162 results found for 'Greater Changhua 1 and 2a'

162 results found for 'Greater Changhua 1 and 2a'
Order results by

A list of search results

  • 9 October 2025
    Business & Finance, Contracts & Tenders, Supply Chain, Vessels

    Global Maritime (GM) has signed a framework agreement with Van Oord, under which the marine and engineering consultancy company will provide a range of services to support Van Oord’s work in the offshore wind sector. The framework covers consultancy and technical support for operations and maintenance (O&M) campaigns, as well as wind turbine and foundation […]

  • 8 September 2025
    Business & Finance, Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Ørsted’s Greater Changhua 2b offshore wind project in Taiwan will be commissioned in the third quarter of 2026 instead of later this year due to a damaged export cable. The 300 MW offshore wind farm is part of the 920 MW Greater Changhua 2b and 4 project, currently under construction 35-60 kilometres off the coast of Changhua […]

  • 23 July 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The first turbine from the 920 MW Greater Changhua 2b and 4 offshore wind farms, owned by Ørsted, has delivered first power to the national grid of Taiwan. Being built 35-60 kilometres off the coast of Changhua County, the two offshore wind sites will together comprise 66 Siemens Gamesa 14-236 14 MW wind turbines, 32 […]

  • 11 July 2025

    Heerema Marine Contractors’ heavy-lift vessel Aegir has installed the final suction bucket jacket foundation at Ørsted’s 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. According to the company’s latest social media post, the crew onboard Aegir installed a total of 66 foundations at the site located 35-60 kilometres off the coast […]

  • 27 June 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The jacket foundation installation at Ørsted’s Greater Changhua 2b & 4 offshore wind farms is nearing completion, with 61 out of 66 foundations already installed at the site in Taiwan. Additionally, a third of the wind turbines for the project are now in place. Offshore construction of the 920 MW Greater Changhua 2b and 4 […]

  • 3 November 2021
    Wind Farm Update

    116 out of 165 Siemens Gamesa 8.4 MW wind turbines have been installed at Hornsea Two, soon to be the largest offshore wind farm in the world, Ørsted said. 142 inter-array cables have also been installed at the site some 89 kilometres off the Yorkshire coast, the UK. As reported earlier, both offshore substation topsides […]

  • 25 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The Greater Changhua 1 and 2a offshore wind project was officially inaugurated at an event in the Port of Taichung, Taiwan, on 25 April 2024. With a total installed capacity of 900 MW, the project is in operation and fully connected to the grid, making it the largest in Taiwan and the Asia-Pacific region, said […]

  • 30 January 2024
    Project Updates, Wind Farm Update

    107 out of 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at Ørsted’s Greater Changhua 1 and 2a offshore wind farm site in Taiwan, with nearly 85 per cent of them connected to the national grid. Offshore construction on the Greater Changhua 1 and 2a project started in the summer of 2021. […]

  • 9 August 2019
    Contracts & Tenders

    Heerema Marine Contractors (HMC) has secured a contract for the transport and installation of turbine foundations and the installation of offshore substations at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. HMC will utilize its vessel Aegir for the transportation and installation of 111 turbine foundations and the installation of two offshore substations at […]

  • 3 April 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines at the 900 MW Greater Changhua 1 and 2a offshore wind farms have achieved first power and been connected to the Taiwanese national grid. Offshore construction at Ørsted’s Greater Changhua 1 and 2a commenced in the summer of 2021 with the installation of the first wind […]

  • 29 February 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 111 Siemens Gamesa SG 8.0-167 DD wind turbines have been installed at the Greater Changhua 1 and 2a offshore wind farms in Taiwan, according to an update shared on social media by Per Mejnert Kristensen, President of Ørsted Asia Pacific. Offshore construction on the Greater Changhua 1 and 2a wind farms started in the summer of […]

  • 22 August 2019
    Contracts & Tenders, Wind Farm Update

    Seajacks International has won a contract by Ørsted for the transport and installation of turbines at the Greater Changhua 1 and 2a offshore wind projects in Taiwan. Seajacks is planning to use its jack-up vessel Seajacks Scylla for the transport and installation of 111 Siemens Gamesa 8MW turbines at the project site located 35-50km off the coast of […]

  • 9 February 2022
    Operations & Maintenance, Vessels, Wind Farm Update

    The first service operation vessel (SOV) built for the Asian offshore wind market completed six days of sea trials offshore Vietnam back in January. The SOV, to be named TSS Pioneer, is being built by Vard at the Vung Tau shipyard in Vietnam. The vessel will soon be delivered to Ta San Shang Marine, a […]

