124 results found for 'hollandse kust alpha'

124 results found for 'hollandse kust alpha'
Order results by

A list of search results

  • 17 March 2025
    Contracts & Tenders, Grid Connection, Offshore Platforms, Operations & Maintenance, Supply Chain, Vessels

    TenneT is seeking crew transfer vessel (CTV) services for its offshore wind grid connections in the Netherlands, with CTVs required to travel between the port of Vlissingen or the port of IJmuiden to offshore high-voltage platforms in the Dutch North Sea. The Dutch transmission system operator (TSO) will award a contract estimated to be worth […]

  • 24 January 2025
    Business & Finance, Cables, Grid Connection, Offshore Platforms, Outlook & Strategy, Vessels

    China’s first dedicated long-range heavy subsea cable transport barge has completed its inaugural mission at an offshore wind project and will undergo maintenance before embarking on a new mission. Chinese power cable specialist Orient Cable launched the barge named Dongfang Haigong 07 (DFHG 07) in October 2023. Designed to transport various types of subsea cables, including those […]

  • 18 October 2024
    Cables, Contracts & Tenders, Grid Connection, Operations & Maintenance, Supply Chain

    Dutch offshore transmission system operator (TSO) TenneT has opened an application period for a EUR 3 million tender for surveys of cables installed in the Dutch sector of the North Sea. Work will start in 2025 and will be performed on the export cables at the Borssele and the Hollandse Kust offshore wind farm zones […]

  • 25 October 2024
    Business & Finance, Cables, Contracts & Tenders, Fixed-Bottom, Grid Connection, Supply Chain

    DEME has been awarded a contract to carry out the transport and installation of inter-array cables and secondary steel for the 800 MW OranjeWind offshore wind farm in the Netherlands. Scheduled to start in the second half of 2026, DEME will deploy offshore and cable installation vessels, a hopper dredger and a fallpipe vessel, as […]

  • 18 February 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    DEME Offshore has secured a contract for the transport and installation of substations for the Hollandse Kust Noord and Hollandse Kust West Alpha offshore wind farms in the Netherlands. Under the contract awarded by the joint venture ENGIE Solutions-Iemants, DEME will also supply and install scour protection for the two substations. Installation of the scour […]

  • 7 September 2018
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Offshore grid operator TenneT has selected the Van Oord-Hellenic Cables consortium to connect the Hollandse Kust (South) Alpha and Beta offshore platforms to the Dutch onshore grid.

  • 21 September 2021
    Grid Connection

    Waves Group Ltd has secured the contract to carry out Marine Warranty Surveyor (MWS) services for the installation of TenneT’s Hollandse Kust Noord and West Alpha export power cables.  The agreement will see Waves Group provide MWS services during the installation of the Hollandse Kust Noord and Hollandse Kust West Alpha export cables, with installation […]

  • 6 January 2020
    Contracts & Tenders, Grid Connection

    TenneT has awarded RPS Energy Ltd with a contract to provide unexploded ordnance (UXO) consultancy services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers six offshore wind zones, the 700MW Hollandse Kust Noord, the 700MW Hollandse Kust (west) Alpha, the 700MW Hollandse Kust (west) Beta, […]

  • 13 November 2019
    Grid Connection

    Dutch transmission system operator TenneT TSO B.V. has issued a tender for offshore unexploded ordnance (UXO) survey, identification and clearance at the zones identified in the Offshore Wind Energy Roadmap 2030. The tender covers the 700MW Hollandse Kust Noord, the 700MW Hollandse Kust (west) Alpha, the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden […]

  • 18 September 2019
    Contracts & Tenders, Grid Connection

    Dutch transmission system operator TenneT TSO B.V. has issued a tender seeking unexploded ordnance (UXO) consultancy services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. As the designated offshore grid operator for the future wind farms, TenneT is responsible for the engineering, procurement, installation, construction, and operation of the […]

  • 28 November 2019
    Contracts & Tenders, Grid Connection

    Van Oord-Cablel Hellenic Cables consortium has awarded First Subsea with a contract to supply a cable protection system (CPS) for the Hollandse Kust (zuid) export cables, and a cross over protection for TenneT’s Net op zee Hollandse Kust (zuid). Under the contract, First Subsea will engineer, test, and supply a CPS for the protection of […]

  • 21 February 2022
    Grid Connection, Wind Farm Update

    The second offshore transformer station topside for the grid connection of the 1.5 GW Hollandse Kust Zuid offshore wind project has set sail from the Drydocks World Dubai’s fabrication facility in the United Arab Emirates. In charge of the weighing, transport and load-out of the 700 MW, 3,950-tonne Hollandse Kust Zuid Beta topside is the […]

  • 25 March 2022
    Grid Connection, Vessels, Wind Farm Update

    Boskalis has completed the transport of the Hollandse Kust Zuid (HKZ) Beta substation topside from Dubai to Rotterdam using its semi-submersible heavy transport vessel Mighty Servant 3. The HKZ Beta topside is scheduled to be installed in the Hollandse Kust Zuid wind farm zone in the Dutch North Sea in the coming days. According to […]

