380 results found for 'BorWin6'

380 results found for 'BorWin6'
Order results by

A list of search results

  • 9 February 2026
    Grid Connection, Offshore Platforms, Project Updates

    Mammoet has completed the transport, load-out and mooring of the jacket foundation for the BorWin kappa offshore converter platform at McDermott’s yard in Dubai, UAE. BorWin kappa is part of TenneT’s 980 MW BorWin6 offshore wind grid connection in the German North Sea. The Dutch company has been selected as a subcontractor to provide jacking, […]

  • 18 February 2026
    Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain

    McDermott has cut first steel for the offshore converter platform for TenneT’s LanWin1 offshore grid connection in Germany. The LanWin1 project will include an offshore converter station in the North Sea and an onshore converter station in the region of Wesermarsch. The platform will be delivered under a contract GE Vernova and McDermott International signed with the […]

  • 23 September 2025
    Business & Finance, Contracts & Tenders, Supply Chain

    EnBW has selected HTM Helicopter Travel Munich and HeliService to provide helicopter transport services for the company’s offshore wind farms in the German North Sea. HTM Helicopter Travel Munich and HeliService were selected to provide aerial and related services for EnBW’s Hohe See, Albatros, and He Dreiht offshore wind farms in Germany. EnBW plans to […]

  • 30 October 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Vattenfall has received the green light from Germany’s Federal Maritime and Hydrographic Agency (BSH) for the construction and operation of the Nordlicht 2 offshore wind farm in the North Sea. On 29 October, BSH granted planning approval for Vattenfall’s 630 MW Nordlicht 2, which will be built in area N-6.6, located more than 84 kilometres […]

  • 21 January 2026
    Fixed-Bottom, Operations & Maintenance, Project Updates, Vessels, Wind Farm Update

    Vard has delivered a new vessel built for Norwind Offshore, Norwind Maestro, which will be deployed on a German offshore wind farm. The new commissioning service operations vessel (CSOV) is built to the VARD 4 19 design and constructed at Vard Shipyards Romania, with final outfitting, commissioning, and completion carried out at Vard Søviknes in […]

  • 8 October 2025
    Vessels

    Vard has cut the first steel for Norwind Offshore’s energy construction vessel (ECV), the first vessel of this category, according to the two companies. A steel-cutting ceremony was held on 6 October at Vard Vung Tau shipyard in Vietnam, kicking off the construction of the vessel, which Norwind Offshore ordered last year. Vard says the ECV […]

  • 28 August 2025
    Cables, Grid Connection, Offshore Platforms

    Denmark’s NKT has finalised the installation of a 320 kV high-voltage DC (HVDC) power cable system at the 900 MW BorWin5 offshore grid connection in Germany. The pull-in work to the offshore platform was carried out by the company’s NKT Victoria vessel. NKT was responsible for the delivery and installation of 230 kilometres of 320 […]

  • 25 February 2026
    Vessels

    Allseas’ new cargo barge Braveheart, built by the CIMC Changhong Shipyard, which held a keel-laying ceremony for the new vessel in April 2025, has now departed China for the Netherlands. Braveheart was purpose-built to fit precisely within Pioneering Spirit‘s bow slot to enable seamless transfer of offshore structures, from decommissioned platforms heading ashore to newly […]

  • 4 March 2026
    Business & Finance, Vessels

    Edda Wind has entered into agreements for the potential sale of its fleet of service operation vessels (SOVs) and commissioning SOVs (CSOVs), including newbuilds, with two buyers amongst which the fleet will be split: North Star and an affiliate of Navigare Capital Partners. The vessel operator said on 4 March that additional information would be […]

  • 15 December 2025
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Jan De Nul has installed three HVAC subsea cables, delivered by Hellenic Cables, between TenneT’s offshore converter station DolWin kappa and Nordseecluster 1 and 2 sites in the German North Sea. The two locations make up the 660 MW Nordseecluster A offshore wind farm, which itself is part of a bigger, two-phased Nordseecluster project. With […]

  • 12 December 2025
    Business & Finance, Innovation, Supply Chain

    The Crown Estate, through its Supply Chain Accelerator programme, has awarded GBP 13 million (nearly EUR 15 million) to 16 UK offshore wind supply chain projects in the early stage of development to help de-risk them and accelerate their path to the market. The second round of the Supply Chain Accelerator, which is awarding nearly […]

  • 8 September 2025
    Business & Finance, Grid Connection

    RWE and the global asset manager and infrastructure investor, Apollo Global Management, have signed an agreement under which Apollo will pay EUR 3.2 billion to RWE in exchange for an equity stake in a to-be-established joint venture (JV), which will hold RWE’s existing 25.1 per cent stake in the German transmission system operator (TSO) Amprion. […]

  • 4 August 2025
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    The German subsidiary of Denmark’s Semco Maritime, Wind Multiplikator, has signed a long-term charter agreement with Norwind Offshore to deploy a Commissioning Service Operation Vessel (CSOV) on the Global Tech I offshore wind farm in the German North Sea. The vessel Norwind Maestro is scheduled for delivery in the first quarter of 2026, with a […]

