440 results
A list of search results
-
DEME Offshore’s newbuild jack-up vessel Apollo is currently undergoing mobilization for the Moray East offshore wind project at Damen Shiprepair Dunkerque in France. The multi-purpose, self-propelled jack-up vessel will carry out one-month mobilization to prepare for pre-piling works at the 950MW project in the UK. Apollo was constructed by Croatian shipbuilder Uljanik Shipyard and was delivered to DEME in […]
-
Business & Finance, Contracts & Tenders, Grid Connection, Technology, Wind Farm Update
Moray Offshore Windfarm (East) Ltd and Siemens have signed a Preferred Bidder Agreement (PBA) for the onshore works, and offshore substation platform topsides for the 950MW Moray East offshore wind farm.
-
Work has commenced on the onshore sites of the Moray East offshore wind project in Scotland after a break due to the coronavirus crisis. At the end of March, Moray Offshore Windfarm (East) Ltd announced the demobilization of work at the project’s onshore sites, including the new underground cable and substation in Aberdeenshire. Following the […]
-
According to the latest update from the Moray East project, there are now 64 wind turbines installed at the site off the Aberdeenshire coast, which puts Moray East ahead of Scotland’s Beatrice offshore wind farm in terms of installed capacity. With each Vestas turbine having an output of 9.5 MW, Moray East is now on […]
-
The Kansai Electric Power Co., Inc (KEPCO) and Mitsubishi UFJ Lease & Finance Company Limited (MUL) have acquired stakes in the Moray East offshore wind project in Scotland.
-
Contracts & Tenders, Grid Connection
Siemens has placed multi-million pound contracts with companies across the UK for the construction of the transmission infrastructure for the Moray East offshore wind farm. As the lead contractor for onshore transmission infrastructure construction works for the 950MW wind farm, Siemens has placed several subcontracts since work began in September 2018. BAM Nuttall has been […]
-
Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update
Boskalis has secured a contract for the supply and installation of the inter-array cables for the Moray East offshore wind farm in Scotland.
-
Denmark’s Welcon has received an order from MHI Vestas to deliver tower sections for the 950MW Moray East wind farm offshore Scotland. In total, Welcon will manufacture and deliver 70 bottom sections, 34 middle sections and 34 top sections for the project. The sections are scheduled to be delivered from the fourth quarter of 2019 until […]
-
Contracts & Tenders, Ports & Logistics, Wind Farm Update
Ayrshire-based Windhoist Limited has won a contract to provide local technicians to assist with pre-assembly works for Moray East offshore wind farm in Scotland. 20 locally-based technicians have been recruited for the project which commences this month and is expected to reach completion in September 2021. This marks the third scope of works Windhoist has […]
-
Contracts & Tenders, Vessels
Solstad Offshore ASA has secured a contract with GeoSea for the Moray East offshore wind project in the UK. Solstad Offshore will provide the vessel Normand Service, previously Sea Spider, to support wind farm installation operations at the 950MW project. The vessel will be chartered for a period of 180 days firm, with up to […]
-
Grid Connection, Wind Farm Update
The third and final offshore transformer module (OTM) has been installed at the Moray East wind farm offshore Scotland. The wind farm’s first OTM was installed on 10 August, and the second unit followed shortly. Siemens Energy secured the contract to connect the wind farm to the grid in 2018. The company is also in charge […]
-
Ports & Logistics, Vessels
Invergordon-based PSG Marine & Logistics Ltd has started loading in and loading out the jacket prepiles and the related equipment from the Port of Cromarty Firth as part of the port marshalling contract awarded by DEME Offshore in support of the Moray East offshore wind project. As reported earlier, DEME’s installation vessel Apollo is carrying out […]
-
The UAE-based Lamprell plans to start delivering the jacket foundations for the Moray East offshore wind farm from its facility in Hamryiah at the end of the first quarter of 2020. The upending of the jackets is ongoing, the company said. Lamprell won a contract to manufacture and deliver 45 wind turbine jacket foundations and three […]
-
Contracts & Tenders, Wind Farm Update