  • 5 May 2021
    Vessels, Wind Farm Update

    Heerema Marine Contractors’ (HMC) vessel Aegir has started installing jacket foundations at Ørsted’s Greater Changhua offshore wind project site in Taiwan. The vessel is currently installing the jacket for one of the two offshore substations of the Greater Changhua 1 and 2a offshore wind farms. Aegir, which had been undergoing an upgrade at Sembcorp in Singapore […]

  • 10 April 2024
    Operations & Maintenance

    In February 2024, Global Maritime completed its task of providing marine warranty services (MWS) for the installation of 111 wind turbines on Ørsted’s Greater Changhua 1 and 2a offshore wind farms in Taiwan. Ørsted awarded the MWS contract to Global Maritime Singapore in March 2021. The Greater Changhua 1 and 2a offshore wind project is […]

  • 11 August 2022
    Business & Finance, Contracts & Tenders, Wind Farm Update

    The commissioning of the 900 MW Greater Changhua 1 & 2a has been delayed to 2023, according to Ørsted’s interim report for the first half of 2022. The project was initially scheduled to be fully operational by the end of the year, but due to COVID-19-related delays, the commissioning of the wind farm is being […]

  • 27 January 2021
    Contracts & Tenders, Wind Farm Update

    Master Builders Solutions has won the grout supply contracts for the Formosa 2, the Changfang and Xidao, and the Greater Changhua 1 and 2a offshore wind projects in Taiwan. In total, Master Builders Solutions will be supplying MasterFlow 9500 and MasterFlow 9800 to 222 offshore foundations over the next three years. “2020 has been a […]

  • 5 May 2021
    Operations & Maintenance, Training & Education

    Ten wind turbine generator (WTG) technicians Ørsted Taiwan recently recruited have departed for training in the UK, the company reported on 5 May. The team of ten technicians, who will be on their training secondment in the UK until the end of the year, were recruited in January, when the offshore wind developer hired 22 […]

  • 9 May 2024
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Supply Chain

    Ørsted has appointed energy and marine consultancy, ABL, to provide marine warranty survey services (MWS) for the offshore transportation and installation (T&I) of wind turbines and cables package for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. ABL’s scope of work includes reviewing, surveying, and approving all operations relating to the transportation […]

  • 17 March 2021
    Ports & Logistics, Wind Farm Update

    The first wind turbine tower section built for the 900 MW Greater Changhua 1 and 2a offshore wind farm has arrived at the Port of Taichung, Taiwan, Ørsted, the developer of the project, said. This is the first of 333 tower sections in total that are being manufactured locally by the consortium of CS Wind […]

  • 3 August 2021
    Ports & Logistics

    Siemens Gamesa’s offshore wind nacelle assembly facility in Taichung, Taiwan has assembled its first nacelle. This marks the first time a Siemens Gamesa offshore turbine nacelle has been assembled outside Europe. The construction work on Siemens Gamesa’s assembly facility in Taichung Harbor started in March 2020. The parcel of land being developed in Taiwan measures […]

  • 21 April 2020
    Wind Farm Update

    Heerema Fabrication Group is set to manufacture the pre-piling template for the Greater Changhua offshore wind project in Taiwan. The template, which will enable Heerema Marine Contractors to install the piles accurately, consists of three pile sleeves connected by framing, including hydraulically adjustable pile guides and mudmats. Heerema Vlissingen will fabricate the steel structure and […]

  • 10 September 2020
    Business & Finance

    Ørsted has appointed BNP Paribas, Cathay United Bank and CTBC Bank as Mandate Lead Arranger’s for a potential TWD denominated green bond issuance in Taiwan. The green bond, set to be issued in Q4 2020, represents Ørsted’s second green bond offering in Taiwan. Ørsted intends to issue the new green bonds for the purpose of […]

  • 3 May 2023
    Business & Finance

    World’s leading offshore wind developer, Ørsted, has reported DKK 6.9 billion (EUR 926 million) operating profit (EBITDA) for the first quarter of 2023, DKK 2.5 billion less compared to the same period a year earlier. EBITDA excluding new partnerships in Q1 2023 was DKK 0.9 billion lower than Q1 2022, as Q1 2022 was positively […]

  • 12 March 2021
    Vessels, Wind Farm Update

    Subsea construction vessel Topaz Tangaroa has left the Netherlands and is on her way to Taiwan to join Van Oord’s cable laying vessel Nexus on the Greater Changhua 1 and 2a offshore wind project. Prior to leaving the Netherlands, Topaz Tangaroa was equipped with Van Oord’s trencher Dig-It, and a walk-to-work system. AIS data shows […]

  • 1 April 2022
    Ports & Logistics, Vessels, Wind Farm Update

    The first of the 111 Siemens Gamesa SG 8.0-167DD wind turbines has been installed at the 900 MW Greater Changhua 1 & 2a wind farm project offshore Taiwan. The first batch of turbine components was transported from the Port of Taichung, and the first turbine was installed at the site by Seajack Scylla, a wind […]