May 2020
    Contracts & Tenders, Grid Connection

    Tekmar Group has revealed the involvement of its operating companies in the 12 MW Coastal Virginia Offshore Wind (CVOW) project in the U.S. Tekmar Energy supplied Seaway 7 with TekLink cable protection systems and TekDuct cable crossing protection for the construction phase of the project. AgileTek Engineering performed product design verification analysis on behalf of […]