  • 26 August 2014

    Thursday September 4 sees the opening of an exhibition of drawings at the Orkney Museum, Tankerness House, which chart the development of a wind farm in the Moray Firth. ‘Beatrice Works’ by Sue Jane Taylor, follows the creation of a major new development in the offshore renewables sector. The exhibition takes its name from the […]

  • 14 October 2016
    Grid Connection, Wind Farm Update

    The 588MW Beatrice offshore wind farm project reached another milestone with the recent breaking of ground near Portgordon in Moray, Scotland, SSE reports. Enabling works are now underway at the main onshore construction compound near the cable landfall point for the route to Blackhillock. Work on the Operations and Maintenance site based in two historic […]

  • 28 February 2017

    IHC IQIP will provide jacket pile grippers, the Hydrohammer S-2500 with two specially designed hammer sleeves, and an internal lifting tool to Seaway Heavy Lifting (SHL), the EPCI contractor in charge of foundations for the Beatrice project.

  • 13 November 2017
    Business & Finance

    BiFab is facing a critical cash position due to a challenging situation regarding its ongoing contracts for the Beatrice offshore wind farm. Given the circumstances, the company’s directors have filed a Notice of Intention to Appoint Administrators, however they hope a solution could be found and BiFab would not need to go into administration.

  • 2 March 2017
    Technology, Wind Farm Update

    Seaway Heavy Lifting (SHL) has awarded Bauer Renewables with a subcontract to design, build, test and operate specialized equipment – the BAUER Dive Drill C40 – to execute relief drilling services for the foundation piles at the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland. SHL will install 84 jackets for the […]

  • 6 November 2017
    Vessels, Wind Farm Update

    Seaway Heavy Lifting’s crane vessel Stanislav Yudin has installed 84 out of the 86 sets of piles for jacket foundations on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

  • 25 February 2019
    Wind Farm Update

    63 out of the 84 Siemens Gamesa 7MW wind turbines have been installed on the 588MW Beatrice wind farm offshore Scotland, according to Beatrice Offshore Windfarm Limited (BOWL). 59 out of the 63 units installed have been commissioned, BOWL said. The turbine installation is expected to be completed in Spring 2019. Swire Blue Ocean’s jack-up is loading […]

  • 23 May 2016
    Business & Finance, Grid Connection, Vessels, Wind Farm Update

    Subsea 7 has teamed up with Seaway Heavy Lifting on an engineering, procurement, construction and installation (EPCI) contract for wind farm turbine foundations and array cables to be installed at the 588MW Beatrice offshore wind farm located in the Outer Moray Firth, Scotland. The value of the contract is over USD 1.3 billion (over GBP 896 million), according to Seaway Heavy […]

  • 28 December 2017
    Vessels, Wind Farm Update

    Siem Offshore Services’ cable laying vessel Siem Aimery has installed 15 inter-array cables during the first cable installation campaign on the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

  • 26 May 2016
    Technology, Wind Farm Update

    Seaway Heavy Lifting (SHL) has appointed Atkins to carry out the detailed design of the jacket substructure and foundations for the 588MW Beatrice offshore wind farm in the outer Moray Firth, UK, as part of SHL’s EPCI contract with the farm’s developer Beatrice Offshore Windfarm Limited (BOWL). 84 jacket substructures and associated foundations for the […]

  • 29 March 2017
    Ports & Logistics, Vessels, Wind Farm Update

    Scotland’s Port of Cromarty Firth has been awarded two contracts by Seaway Heavy Lifting (SHL) to support the installation of the 580MW Beatrice offshore wind farm in Outer Moray Firth.

  • 23 May 2016

    Scottish Renewables, Scottish Enterprise (SE) and Highlands and Islands Enterprise (HIE) have responded to news that the Beatrice offshore wind project reached financial close and will now proceed to construction. Lindsay Roberts, Senior Policy Manager at Scottish Renewables, said: “Beatrice is the first commercial offshore wind farm to reach this stage of development in Scottish waters. It’s fantastic […]

  • 17 July 2019
    Environment

    Marine Scotland Science (MSS) and the University of Aberdeen (UoA) carried out a multi-disciplinary survey within the Moray Firth wind farm sites in June 2019. MSS colleagues and UoA postgraduate students set sail on the Alba na Mara to characterise the distribution of the prey species (fish schools, zooplankton patches) across the Smith Bank in […]

  • 25 May 2017
    Vessels, Wind Farm Update

    Almost 20 percent of piles for jacket foundations at the 588MW Beatrice offshore wind farm have been installed so far, Beatrice Offshore Windfarm Ltd (BOWL) reports.

