Turbine Installation Starts on East Anglia ONE

DEME Offshore's jack-up vessel Sea Installer has arrived at the East Anglia ONE offshore wind farm carrying the first load of wind turbine components.

Sea Installer departed from Great Yarmouth at around noon, Thursday, 20 June, and arrived at the East Anglia ONE wind farm some four hours later, AIS data shows.

Located 43 kilometres off the Suffolk coast in the UK, the 714MW East Anglia ONE will comprise 102 Siemens Gamesa 7MW wind turbines scheduled for commissioning in 2020.

The GBP 2.5 billion wind farm is owned and developed by ScottishPower Renewables, a subsidiary of Spain's Iberdrola.

Related news

List of related news articles

Posted: about 1 month ago

Sea Installer Loading First East Anglia ONE Turbine Parts

DEME Offshore's jack-up vessel Sea Installer has arrived in Great Yarmouth to load the first set of ...

Categories:
  • Wind Farm Update
Posted: about 1 month ago
Posted: 3 months ago

East Anglia Consultation Wraps Up

ScottishPower Renewables has closed the Phase 4 Consultation on the proposed East Anglia ONE North a...

Categories:
  • Wind Farm Update
Posted: 3 months ago
Posted: about 1 month ago

Island Crown Heads to East Anglia ONE

Siemens Gamesa has on behalf of ScottishPower Renewables contracted the service offshore vessel Isla...

Categories:
  • Vessels
Posted: about 1 month ago
Posted: 2 months ago

Deutsche Bucht Nears Turbine Installation

The Northland Power team is gearing up for the beginning of the turbine installation campaign at the...

Categories:
  • Wind Farm Update
Posted: 2 months ago