Engie has signed a Power Purchase Agreement (PPA) with Moray Offshore Windfarm (East) Ltd to purchase 23.3% of the electricity generated from the 950MW Moray East wind farm. The PPA is for a 15-year period, starting from commercial operation of the wind farm which is scheduled to commence in 2022. Engie currently holds a 23.3% […]
-
Vessels, Wind Farm Update
40 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The 40th turbine was installed at the site some 22 kilometres off the Aberdeenshire coast on 20 May, the project’s latest Notice of Operations shows. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern installed […]
-
Smulders has sent off the final three upper jackets for the Moray East offshore wind farm from its yard in Hoboken, Belgium, to Newcastle upon Tyne. Smulders will deliver 55 turbine jacket foundations for the project, with the remaining 45 being delivered by Lamprell from its yards in the United Arab Emirates. The 55 jackets are […]
-
UAE-based Lamprell has held a steel cutting ceremony to mark the start of construction of jacket foundations for the 950MW Moray East wind project offshore Scotland. GeoSea, part of DEME Offshore, the Engineering, Procurement, Construction and Installation (EPCI) contractor for the project’s 100 wind turbine foundations and three offshore substation foundations, contracted Lamprell to fabricate 45 wind turbine and […]
-
Business & Finance, Grid Connection, Wind Farm Update
The TFKable Group has produced the first part of the 220kV onshore high-voltage cable for the Moray East offshore wind farm in the UK. According to the company, the 220kV cable is now ready to be delivered from its Bydgoszcz plant in Poland for the 950MW offshore wind project. TFKable and VolkerInfra won the contract to […]
-
Contracts & Tenders, Vessels
The Island Crown vessel has started working at the Moray East offshore wind farm site, providing accommodation and walk-to-work (W2W) services during the project construction activities. Island Crown has joined the fleet of vessels deployed on the project after Moray Offshore Windfarm (East) Ltd (MOWEL) awarded Island Offshore with a contract for offshore accommodation and […]
-
Operations & Maintenance, Wind Farm Update
EDP has inaugurated the operations and maintenance center of the 950 MW Moray East offshore wind farm, which will now be controlled by this new infrastructure located in Fraserburgh Port, Scotland. This new operations and maintenance center will now manage this offshore wind farm, in particular by controlling the vessel ‘Alba’, which regularly spends two-week […]
-
Gulf Marine Services’ jack-up vessel GMS Endeavour is set to be deployed at the Moray East offshore wind farm site to support the commissioning of the project’s offshore transformer platforms. The vessel will arrive at the project site on or around 19 August, from when it will provide accommodation for workers carrying out commissioning works […]
-
Seajacks Scylla installed the 33rd jacket foundation at the Moray East offshore wind farm site on 20 September, according to the project’s Notice of Operations from 21 September. The jack-up vessel is transporting the jacket foundations to the project site from Global Energy Group’s site in Nigg. The first jacket was installed at the beginning of […]
-
Vessels, Wind Farm Update
32 out of the 100 Vestas V164-9.5MW wind turbines have been installed at the 950 MW Moray East wind farm offshore Scotland. The wind turbine installation is being carried out by Fred. Olsen Windcarrier’s jack-up vessel Bold Tern. The first turbines were installed some 22 kilometres off the Aberdeenshire coast during the second half of […]
-
Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project. Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be completed in January, weather permitting, […]
-
Grid Connection, Wind Farm Update
Work to install the onshore cable which will connect the 950 MW Moray East offshore wind farm to the Scottish grid has ended, Siemens Energy said. The onshore cable, which starts near Banff, Aberdeenshire, takes the power generated offshore from the three 220kV subsea cables, and transmits it to the new onshore substation at New […]
-
Business & Finance, Contracts & Tenders
The Osprey Group has won a contract to provide handling and storage services for the spare export cable for the Moray East offshore wind farm. Under the contract, the company will receive and store approximately 2,500 metres of subsea cable and approximately 1,500 metres of HDD cable to be received from NKT’s cable laying vessel […]