2104 results found for 'voltaire'

2104 results found for 'voltaire'
Order results by

A list of search results

  • 23 February 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 95th and final wind turbine has been installed at the 1.2 GW Dogger Bank A offshore wind farm, the first phase of the 3.6 GW Dogger Bank Wind Farm in the UK. The wind turbine installation vessel (WTIV) Voltaire, which carried out the installation on Dogger Bank A, is now on its way to […]

  • 3 March 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of the 95 GE Haliade-X 13 MW wind turbines has been installed at Dogger Bank B, the second phase of the 3.6 GW Dogger Bank Wind Farm in the UK. This is according to the information in a Notice to Mariners issued by the project on 2 March, which states the wind turbine installation […]

  • 30 March 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first preparations ahead of offshore construction work at the OranjeWind project site in the Netherlands have begun, as Jan De Nul has started the filter layer installation campaign. In the coming weeks, the rock installation vessel Simon Stevin will install the first layer of erosion protection, which is essential to enable the subsequent installation […]

  • 27 October 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The first high-voltage transformer has been placed on one of four offshore substations that will be installed at the Baltica 2 offshore wind project site in the Polish Baltic Sea. The substations will collect electricity from the 107 Siemens Gamesa 14 MW-222 turbines, stepping up the voltage, and transmitting the electricity to shore. “Installing the transformer […]

  • 9 March 2026
    Business & Finance, Grid Connection

    Lamprell, a UK manufacturer of offshore wind foundations with facilities in the Middle East, and RTE International, a subsidiary of RTE France specialising in electricity transmission engineering, have signed a strategic Memorandum of Understanding (MoU) under which the two companies plan to team up on offshore wind transmission projects. Lamprell said on 9 March that […]

  • 28 October 2025
    Business & Finance, Business development, Cables, Grid Connection, Infrastructure, Innovation, Outlook & Strategy, Technology

    The Offshore Renewable Energy (ORE) Catapult, in partnership with the North East Combined Authority, is investing GBP 2.1 million (around EUR 2.4 million) in a new offshore wind cable testing rig at its facilities in Blyth in North East England. Funded by the North East Combined Authority, the investment will allow ORE Catapult to build […]

  • 17 October 2025
    Grid Connection, Offshore Platforms

    The Dutch/German transmission system operator (TSO) TenneT Germany has commenced the commissioning of the 900 MW DolWin5 offshore grid connection system. Following the completion of the installation campaign in the summer, the consortium of Aibel and Seatrium, together with Hitachi Energy and TenneT, started commissioning as planned in the autumn, said the TSO. In addition […]

  • 6 January 2026
    Business & Finance, Business development

    Danish electrical engineering specialist ProCon Group and Norwegian company Hyndla have completed an all-share merger to form an integrated electrical solutions provider targeting the offshore wind industry, IWS Services, the 75-per-cent-owner of ProCon said on 5 January.   The combined business will operate under the parent company brand. Following the transaction, IWS Services, the offshore […]

  • 15 January 2026
    Vessels

    Vard’s shipyard in Romania has sent Prysmian’s cable-laying vessel (CLV), Alessandro Volta, to Norway, where the construction of the new CLV will be completed. The Norwegian ship designer and shipbuilder commenced construction of the cable-laying vessel in September 2024 at its shipyard in Tulcea, Romania, where the vessel’s hull was erected in September 2025. The vessel is now […]

  • 9 December 2025
    Business & Finance, Business development, Cables, Grid Connection, Innovation, Outlook & Strategy, Research & Development, Transition

    The European Investment Bank (EIB) has approved a EUR 300 million financing package for Prysmian that will support the Italian cabling giant’s research and development (R&D) activities with the ultimate goal of accelerating energy security and digitalization in Europe. The financing will support Prysmian’s European research and development activities for the 2025–2028 period, accelerating the […]

  • 27 January 2026
    Business & Finance, Business development, Cables, Grid Connection, Industry, Outlook & Strategy, Vessels

    UK-based XLCC has rebranded and relaunched as Aquora, with a focus on cable installation and manufacturing to address the “critical demand” for high-voltage cable supply in the UK and Europe. Aquora will focus first on installation, utilising a new, UK-flagged cable-lay vessel (CLV), which will also provide maintenance services for critical infrastructure, and with cable […]

  • 18 November 2025
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    NKT has completed a turnkey repair of one of the 220 kV high-voltage AC subsea export cables connecting the Beatrice offshore wind farm in the Scottish Moray Firth to the Aberdeenshire coast. In April 2025, an unplanned transmission outage occurred on one of two of Beatrice’s Transmission Capital Partner (TCP) -owned export cables, bringing renewable […]

  • 7 January 2026
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Polish state-owned transmission system operator (TSO), Polskie Sieci Elektroenergetyczne (PSE), has confirmed the technical readiness of the transmission infrastructure to accept power from offshore wind farms. “The new Choczewo station and the expanded Żarnowiec station, as well as the 400 kV line connecting them, are ready to transmit energy from wind farms being built in […]