  • 31 January 2022
    Authorities, Vessels

    A rudderless cargo ship is drifting around the Hollandse Kust Zuid offshore wind farm in the Dutch North Sea following a collision with an oil and chemicals tanker in heavy seas in the anchorage area near IJmuiden on Monday, 31 January, the Dutch Coastguard said. In one of its most recent updates on the incident, […]

  • 24 March 2022
    Grid Connection, Wind Farm Update

    The installation of the Hollandse Kust Zuid Beta offshore substation topside will not be affected by the damage the substation’s jacket foundation suffered in a recent collision with a cargo ship, TenneT said. As reported, the cargo ship Julietta D collided with the substation jacket and a turbine foundation at the Hollandse Kust Zuid wind […]

  • 20 September 2019
    Contracts & Tenders

    TenneT TSO has issued a tender seeking non-UXO offshore route survey services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers the 700MW Hollandse Kust (west) Beta, the 700MW Ten noorden van de Waddeneilanden, the 2GW IJmuiden Ver Alpha, and the 2GW IJmuiden Ver Beta offshore wind farm zones. […]

  • 12 January 2022
    Contracts & Tenders

    Energy logistics provider Peterson is supporting the offshore installation of the two 700 MW transformer platforms for TenneT’s Hollandse Kust Zuid (HKZ) offshore grid connection under a logistics contract with Petrofac. HKZ Alpha, the first of the two offshore substations that will connect Vattenfall’s 1.5 GW Hollandse Kust Zuid offshore wind farm to the Dutch grid, was installed […]

  • 25 September 2020
    Grid Connection

    The joint venture between ENGIE Solutions and Iemants, a subsidiary of Smulders, has cut the first steel for the topside of the offshore transformer station for the Hollandse Kust Noord wind farm zone in the Netherlands. The joint venture partners, together with TenneT representatives, officially marked the beginning of works at a steel cutting ceremony […]

  • 28 January 2019
    Authorities, Environment, Grid Connection

    The Netherlands commission for environmental assessment has issued a positive recommendation on the Environmental Impact Report of the Hollandse Kust (noord) and the Hollandse Kust (west Alpha) grid connections. Pondera Consult, together with Arcadis, provided the EIR and the necessary studies. The Hollandse Kust (noord) wind farm will be located about 18.5 kilometers offshore. The Hollandse […]

  • 31 March 2022
    Grid Connection, Wind Farm Update

    The topside of the Hollandse Kust Zuid (HKZ) Beta offshore substation has been installed on its jacket foundation in the Dutch North Sea, TenneT said. The HKZ Beta topside was loaded from the transport vessel onto Allseas’ platform installation vessel Pioneering Spirit in the Alexiahaven. The Pioneering Spirit then sailed to the installation site and, […]

  • 11 December 2020
    Contracts & Tenders, Grid Connection

    TenneT and a joint venture of ENGIE Solutions and Iemants have signed a contract to design, engineer, produce, deliver, transport, and install the Hollandse Kust West Alpha offshore transformer substation. Earlier this year, the consortium had won the contract for the construction and installation of the Hollandse Kust North offshore transformer substation, with options for […]

  • 3 April 2023
    Grid Connection, Wind Farm Update

    The Dutch-German transmission system operator (TSO), TenneT, has announced that the grid connection for the 759 MW Hollandse Kust Noord offshore wind farm is ready for commissioning. Now the wind farm’s operator, CrossWind, can connect the 69 Siemens Gamesa’s SG 11.0-200 DD 11 MW wind turbines to the offshore substation located some 20 kilometres off the […]

  • 1 June 2023
    Grid Connection, Wind Farm Update

    The Hollandse Kust Noord platform has been taken over by the Dutch transmission system operator (TSO) TenneT. After a successful project engineering, procurement, construction, installation, and offshore hook-up, the Hollandse Kust Noord platform take-over is now official by signing off the Taking-Over certificate. In March 2020, TenneT awarded the joint venture Equans-Smulders the contract to […]

  • 23 March 2022
    Contracts & Tenders, Grid Connection

    TenneT has awarded a consortium between Boskalis and Orient Cable (NBO) a contract for the Hollandse Kust West Beta export cable, which will connect the 700 MW offshore platform to TenneT’s onshore grid in the Netherlands. The contract scope comprises the supply and installation of two 65-kilometre-long 220kV export cables and a 9-kilometre-long 66 kV […]

  • 27 May 2020
    Contracts & Tenders, Grid Connection, Wind Farm Update

    TenneT has selected the consortium of ENGIE Fabricom and Iemants to design, engineer, produce, deliver, transport, and install a 700 MW offshore substation for the Hollandse Kust Noord offshore wind farm. The contract also includes the options for identical work on the Hollandse Kust West Alpha and Hollandse Kust West Beta offshore substations. The Hollandse […]

  • 11 June 2021
    Grid Connection

    TenneT and the joint venture of ENGIE Solutions and Iemants have cut the first steel for the Hollandse Kust (west Alpha) offshore transformer station topside. The joint venture partners and TenneT officially kicked off the steel fabrication for the Hollandse Kust (west Alpha) topside at the Smulders’ facility in Hoboken, Belgium. Smulders is the parent […]