  • 25 July 2025
    Authorities, Business & Finance, Grid Connection

    TenneT Holding is exploring two options to meet TenneT Germany’s equity requirements: a private placement of shares and an initial public offering (IPO), and expects to decide on which option to proceed with in September. The German government has not yet excluded the possibility of buying into the German transmission system operator (TSO). On 15 […]

  • 1 July 2025
    Cables, Project Updates, Wind Farm Update

    All inter-array cables have been installed at EnBW’s He Dreiht offshore wind farm in the German North Sea. Seaway7 said on 1 July it completed the installation of the last inter-array cable, connecting the 13th and last string of the He Dreiht project to the BorWin epsilon converter platform, part of the BorWin5 grid connection. […]

  • 10 June 2025
    Grid Connection, Offshore Platforms

    The DolWin epsilon converter platform, part of the DolWin5 offshore grid connection, has been installed in the German North Sea. After three years of construction at Seatrium’s shipyard in Singapore, the 82-metre-long platform has covered approximately 13,000 nautical miles to Norway in 60 days. There, Aibel and Hitachi Energy installed the final technical equipment, including […]

  • 4 June 2021
    Contracts & Tenders, Grid Connection

    TenneT has awarded several companies and consortia with contracts for consultative engineering and construction services for the offshore transformer stations that will be part of the BorWin5 and BorWin6 offshore grid connections in Germany. A consortium between Fichtner and SeaRenergy will deliver the services for both platforms, while DNV GL, Lloyd’s Register and TÜV Rheinland […]

  • 16 June 2025
    Grid Connection, Offshore Platforms

    The first steel has been cut for the BalWin1 and BalWin2 grid connection systems that will be installed in the German North Sea. Last week, Meyer Werft, together with the German transmission system operator (TSO) Amprion, Dragados Offshore, and Siemens Energy, celebrated the start of production of the converter platforms for the BalWin1 and BalWin2 […]

  • 15 December 2021
    Contracts & Tenders, Grid Connection

    TenneT has opened a tender for ground investigation work to be performed offshore Germany, where the transmission system operator (TSO) will install the BorWin kappa offshore converter platform as part of the BorWin6 offshore grid connection. The TSO is looking to award a contract for the execution of main ground investigation for a specific type of […]

  • 6 July 2022
    Contracts & Tenders, Grid Connection

    Nexans has won the contract for cabling work on the BorWin6 offshore grid connection in Germany, which TenneT awarded following a tendering process. Under the contract with TenneT, awarded through a tendering process, Nexans is responsible for the production and laying of cables, including the sea, tidal flat, and land cables.  The cable laying work […]

  • 27 March 2023
    Contracts & Tenders, Grid Connection

    Bohlen & Doyen, a subsidiary of the German energy infrastructure construction company Friedrich Vorwerk Group, has signed a contract with French cable manufacturer Nexans to build the onshore cable connection for the BorWin6 offshore wind grid in Germany. The total volume of the order is in the mid-two-digit million range, according to a press release […]

  • 5 July 2023
    Grid Connection

    The construction work has begun on the BorWin6 High-Voltage Direct Current (HVDC) project which will be delivered by TenneT to link 980 MW of offshore wind capacity to the German grid. Through a consortium with Global Energy Interconnection Research Institute and C-EPRI Electric Power Engineering (GEIRI/CEPRI), McDermott is providing engineering, procurement, construction, installation, and commissioning […]

  • 28 March 2022
    Contracts & Tenders, Grid Connection

    VCE Vienna Consulting Engineers ZT has been awarded a contract to install Structural Health Monitoring (SHM) systems on twelve TenneT’s HVDC platforms in Germany. On nine platforms, which are in operation, the installation of the SHM systems will be carried out offshore during operation, while for the three platforms which are under construction or in […]

  • 12 March 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a periodic indicative notice to carry out the market investigation on the planned procurement of the BorWin6 HVDC cable system. All potential and interested market participants are invited to express their interest in the market investigation and to provide an overview of the current status of the planning documents. Located in the […]

  • 4 December 2020
    Contracts & Tenders, Grid Connection

    TenneT TSO GmbH has issued a tender notice for the design, manufacture, installation, and commissioning of the BorWin6 converter platforms. Located in the North Sea Cluster 7, the 900 MW BorWin6 is scheduled to be commissioned by 2027. The offshore grid connection will collect the three-phase electric power generated at an offshore wind farm to […]

  • 21 September 2021
    Contracts & Tenders, Grid Connection

    TenneT has issued a call for tenders for Structural Health Monitoring systems (SHM systems) and their installation on twelve offshore HVDC platforms, including both existing and platforms yet to be installed offshore. Under a five-year, EUR 3.25 million contract, the tender winner will develop and install a monitoring concept for the support structures of the […]