209 results found for 'neart na gaoithe'

209 results found for 'neart na gaoithe'
Order results by

A list of search results

  • 22 March 2024
    Cables, Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    Cable burial activities at the inter-array routes within the Neart na Gaoithe offshore wind farm site have been completed, following the wrap-up of cable installation works in January. The pre-lay grapnel run (PLGR) along the inter-array cable (IAC) routes was completed in November 2023 by the vessel Pacific Discovery. The PGLR work started in March […]

  • 5 April 2024
    Cables, Fixed-Bottom, Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Italy-headquartered Prysmian has concluded the installation of submarine and land power cables to connect the 450 MW Neart na Gaoithe offshore wind farm to the Scottish mainland power grid. The offshore wind project is now in the testing and commissioning phase and the system is scheduled to go live during 2024. Prysmian designed, supplied, and […]

  • 5 April 2024
    Business development, Grid Connection, Onshore Infrastructure, Research & Development

    National Grid Ventures (NGV) and Con Edison Transmission have submitted plans for building a transmission infrastructure that will connect offshore wind power to the New Jersey electricity grid. The project, named the Garden State Energy Path, proposes laying underground cables that will enable the delivery of approximately 6 GW of offshore wind power from its […]

  • 10 April 2024
    Business & Finance, Floating Wind, Planning & Permitting, Project Updates, Wind Farm Update

    The joint venture company behind the 1 GW Gwynt Glas floating wind project is set to change ownership structure as EDF Renewables UK, which owns Gwynt Glas together with DP Energy, is entering into a partnership with Irish renewable energy developer ESB and UK-headquartered offshore wind investor Reventus Power. DP Energy will remain a development […]

  • 24 October 2023
    Fixed-Bottom, Project Updates, Wind Farm Update

    Saipem has completed the foundation installation works for the Neart na Gaoithe (NnG) wind farm offshore Scotland. Located 15 kilometres off the east coast of Scotland, the NnG offshore wind farm will be able to generate around 450 MW of low-carbon electricity and supply enough energy to the National Grid to power around 375,000 homes. […]

  • 16 August 2023
    Contracts & Tenders, Wind Farm Update

    Global Wind Projects has been awarded a contract by Siemens Gamesa for the pre-assembly of 54 wind turbine towers for the 450 MW Neart na Gaoithe (NnG) offshore wind farm, being developed by EDF Renewables and ESB off the coast of Scotland. Global Wind Projects said that this is the company’s first standalone offshore wind […]

  • 9 August 2023

    The third phase of the installation of wind turbine jacket foundations at the Neart Na Gaoithe offshore wind farm in Scotland is scheduled to start on or around 11 August, with the heavy lift vessel Thialf set to install eleven jackets within this campaign. The jackets will be brought directly to the site from the […]

  • 10 September 2019
    Authorities, Wind Farm Update

    Neart na Gaoithe Offshore Wind Limited, the developer of the 450MW Neart na Gaoithe wind farm offshore Scotland, has made an application to the UK Gas and Electricity Markets Authority for an electricity generation licence. The licence application will remain open for comments until 8 October. The Edinburgh-based Neart na Gaoithe Offshore Wind Limited is a special […]

  • 30 November 2017
    Contracts & Tenders, R&D, Wind Farm Update

    Mainstream Renewable Power has begun the selection process to bring on board a majority equity partner to help take its 450MW Neart na Gaoithe offshore wind project into construction and commercial operation.

  • 28 December 2020
    Wind Farm Update

    The geotechnical borehole survey campaign at the Neart na Gaoithe offshore wind farm site has been completed. According to the project’s Notice to Mariners from 26 December, the Ocean Vantage vessel, which has been deployed for the work, has been demobilised. As reported earlier this year, the borehole survey campaign at the Neart na Gaoithe […]

  • 18 November 2022
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ semisubmersible crane vessel Balder has replaced Saipem 3000 at the Neart na Gaoithe offshore wind farm in Scotland, taking over the installation of piles for the project’s jacket foundations. Balder arrived at the project site in October to install the first ten jacket foundations and completed the work on 7 November, and moved on […]

  • 5 May 2014
    R&D, Technology, Wind Farm Update

    Offshore WIND’s photo of the day: A floating LiDAR deployed on Mainstream Renewable Power’s 450MW Neart na Gaoithe offshore wind farm site.  On April 20, FLiDAR NV (a joint venture between DEME and 3E), has set up the device at Mainstream Renewable Power’s Neart na Gaoithe offshore wind farm site, almost 21km off the Fife coast. The […]

  • 18 November 2019
    Wind Farm Update

    Nearshore geotechnical surveys along the Neart na Gaoithe export cable corridor route are due to start off the Fife coast in Scotland later this month. The survey work is being carried out by Fugro using a ‘walking’ jack-up barge, Wavewalker 1. The survey is planned to start no earlier than 25 November and last approximately […]

