    ArGe Baltic 2 foundations, a Joint Venture between Hochtief and GeoSea, has awarded Ulstein Idea Equipment Solutions BV a contract for the Engineering, Procurement, Construction and Installation (EPCI) of a complete pile upend as well as lifting tool for the Baltic 2 wind farm installation project. By using basic laws of mechanical equilibrium, Ulstein Idea […]

  • 9 February 2015
    Grid Connection, Wind Farm Update

    50Hertz is in charge of connecting EnBW Baltic 2 to the grid.  The German offshore wind farm, being constructed 32 kilometers north of the Baltic island of Rügen, is four times as large as EnBW Baltic 1. With 80 Siemens SWT-3.6-120 turbines, it can produce six times as much power. The construction of EnBW Baltic 2 began in […]

  • 11 January 2013
    Business & Finance

    The European Investment Bank (EIB) has granted a loan of € 500 million to the largest offshore wind farm to date in the German Baltic Sea; EnBW Baltic 2. The project is being realised by EnBW Erneuerbare Energien GmbH. The financing contract was signed today in Karlsruhe. The position and scale of EnBW Baltic 2 […]

  • 29 April 2015
    Wind Farm Update

    EnBW’s offshore wind farm Baltic 2 generated the first kilowatt hour of electricity and fed it into the grid last weekend.  EnBW Baltic 2 is currently being built 32 kilometres north of the island of Rügen in the Baltic Sea. At this point, 60 of a total of 80 wind energy turbines have been installed. Now that […]

  • 22 April 2020
    Operations & Maintenance, Ports & Logistics

    The 288 MW EnBW Baltic 2 offshore wind farm in the German Baltic Sea will be serviced from the Danish port of Klintholm on the island of Møn from August 2020, EnBW said. Until now, the company’s service team of up to 25 has travelled from Rostock to a hotel vessel close to the wind […]

  • 27 August 2014
    Wind Farm Update

    In the development of its second offshore wind farm, Energie Baden-Württemberg AG (EnBW) has reached a milestone with the installation of the first wind turbine at its EnBW Baltic 2 offshore wind farm. In Sassnitz harbor, the installation vessel Vidar had taken on board components for a total of six wind turbines. Yesterday afternoon, the […]

  • 5 May 2021
    Operations & Maintenance, Vessels, Wind Farm Update

    The service operations vessel Esvagt Dana has returned to the Baltic 2 offshore wind farm in the German Baltic Sea to support Siemens Gamesa during maintenance work. Esvagt and Siemens Gamesa entered into a 95-day agreement with an option of a further three months. The vessel provided support in Baltic 2 from November 2019 to […]

  • 15 April 2014
    Wind Farm Update

    All jacket pin piles have been installed at the Baltic 2 offshore wind farm, the project’s developer EnBW confirmed to Offshore WIND. Workers on the jack-up vessel Goliath have driven the jacket pin piles into the seabed. An important part of the work on the foundations is now complete, the company said. Baltic 2 consists […]

  • 6 October 2023
    Contracts & Tenders, Supply Chain

    Van Oord has contracted Jumbo Offshore to transport and install transition pieces (TPs) for Iberdrola’s Baltic Eagle offshore wind project in the German Baltic Sea. Operations on the project are to commence this month. Van Oord recently installed all monopiles and began inter-array cable installation activities at the Baltic Eagle site northeast of the Rügen […]

  • 1 June 2022
    Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Vessels

    EnBW has selected Njord Offshore and FRS Windcat Offshore Logistics to provide crew transfer vessels (CTVs) that will operate on the Baltic 1 and the Baltic 2 offshore wind farms in the German Baltic Sea. Njord Offshore will provide two 12-PAX CTVs for each of the wind farms, and FRS Windcat will supply one 18-PAX […]

  • 27 March 2013
    Grid Connection

    Ballast Nedam has signed a contract for the installation of foundations at the German EnBW Baltic 2 offshore wind farm with ARGE BALTIC 2 Foundations, a joint venture between HOCHTIEF Solutions AG, GeoSea N.V. and HOCHTIEF Offshore Crewing GmbH. Ballast Nedam will erect the project’s 39 monopile and transition piece foundations and provide the logistics […]

  • 20 August 2013
    Wind Farm Update

    The construction of the second offshore wind farm of EnBW Energie Baden-Württemberg AG has entered its late stage: the “Goliath” installation platform left Rostock port on August 16 for its destination – EnBW’s Baltic 2 construction area, which is located 32 kilometres north of the Baltic Sea island of Rügen. Installation has started there on […]

  • 16 April 2013

    Ecosse Subsea Systems (ESS) has reported a successful start to a 10-week boulder clearing and trenching campaign on the Baltic 2 offshore wind farm project. Mobilised onboard the Siem Topaz anchor handling vessel, Ecosse Subsea’s SCAR subsea plough system is engaged on route clearing and pre-lay trenching operations on behalf of Siem Offshore Contractors. Soils […]

