Ningbo Orient Cable (NBO) has completed the installation of the export cable at the China Three Gorges New Energy (CTGNE) Yangjiang Shapa Phase 1 offshore wind project.
According to NBO, the installation of two 220kV export cables was finished after 14 months and now the offshore engineering team is installing the 35kV inter-array cables.
Seven circuits have been completed and the rest is expected to be done before the end of this year.
CTGNE Yangjiang Shapa Phase 1 comprises 55 5.5 MW turbines and is Three Gorges Group’s first wind project off the Guangdong Province.
The 300 MW wind farm, also known as Yangxi Shapa Phase 1, produced first power in November 2019.
It is part of a larger offshore wind project which once fully commissioned will have an installed capacity of over 1 GW.
Photo: Orient Cable
List of related news articles
-
Posted: 7 months ago
NBO Delivers 2nd Batch of Export Cable for Yangxi Shapa 1
Ningbo Orient Cable (NBO) has delivered 39.6 kilometres of 220 kV export cable for the China Three G...
Posted: 7 months ago -
Posted: 4 months ago
Orient Cable Bags Yangjiang Qingzhou III Deal
Ningbo Orient Cable (NBO) has won a contract to provide subsea cables for the Yangjiang Qingzhou III...
Posted: 4 months ago -
Posted: 4 months ago
SPT Installs Suction Pile Jacket Offshore China
SPT Offshore has installed the first suction pile jacket foundation at the 300 MW CTGNE Yangxi Shaba...
Posted: 4 months ago -
Posted: 27 days ago
Yangjiang Nanpeng Island Offshore Wind Farm Fully Connected
The Yangjiang Nanpeng Island offshore wind project in China has been fully connected to the grid. Mi...
Posted: 27 days ago