389 results found for 'Coastal Virginia Offshore Wind'

389 results found for 'Coastal Virginia Offshore Wind'
Order results by

A list of search results

  • 20 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    CS Wind Offshore has loaded out the final batch of transition pieces (TPs) for Dominion Energy’s 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, currently under construction in the US. The company signed a contract with Dominion Energy in November 2021 and started production at the Port of Aalborg, Denmark, in March 2023. In April […]

  • 15 July 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Vessels, Wind Farm Update

    The new cable-laying vessel (CLV) that joined Prysmian’s fleet earlier this year, Monna Lisa, has begun installing its first submarine cable at the Coastal Virginia Offshore Wind (CVOW) project site in the US, where Dominion Energy is building the country’s largest offshore wind farm. Dominion Energy selected the consortium of DEME Group and Prysmian as the Balance of Plant […]

  • 3 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    All monopiles and almost half of the transition pieces (TPs) have been installed at the Coastal Virginia Offshore Wind (CVOW) project site, with wind turbine installation expected to start this month and the project anticipated to produce first power at the beginning of next year. The offshore wind turbine installation vessel (WTIV) Charybdis arrived at […]

  • 3 November 2025
    Business & Finance, Fixed-Bottom, Project Updates, Wind Farm Update

    Dominion Energy said in its third-quarter 2025 results that recently imposed US tariffs have been incorporated into the updated cost estimate for the Coastal Virginia Offshore Wind (CVOW) project. The company now places total capital costs for the 2.6 GW offshore wind farm at approximately USD 11.2 billion (approximately EUR 9.7 billion), up from about […]

  • 19 September 2025
    Vessels

    Charybdis, the first Jones Act-compliant offshore wind turbine installation vessel (WTIV), has arrived at Portsmouth Port ahead of its work at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the US. The vessel, built in the US, sailed into Portsmouth Port on 17 September, according to the ship’s AIS data available online. With […]

  • 12 September 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    US Interior Secretary Doug Burgum said at a press conference on 10 September that offshore wind has no future in the US under the Trump administration and that the government was reviewing five offshore wind projects that are now under construction. Speaking to the press at the Gastech event in Milan, Italy, Burgum said offshore […]

  • 15 May 2025
    Business & Finance, Foundations, Industry, Manufacturing, Supply Chain

    Spain-based wind turbine tower supplier, Windar Renovables, has joined the Offshore Wind Foundation Alliance (OWFA), expanding the alliance to seven members. “We believe offshore wind energy stands as a proven and vital component in Europe’s path towards net zero, and European foundation manufacturers provide a crucial part of the wind supply chain. We view OWFA […]

  • 21 April 2025
    Business & Finance, Cables, Grid Connection, Project Updates, Vessels

    Prysmian’s new cable laying vessel (CLV) Monna Lisa has been loaded for the first time with submarine cable, destined for what will become the largest US offshore wind farm once operational. Prysmian reported two days ago that the submarine cable for Dominion Energy’s Coastal Virginia Offshore Wind (CVOW) project was being loaded on Monna Lisa […]

  • 25 March 2025
    Ports & Logistics

    Sweden-headquartered construction company Skanska has completed the redevelopment of the Portsmouth Marine Terminal in the US. According to the Port of Virginia, the USD 220 redevelopment project of Portsmouth Marine Terminal was completed earlier this month on time and on budget. The project upgraded 72 acres and 1,500 feet of wharf, transforming the terminal into […]

  • 14 March 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of three offshore substations has been installed at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, located 43 kilometres off the coast of Virginia Beach, the US. The 3,907-metric tonne lift marks the completion of the installation of the first topside onto the jacket, which was previously installed by DEME. According to […]

  • 15 April 2025
    Business development, Floating Wind, Industry, Innovation, Market Outlooks, Outlook & Strategy, Technology

    Despite uncertainty about US markets, one thing is for sure: Norwegian companies still believe in both short-term and long-term opportunities in US offshore wind. Norwegian offshore wind suppliers, including Autronica, DOF and Uptime International, are forging ahead with plans to expand their activities in the US. Meet Autronica, DOF and Uptime International – at the […]

  • 4 March 2025
    Industry, Market Outlooks, Outlook & Strategy

    According to research from Norway-headquartered Rystad Energy, the global offshore wind industry is set for a rebound in 2025, with capacity additions expected to reach 19 GW and sector-wide expenditure projected to hit USD 80 billion (approximately EUR 76 billion). A record wave of lease auctions is driving the resurgence, said Rystad Energy, with the […]

  • 18 February 2025
    Vessels

    The sea trials have commenced and are in progress for Charybdis, the first Jones Act-compliant wind turbine installation vessel (WTIV), built in the US. Under construction at Seatrium’s AmFELS shipyard in Brownsville, Texas, the vessel also recently completed the jacking trial and main crane load testing. Commissioned by Dominion Energy, the vessel is 96 per […]