  • 31 May 2013

    EnBW is looking for a contractor for the lifting operations taking place in connection with loading of wind turbines onto the installation vessel as well as installation at an offshore windfarm EnBW Baltic 2 of 80 wind turbines. EnBW will need the assistance of lifting supervisors on board the wind turbine installation vessel surveying and […]

  • 26 August 2014

    On 19 August 2014 a new catamaran was christened at Knock Jetty in Emden. The ship’s godmother, Insa Stoidis-Connemann from Leer, gave the name “Windea Two” to the “Twin Axe Bow” type catamaran from Damen Shipyards and she wished: “Safe voyages for the crew and always a handbreadth of water under the keel for the […]

  • 18 April 2013

    After already manufacturing the foundations for the OWF EnBW Baltic 1, EEW Special Pipe Constructions GmbH has now also been appointed with the delivery of 123 Pin Piles (Lot 2) as well as 39 Monopiles and Transition Pieces (Lot 3) for EnBW Baltic 2. The MPs/TPs will be manufactured in a joint venture with Bladt […]

  • 18 November 2011

    Karlsruhe based publicly traded electric utilities company, EnBW, is looking for contractor for monitoring during the construction of offshore wind farms ‘EnBW Baltic 2’, including all necessary logistical and technical services. The scope of investigations are related to sediment and habitat structures, habitat use, hydrographic, benthos, fish, marine fauna (continual users and migration movements), marine […]

  • 18 June 2015
    Business & Finance, Wind Farm Update

    Dutch pension fund manager PGGM is taking part in the new German offshore wind farm Baltic 2. PGGM will invest in the project alongside Macquarie Capital, who agreed to acquire a 49.89 percent stake in the project earlier this year.   This investment is in line with the ambition of PGGM’s clients to use pension money […]

  • 9 August 2011

    nkt cables has entered into a contract with 50Hertz Offshore GmbH at a value of around 750 mDKK (95 mEUR) for the offshore wind farm Baltic 2. For nkt cables, Baltic 2 will be another turnkey project which includes armoured high-voltage subsea cables, accessories and installation. The cables will be manufactured at the production facilities […]

  • 4 November 2014
    Business & Finance, Wind Farm Update

    The order for AMBAU to manufacture 41 transition pieces (TPs) for Bladt Industries A/S to be used in the EnBW Baltic 2 wind farm came to an end on 16 October 2014 as the TPs were loaded for shipment. With a footprint of 13.5 metres, these TPs were the largest components ever to have left the facilities at AMBAU Bremen […]

  • 4 July 2014
    Business & Finance, Operations & Maintenance, Wind Farm Update

    Specialist Marine Consultants Ltd (SMC) has begun another contract with Siemens Wind Power to provide marine coordination. The provision of services for the Baltic 2 offshore wind farm started at the beginning of July 2014 and sees SMC providing marine coordination on five offshore wind farm construction projects at once. Instructed by Siemens, SMC’s innovative […]

  • 14 January 2015
    Wind Farm Update

    With EnBW Baltic 2 in the Baltic Sea, about 32 kilometers north of Rügen, one of the largest offshore wind farms in Germany is under construction at the moment.  At the same time, EnBW is building a service station on the land of the Kraftwerks Rostock. When the wind farm goes into operation, service deployments will be […]

  • 30 June 2014
    Wind Farm Update

    The first set of transition pieces (TPs) for EnBW’s Baltic 2 offshore wind farm has left the port in Rostock on board the installation jack-up platform Goliath on Friday. Two transition pieces per shipment are loaded on the Goliath and then transported in around 12 hours of sailing to their destination in the Baltic 2 […]

  • 1 February 2016

    Specialist Marine Consultants Ltd (SMC) has completed marine coordination work for Siemens on the Baltic 2 offshore wind farm. SMC’s services included coordination of Siemens personnel movements, planning of daily transfers, conducting site inductions, and safety briefings. SMC also covered the event of emergencies and undertook vessel inspections to ensure fitness for purpose and compliance with relevant […]

  • 29 August 2013
    Wind Farm Update

    Bladt’s new facilities at Lindø Industrial Park are nearly all set and the production of the 41 jackets for ENBW Baltic 2 offshore wind farm is well under way. At the moment, almost 100 men are in full swing in the workshops where they have spent the last months preparing these with the so called […]

  • 17 September 2014
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    A 4,400-ton substation for the EnBW Baltic 2 offshore wind farm has been prepared for transport at the shipyard of Abu Dhabi Mar Kiel. Since a very good weather for transportation and installation offshore is expected in the next few days, the platform should be moved directly to the construction field. Should the weather worsen, […]