  • 20 February 2019
    Vessels

    Danish company MH-O&C has held a naming ceremony for the crew transfer vessel (CTV) MHO Gurli. The 39m long Fast Supply Cat vessel was ordered by Ørsted for the Hornsea Project One offshore wind farm in the UK and is expected to enter service shortly. MHO Gurli has a 10.3m beam, a max draft of […]

  • 23 December 2016
    Grid Connection, Wind Farm Update

    Prefabrication work on three substations for DONG Energy’s 1.2GW Hornsea Project One offshore wind farm is well under way, Danish offshore structure construction specialist Bladt Industries reports. Each substation will weigh 2,800 tons and the first unit will be delivered during the first half of 2018, the company said. The contract represents Bladt’s first ever order to fabricate […]

  • 12 September 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    The Edda Mistral Service Operations Vessel (SOV) has arrived at the Royal Dock in Grimsby ahead of the vessel’s start of operations on Ørsted’s Hornsea Project One offshore wind farm.

  • 5 August 2019
    Wind Farm Update

    124 out of 174 Siemens Gamesa 7MW turbines have been installed and commissioned at the Hornsea Project One wind farm in the UK, a spokesperson from Ørsted told Offshore WIND. Fred. Olsen Windcarrier’s jack-up vessel Bold Tern is in charge of installing 88 out of the 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 […]

  • 6 February 2019
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has arrived at the Hornsea Project One offshore wind farm in the UK ready to install the first turbines. According to the UK-based company, the vessel left the Alexandra Dock in Hull yesterday morning after picking up the first batch of Siemens Gamesa 7MW turbines. Bold Tern is in […]

  • 1 November 2018
    Wind Farm Update

    104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed on the 1,218MW Hornsea Project One wind farm, Ørsted said.

  • 24 June 2016
    Business & Finance, Grid Connection, Wind Farm Update

    DONG Energy has awarded J. Murphy & Sons Limited (Murphy) the onshore cable installation contract for the 1.2GW Hornsea Project One offshore wind farm. Hornsea Project One, located off the Yorkshire coast, will comprise 174 wind turbines installed across an area of 407sq km, and will be the first offshore wind farm in the world to exceed one […]

  • 19 April 2017
    Wind Farm Update

    Royal Boskalis Westminster N.V. (Boskalis) has contracted SPT Offshore to install suction pile foundations on DONG Energy’s 1.2GW Hornsea Project One wind farm off UK.

  • 17 January 2018
    Grid Connection, Wind Farm Update

    J. Murphy & Sons is currently installing the onshore portion of cables that will connect Orsted’s 1.2GW Hornsea Project One offshore wind farm to the UK grid.

  • 22 May 2018
    Vessels, Wind Farm Update

    SMST has equipped the Platform Supply Vessel (PSV) Eurus Express with a motion compensated gangway ahead of the vessel’s deployment on Orsted’s Hornsea Project One offshore wind farm in the UK.

  • 22 August 2018
    Technology, Wind Farm Update

    SeaRoc Group has deployed its SeaHub Communications System on Hornsea Project One’s Reactive Compensation Station (RCS) – the world’s first offshore RCS – thus delivering the third SeaHub system for Ørsted’s 1.2GW offshore wind farm in the UK.

  • 15 September 2016

    DONG Energy will hold two community events in Grimsby and Stallingborough to give local people a chance to find out more about the Hornsea Project One offshore wind farm. When built, the 1.2GW Hornsea Project One will be the world’s largest offshore wind farm by a considerable margin, capable of providing enough renewable energy for well over […]

  • 30 July 2018
    Grid Connection, Wind Farm Update

    Bladt Industries has sent off the last two offshore substation topsides for Ørsted’s Hornsea Project One offshore wind farm from its site in Aalborg, Denmark.

  • 28 June 2019
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has completed the installation of 53 turbines at the Hornsea Project One offshore wind farm in the UK. Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 units. According to Fred. Olsen Windcarrier, the […]

  • 17 November 2016
    Wind Farm Update

    DONG Energy has awarded Siem Offshore Contractors (SOC) with a contract for the transport and installation of parts of the inner-array grid cable system for the 1.2GW Hornsea Project One offshore wind farm. SOC’s scope of work includes the installation of 81 submarine composite cables as well as the associated post-lay trenching works. The project engineering […]

  • 11 April 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted and Balfour Beatty have broken ground on the onshore substation for the Hornsea Project Two offshore wind farm. Balfour Beatty is in charge of enabling works for the wind farm’s onshore substation to ensure the site preparation is underway in good time, avoiding future schedule pressures, a spokesperson from Ørsted told OffshoreWIND. The main contract for […]

  • 5 July 2019
    Wind Farm Update

    The 100th Siemens Gamesa 7MW turbine has been installed at the Hornsea Project One offshore wind farm in the UK. Fred. Olsen Windcarrier’s Bold Tern is in charge of installing 88 out of the project’s total 174 turbines, with A2SEA’s Sea Challenger responsible for installing the remaining 86 units. According to Fred. Olsen Windcarrier, Bold Tern recently […]

  • 26 February 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up Bold Tern has departed from Hull, the UK, carrying the second batch of turbines for the Hornsea Project One offshore wind project. The vessel installed the first Siemens Gamesa 7MW turbine at the site some 120km off the Yorkshire coast in early February. Bold Tern is in charge of transporting and installing half […]

  • 21 June 2019
    Business & Finance

    The Hornsea Project One offshore wind farm has begun receiving Contract for Difference (CfD) payments. The Low Carbon Contracts Company (LCCC) began allocating the payments for the first phase of the 1.2GW offshore wind project as it passed the required tests for its Operational Conditions Precedent (OCP). The first project phase, with a capacity of 400MW, achieved a […]

  • 27 August 2019
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has installed 79 turbines at the Hornsea Project One offshore wind farm in the UK. According to the company, Bold Tern is on its way back to the Port of Hull to pick up another load of Siemens Gamesa turbines for the 1.2GW project. Hornsea Project One will comprise […]

  • 3 May 2018
    Operations & Maintenance, Vessels

    C-bed Floating Hotels’s DP2 walk-to-work vessel Wind Innovation will be used during the installation and commissioning phase of a 1.2GW offshore wind farm off Grimsby in the western UK.

  • 16 August 2019
    Wind Farm Update

    The Hornsea Project One offshore wind farm in the UK suffered a technical fault on 9 August due to grid problems. During the technical fault, the 1.2GW offshore wind farm significantly dropped its power production as it lost 800MW of electricity, around the same time as another generation source lost load, Ørsted said. “During a rare and […]

  • 27 June 2017
    Technology, Wind Farm Update

    DONG Energy has signed a new contract with SeaRoc Group for the deployment of two SeaHub communication containers for its Hornsea Project One Offshore wind farm construction phase.

  • 14 June 2016
    Vessels, Wind Farm Update

    Tideway BV has been awarded a Design and Build cable installation contract by DONG Energy for the Hornsea Project One offshore wind farm.  For the project, Tideway, a subsidiary of DEME, will deploy the new DP3 cable-laying vessel Living Stone, which is currently being built by the Spanish shipyard LaNaval and is scheduled to be delivered in April […]

  • 28 November 2018
    Business & Finance, Vessels

    MH-O&C has launched the newbuild crew transfer vessel (CTV) MHO Gurli which Ørsted ordered for its Hornsea Project One offshore wind farm in the UK.

  • 28 November 2018
    Business & Finance

    The UK-based Aviva Investors has invested GBP 400 million to help fund the construction of Ørsted’s Hornsea Project One offshore wind farm.