  • 19 December 2025
    Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Four transformers and other high-voltage power equipment necessary for power transfer to the Polish national grid have been delivered to the construction site of the onshore substation for the Baltica 2 offshore wind farm, being built by a joint venture of PGE and Ørsted in the Polish Baltic Sea. The onshore infrastructure for the offshore […]

  • 30 March 2026
    Business & Finance, Ports & Logistics

    An investment of over GBP 30 million (around EUR 35 million) in new facilities that will support offshore wind construction at the Port of Nigg in Scotland has received final approval by Maraen, a new integrated energy infrastructure brand launched by Mitsui & Co. Europe and Mitsui O.S.K. Lines (MOL), which acquired Port of Nigg, […]

  • 9 January 2026
    Cables, Grid Connection, Project Updates

    National Grid Ventures (NGV) has published updated proposals for the LionLink interconnector, which will connect the future Nederwiek 3 offshore wind farm in the Netherlands to the UK and Dutch grids. NGV, responsible for building and operating the UK side of LionLink, has now opened an eight-week public consultation for the revised plan that, among […]

  • 13 October 2025
    Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    Njord Survey has signed a long-term framework agreement with 50Hertz for survey services that will support offshore wind development in the German Baltic Sea. Under the agreement, the Sweden-based offshore survey provider will deliver geophysical and remotely operated vehicle (ROV) seabed surveys, with biofuel to be used by all vessels, which will minimise emissions. Philip […]

  • 21 October 2025
    Business & Finance, Contracts & Tenders, Supply Chain, Technology

    The offshore wind developer Ocean Winds has renewed its Market Intelligence contract with Spinergie for the third consecutive year to strengthen fleet analysis and project benchmarking. Spinergie’s Market Intelligence platform provides real-time and historical insight into global installation and maintenance campaigns. With detailed fleet schedules, specs, and project intelligence, Ocean Winds can identify and secure […]

  • 11 December 2025
    Contracts & Tenders, Fixed-Bottom, Grid Connection, Manufacturing, Offshore Platforms, Supply Chain

    The GE Vernova-Seatrium consortium has been awarded a contract to deliver the offshore converter platform for TenneT’s 2.2 GW BalWin5 offshore grid connection in the German North Sea. The contract is the fourth one awarded under the five-year framework agreement that GE Vernova and Seatrium signed with TenneT in 2023, and marks the consortium’s first […]

  • 30 October 2025
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    Vattenfall has received the green light from Germany’s Federal Maritime and Hydrographic Agency (BSH) for the construction and operation of the Nordlicht 2 offshore wind farm in the North Sea. On 29 October, BSH granted planning approval for Vattenfall’s 630 MW Nordlicht 2, which will be built in area N-6.6, located more than 84 kilometres […]

  • 2 February 2026
    Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    The HSI Joint Venture, comprising HSM Offshore Energy, Smulders, and Iv, has rolled out the topside of the second offshore substation (OSS) for the German offshore wind farm Gennaker at HSM Offshore Energy’s yard in Schiedam, the Netherlands. The joint venture will now work toward the upcoming load-out, sail-away, and offshore installation. The substation, named […]

  • 29 January 2026
    Energy Islands, Foundations, Grid Connection, Project Updates, Supply Chain

    Jan De Nul has constructed and floated the remaining concrete structures for the Belgian Princess Elisabeth Energy Island at the Vlissingen site in the Netherlands. The concrete caissons are now at the Scaldia terminal, where they will undergo final works before being installed offshore this spring. The installation of the caissons started in April last year, […]

  • 2 March 2026
    Business & Finance, Vessels

    OEG has taken the delivery of a multi-purpose crew transfer vessel (CTV), named Fulmar, which recently completed sea trials and will soon be deployed on the Inch Cape offshore wind farm in Scotland. Fulmar will be supporting the offshore construction of the 1.1 GW offshore wind farm under a contract OEG was awarded last year. At […]

  • 31 March 2026
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    Installation of the first of 84 Siemens Gamesa 11 MW wind turbines is underway at the Sunrise Wind project site, located approximately 30 miles (around 48 kilometres) east of Montauk, New York. The installation vessel Wind Scylla, owned by Cadeler, arrived at the site on 25/26 March, according to the vessel’s AIS data available online. According […]

  • 10 February 2026
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Chantiers de l’Atlantique has completed the construction and integration of two offshore electrical substations for the 660 MW Nordseecluster A offshore wind farm, currently under construction off the German coast. Each of the topsides is approximately 40 metres long and 22 metres high, with one weighing about 1,800 tonnes, while the other one comes in […]

  • 28 October 2025
    Authorities, Fixed-Bottom, Floating Wind, Planning & Permitting

    The UK government has set a total budget of GBP 1.08 billion (approximately EUR 1.24 billion) for offshore wind and floating wind in the Contracts for Difference (CfD) Allocation Round 7 (AR7) renewables auction. A total of GBP 900 million has been set for fixed-bottom projects in Pot 3, with delivery years of 2028/29, 2029/30, […]