East Anglia ONE Turbine Installation Enters Final Stretch

82 out of the 102 Siemens Gamesa 7MW wind turbines have been installed on the 714MW East Anglia ONE wind farm offshore Suffolk, UK, Iberdrola said.

ScottishPower Renewables/Illustration
ScottishPower Renewables/Illustration

The turbines are pre-assembled and loaded out on DEME Offshore’s jack-up vessel Sea Installer from Peel Ports Great Yarmouth prior to being transported and installed at the site located some 43 kilometres from the coast of Lowestoft.

The first wind turbine was installed at the site in June 2019, and the wind farm delivered the first power to the UK grid in early September 2019. The full commissioning is expected in 2020.

The wind farm will be operated and maintained from a new operations and maintenance base at Lowestoft Port.

The East Anglia ONE offshore wind farm is a joint venture between ScottishPower Renewables, a subsidiary of Iberdrola, and Green Investment Group.