  • 27 July 2016
    Authorities, Business & Finance, Wind Farm Update

    Mainstream Renewable Power has urged Scottish ministers to appeal the recent judicial review of Scottish Court of Session which has ruled in favour of the Royal Society for the Protection of Birds (RSPB) and has put a stop to four offshore wind projects off the Fife coast, including Mainstream’s 450MW Neart na Gaoithe.  In October 2014, Mainstream was granted consent […]

  • 4 December 2013
    R&D

    Neart na Gaoithe Offshore Wind Limited will be carrying out 110 seabed Cone Penetration Tests (CPTs) at the Neart na Gaoithe offshore wind farm site, the KIS-ORCA announced on its website. The tests will commence between the 7th and 10th December 2013, and will be completed approximately within 26 days, weather permitting. The Neart na […]

  • 10 December 2013
    R&D, Wind Farm Update

    Mainstream Renewable Power is undertaking planned survey work on the Neart na Gaoithe Offshore Wind Farm site from Thursday December 12th 2013 (earliest) for approximately 26 days. The work relates to the site of the proposed 450MW Neart na Gaoithe offshore wind farm which is located in the outer Forth Estuary approximately 15 km to […]

  • 10 September 2020
    Grid Connection, Wind Farm Update

    Perth civil engineering company I & H Brown has secured a contract to construct the onshore substation for the Neart na Gaoithe (NnG) offshore wind farm in Scotland. I & H Brown said it is undertaking all the civil elements of the substation to enable the site, including five portal frame buildings in preparation for the […]

  • 10 March 2020
    Contracts & Tenders

    Dutch offshore lifting equipment provider KenzFigee has won a contract to deliver two 3-ton electric hydraulic Ram Luffing offshore cranes to be installed on the Neart na Gaoithe (NnG) offshore substation topsides. KenzFigee was awarded the contract by HSM Offshore, in close collaboration with Iv-Offshore & Energy. The heavy duty 1300 type Ram Luffing design […]

  • 4 August 2017
    Wind Farm Update

    Mainstream Renewable Power will be holding a number of pre-application consultation events in September and October in relation to the Marine Licence(s) for the 450MW Neart na Gaoithe wind farm project offshore Scotland.

  • 8 June 2021
    Grid Connection, Wind Farm Update

    The first of the two shunt reactors for the Neart na Gaoithe (NnG) offshore wind farm has been transported under police escort from Scotland’s Port of Leith to the NnG onshore substation site near Innerwick, East Lothian. The second shunt reactor is due for delivery in the coming days, according to the latest update from […]

  • 27 March 2020
    Contracts & Tenders, Grid Connection

    VolkerInfra has secured a new contract with Prysmian PowerLink for onshore cable services at the Neart na Gaoithe (NnG) offshore wind farm in Scotland. Under the GBP 15.5 million contract, VolkerInfra will install two 220kV onshore export circuits following the completion of the Pre-Construction Activities (PCA). The UK-based company is in charge of enabling works […]

  • 16 May 2017
    Authorities, Business & Finance, Environment, Wind Farm Update

    The Court of Session, Scotland’s supreme civil court, has overturned the ruling which halted further development of four wind projects with a total capacity of 2,284MW in the Firth of Forth and Firth of Tay.

  • 24 August 2020
    Wind Farm Update

    A geotechnical borehole survey campaign is set to begin at the Neart na Gaoithe (NnG) offshore wind project on 1 September. Geotechnical drilling vessel Ocean Vantage is expected to survey 32 of the planned wind turbine and one of the offshore substation locations. The survey works are expected to last approximately 80 days. Neart na […]

  • 18 June 2013
    Grid Connection, Wind Farm Update

    Global wind and solar company Mainstream Renewable Power has been granted planning consent by East Lothian Council for the onshore cable works to connect its 450MW “Neart na Gaoithe” offshore wind farm, located off the coast of Fife, to the National Grid. East Lothian Council’s Planning Committee agreed on 18th June to grant consent for […]

  • 26 May 2015
    Authorities, Environment

    Neart na Gaoithe, the €2.1 billion offshore wind project located 30 km north of Torness will face an environmental challenge in a Scottish court this week. According to an assessment by the Scottish authorities the 450-megawatt Neart na Gaoithe along with three other wind energy project are projected to kill about 1,200 puffins and 1,100 gannets a […]

  • 19 March 2021
    Grid Connection, Wind Farm Update

    The remaining seabed preparation works at the Neart na Gaoithe offshore wind project are set to recommence at the beginning of April, after the winter pause. The vessel Sartor will carry out the remaining boulder relocation operations in preparation for the installation of inter-array cables in the wind farm area. Boulder relocation is due to […]