69 Monopiles and 27 Transition Pieces Installed at Danish Wind Farm

69 Monopiles and 27 Transition Pieces Installed at Danish Wind Farm

The installation of monopiles and transition pieces is ongoing at full speed, and as of 1 June, 69 monopiles and 27 transition pieces are installed in the Anholt wind farm, and Jumbo Javalin has just arrived at the site with a new load of transition pieces.

The installation of monopiles is expected to be completed by the end of July, whereas the last transition piece is expected to be installed in September.

As the sea erases all tracks, it is important that the documentation is in place and accurate. In all 42 positions where a layer of filter stones has been placed, to protect the foundation against erosion, thorough electronic scans have been made to ensure that the rock layer is at the precise height to make it possible to lead the cables into the foundation.

[mappress]

Offshore WIND staff, June 07, 2012; Image: dongenergy