  • 20 August 2017

    Oleg Strashnov Installs First Beatrice Jacket Foundation Seaway Heavy Lifting’s vessel Oleg Strashnov has installed the first of 86 jacket foundations on the 588MW Beatrice offshore wind farm in the Outer Moray Firth, Scotland. Boskalis Buys Gardline Group Royal Boskalis Westminster N.V. has acquired all shares of the UK-based Gardline Group. U.S. Oil & Gas […]

  • 6 December 2017
    Wind Farm Update

    Beatrice Offshore Windfarm Ltd (BOWL) posted a photo on its social media pages today, 6 December, showing Nexans Skagerrak, Siem Aimery and Siem Stingray vessels working at the offshore construction site in the Outer Moray Firth off Scotland.

  • 23 January 2018
    Grid Connection, R&D, Wind Farm Update

    The jacket foundation for a Siemens Offshore Transformer Module (OTM) has been loaded onto a barge destined for the Beatrice offshore wind farm, after undergoing final preparations at BiFab’s yard in Fife, Scotland. 

  • 29 May 2024
    Business & Finance, Fixed-Bottom, Industry

    Beatrice Offshore Windfarm Limited (BOWL), the operator of an 85-turbine wind farm off northeast Scotland, has agreed to make a payment of GBP 33.14 million (approximately EUR 39 million) after admitting it breached energy market rules. BOWL, the operator of the 588 MW Beatrice offshore wind farm, admitted to breaching one of its licence conditions […]

  • 11 April 2017
    Wind Farm Update

    The first stage of works for the Beatrice offshore wind farm’s export cable is scheduled to start on 13 April at Portgordon, near Buckie, and will include installation of horizontal cable pipes, as well as underwater operations including diving, tunnelling and seabed preparation, according to the developer’s notice to mariners.

  • 14 November 2016
    Vessels, Wind Farm Update

    Seaway Heavy Lifting (SHL) has appointed GAC UK to provide shipping services support during the construction and installation of foundations, inter-array cables and offshore substations at the 588MW Beatrice offshore wind farm. SHL, the engineering, procurement, construction and installation (EPCI) contractor, will design, supply and install the piled foundations, jacket substructures and inter-array cables for the […]

  • 14 July 2017
    Grid Connection, Wind Farm Update

    Siem Offshore Contractors GmbH (SOC) has selected the UK-based JDR Cable Systems Ltd. to provide termination and testing services for the inter-array cable system of the 588MW Beatrice Offshore Windfarm Ltd project.

  • 28 September 2016
    Wind Farm Update

    Fugro has placed surrogate unexploded ordnance (UXO) items on the seabed at the Beatrice offshore wind farm area to enable towed magnetometer verification as part of the pre-construction UXO survey, according to Brown & May Marine. The surrogate units are inert and do not contain any explosive charge. After completing the UXO survey of the nearshore extent of the […]

  • 23 April 2014
    Authorities, Business & Finance

    Scottish Renewables responded to the Department of Energy and Climate Change (DECC) announcement that the Beatrice Offshore Windfarm, in the Outer Moray Firth, has been awarded an investment contract.  Lindsay Leask, Senior Policy Manager at Scottish Renewables, said: “It is greatly encouraging to see a Scottish offshore wind project selected for an early investment contract […]

  • 28 August 2015
    Environment

    The 664MW Beatrice offshore wind project site is crawling with activity. According to Kingfisher Fortnightly Bulletin, two companies are conducting surveys in the Outer Moray Firth. Brown and May Marine Ltd has been contracted by SSE to conduct marine survey operations that include larval sampling at 25 locations. Around the same time this last year, […]

  • 6 March 2017
    Vessels, Wind Farm Update

    Ahead of the construction start of the Beatrice offshore wind farm in April, Siem Offshore is set to begin with boulder removal and SCAR plough campaign at the project site as of 8 March.

  • 15 May 2017
    Wind Farm Update