  • 4 February 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    On 3 February, Dominion Energy announced that the estimated total costs for the Coastal Virginia Offshore Wind (CVOW) project have increased by nine per cent. In addition, the developer said that the 2.6 GW wind farm is now approximately 50 per cent complete and remains on track for on-time completion at the end of 2026. […]

  • 23 January 2025
    Fixed-Bottom, Foundations, Project Updates, Wind Farm Update

    The heavy load carrier Sun Rise is on its way to the US from the Port of Aalborg, Denmark, with 18 transition pieces (TPs) for the wind turbine foundations at the Coastal Virginia Offshore Wind (CVOW) project. According to a social media post by CS Wind Offshore, which is delivering 176 TPs for the 2.6 […]

  • 29 January 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first of three offshore substations for the Coastal Virginia Offshore Wind (CVOW) project has arrived at the Portsmouth Marine Terminal in the US. In 2021, a consortium including Semco Maritime and CS Wind Offshore (formerly Bladt Industries) secured a contract to supply three 880 MW substations for the offshore wind project developed by Dominion […]

  • 4 February 2025
    Authorities, Planning & Permitting

    The New Jersey Board of Public Utilities (NJBPU) has cancelled the bidding process for the state’s fourth offshore wind solicitation, citing uncertainty caused by recent federal actions and Shell’s withdrawal from the Atlantic Shores offshore wind project. The state’s fourth round of offshore wind solicitation was launched in May 2024, initially aimed at awarding between […]

  • 20 January 2025
    Business & Finance, Business development, Industry, Manufacturing, Supply Chain

    According to a report released earlier this month, the US offshore wind supply chain spans 40 states as of December 2024, with 1,932 supplier contracts signed for offshore wind and offshore wind-related projects. The report, Offshore Energy at Work, issued by the US offshore renewable energy industry organisation, Oceantic Network on 15 January, shows that […]

  • 13 August 2024
    Fixed-Bottom, Foundations, Project Updates, Wind Farm Update

    The 50th monopile foundation has been installed at the Coastal Virginia Offshore Wind (CVOW) project site off Virginia Beach in the US, according to Dominion Energy. The developer said on 12 August the 176-turbine project was on schedule to reach the goal of having 70-100 monopiles installed during the first installation season that runs through […]

  • 15 October 2019
    Authorities, Wind Farm Update

    Virginia-based Dominion Energy has received two key determinations from the US Bureau of Ocean Energy Management (BOEM) regarding the design, fabrication and installation of the Coastal Virginia Offshore Wind (CVOW) project. Dominion submitted its Facility Design Report (FDR) and Fabrication and Installation Report (FIR) in partnership with Ørsted, a global offshore wind developer contracted for […]

  • 7 January 2025
    Business & Finance

    The European Commission (EC) has approved the acquisition of joint control of EEW Offshore Wind EU by EEW Holding and Japanese trader Sumitomo Corporation. The transaction relates primarily to the manufacturing of large steel tubes used in the construction of offshore wind farms. The Commission concluded that the notified transaction would not raise competition concerns, […]

  • 28 March 2023
    Contracts & Tenders

    Dominion Energy has signed a four-year contract with K2 Management (K2M) for Quality Oversight services for the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the United States. The Denmark-headquartered company will serve as Dominion Energy’s Owner’s Quality Assurance (QA) Representative and, among other services, will provide Quality Oversight at suppliers’ manufacturing facilities for […]

  • 16 February 2021
    Business & Finance, Vessels

    Atlantic Wind Transfers’ new crew transfer vessel (CTV) Atlantic Endeavor has begun working at the Coastal Virginia Offshore Wind (CVOW) project. Blount Boats launched the Chartwell 24 CTV the day after Christmas, after which the vessel spent three days going through sea trials and USCG inspections. At the CVOW project, Atlantic Endeavor is providing marine […]

  • 29 June 2020
    Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has installed the second and final turbine at the Coastal Virginia Offshore Wind (CVOW) pilot project in the U.S. The two Siemens Gamesa SWT-6.0-154 units, which are the first wind turbines installed in U.S. federal waters, will now undergo acceptance testing before being energized later this summer. According […]

  • 26 May 2020
    Contracts & Tenders, Grid Connection

    Tekmar Group has revealed the involvement of its operating companies in the 12 MW Coastal Virginia Offshore Wind (CVOW) project in the U.S. Tekmar Energy supplied Seaway 7 with TekLink cable protection systems and TekDuct cable crossing protection for the construction phase of the project. AgileTek Engineering performed product design verification analysis on behalf of […]

  • 15 January 2025
    Authorities, Fixed-Bottom, Floating Wind, Planning & Permitting

    NOTE: This article was updated on 15 January at 21:50 CET following information offshoreWIND.biz received, attributing the drafting of the executive order halting offshore wind activities on the US East Coast to Congressman Jefferson Van Drew instead of the US President-elect Donald Trump himself. The article was further amended to state that lease, rather than […]