  • 31 August 2016
    Business & Finance, Wind Farm Update

    DONG Energy has awarded Germany’s Steelwind Nordenham with a contract to manufacture 36 monopiles and transition pieces for the 450MW Borkum Riffgrund 2 offshore wind farm. This is not the first time Steelwind Nordenham was contracted by DONG to build foundations for an offshore wind project, but it is the first time the company will produce transition pieces […]

  • 6 August 2018
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Ørsted’s 450MW Borkum Riffgrund 2 offshore wind farm fed electricity into the German national grid for the first time on Saturday, 4 August.

  • 9 August 2018
    Grid Connection, Operations & Maintenance, Vessels

    Attollo Offshore has mobilized the jack-up accommodation vessel Atlantic Amsterdam for Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 26 July 2017
    Vessels, Wind Farm Update

    Jan De Nul’s fall pipe vessel Simon Stevin has arrived at the Visnes Eklogitt quarry in Norway, where it will load the first batch of 32,000 tonnes of rock and transport it to the Borkum Riffgrund 2 offshore wind farm in Germany. There, the vessel will install scour protection layers onto the seabed for the wind turbine foundations.

  • 29 March 2018
    Contracts & Tenders, Grid Connection, Operations & Maintenance, Vessels, Wind Farm Update

    Ørsted has awarded Aberdeen-based Attollo Offshore with a contract to provide an accommodation jack-up vessel during the commissioning of the substation at the Borkum Riffgrund 2 offshore wind farm.

  • 25 September 2020
    Business & Finance, Wind Farm Update

    Thailand’s Gulf Energy Development Public Company Limited has officially taken over the 50 per cent stake in the Borkum Riffgrund 2 offshore wind farm from Global Infrastructure Partners. In July, Gulf acquired 50 per cent shares of Borkum Riffgrund 2 Investor Holding (BKR2) through its subsidiary Gulf International Holding (GIH) which entered into a share […]

  • 9 March 2018
    Vessels, Wind Farm Update

    The first complete monopile foundation has been installed on the Borkum Riffgrund 2 offshore wind farm in the German North Sea, Ørsted, the owner and developer of the wind farm, said.

  • 28 June 2018
    Grid Connection, Wind Farm Update

    The offshore substation topside for Ørsted’s Borkum Riffgrund 2 offshore wind farm has been installed at the site in the German North Sea.

  • 1 June 2017
    Grid Connection, Wind Farm Update

    Jan De Nul has contracted Seaproof Solutions to supply its export cable protection systems (CPS) for the Borkum Riffgrund 2 offshore wind farm and Trianel Windpark Borkum II.

  • 7 May 2018
    Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Bold Tern installed the first MHI Vestas 8MW wind turbine at Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea on 5 May.

  • 6 March 2018
    Vessels, Wind Farm Update

    Jan De Nul’s offshore installation vessel Vole au vent has installed the first monopile on Ørsted’s 450MW Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 23 January 2018
    Grid Connection, Wind Farm Update

    HSM Offshore, the EPC contractor for the Borkum Riffgrund 2 offshore substation, installed the two transformers that make the topside structure on 13 January. The topside left the construction hall for the installation of the transformers and was brought back into the covered construction area after the lifting operation was completed. 

  • 19 July 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    Van Oord’s cable lay vessel Nexus has loaded the final set of inter-array cables for the Borkum Riffgrund 2 offshore wind farm and is currently installing them at the site in the German North Sea.

  • 9 August 2018
    Grid Connection, Vessels, Wind Farm Update

    Van Oord has completed the cable installation work for Ørsted’s Borkum Riffgrund 2 offshore wind project in the German North Sea.

  • 12 December 2017
    Business & Finance, Wind Farm Update

    After completing the transaction with Global Infrastructure Partners (GIP) for the sale of 50% of the Borkum Riffgrund 2 offshore wind farm yesterday, 11 December, Ørsted now expects its EBITDA in 2017 to materialise at some DKK 21 billion (approx. EUR 2.8 billion), compared to the previously guided range of DKK 19-21 billion.

  • 29 June 2018
    Grid Connection

    Jan De Nul has completed the export cable installation works at the Trianel Windpark Borkum II and the Borkum Riffgrund 2 offshore wind farms in the German North Sea.

  • 13 July 2016
    Vessels, Wind Farm Update

    DONG Energy has awarded Jan De Nul with a contract for the transport and installation of 36 monopiles and transition pieces for the Borkum Riffgrund 2 offshore wind farm in Germany, Jan De Nul reported today. Jan De Nul will also be in charge of the supply, transport and installation of scour protection for all foundations. The works […]

  • 28 May 2018
    Wind Farm Update

    Jan De Nul’s jack-up vessel Vole au vent has installed the last monopile foundation at Ørsted’s Borkum Riffgrund 2 offshore wind farm.

  • 1 November 2018
    Wind Farm Update

    Ørsted is expecting a faster ramp-up of generation from the 450MW Borkum Riffgrund 2 offshore wind farm due to good progress on offshore construction which will be completed in the fourth quarter of 2018.

  • 31 May 2018
    Ports & Logistics, Vessels, Wind Farm Update

    Fred. Olsen Windcarrier has devised a solution which allows the jack-up Bold Tern to simultaneously perform bunkering and loading of wind turbine components for the Borkum Riffgrund 2 project at the Port of Esbjerg.

  • 31 July 2018
    Ports & Logistics, Vessels, Wind Farm Update

    GeoSea’s jack-up vessel Innovation has installed the last of the twenty suction bucket jacket foundations on Orsted’s 450MW Borkum Riffgrund 2 offshore wind farm in the German North Sea.

  • 21 June 2018
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    Ørsted has opened a new facility in Norddeich, Germany, which will be used for the Borkum Riffgrund 2 project, currently under construction, as well as the developer’s future projects in the German North Sea.

  • 2 January 2012
    Authorities

    The Federal Maritime and Hydrographic Agency has approved 97 wind turbines in German North Sea. 97 wind turbines are planned for the 43 square kilometers area. Dong Energy will build BR2 as the second phase of BR1. Borkum Riffgrund 1 will consist of up to 89 turbines with 3.6MW capacity each from Siemens Wind Power […]

  • 16 March 2018
    Operations & Maintenance, Ports & Logistics, Wind Farm Update

    EMS Maritime Offshore GmbH (EMO) will from March 2018 onward provide MHI Vestas Offshore Wind with port facilities and logistics services in Emden for the Borkum Riffgrund 2 offshore wind farm.

  • 9 May 2018
    Grid Connection, Operations & Maintenance, Wind Farm Update

    Van Oord’s new tracked remotely operated vehicle (TROV) Dig-It has begun burying the inter-array cables at Ørsted’s Borkum Riffgrund 2 offshore wind farm, marking its first deployment.

  • 8 February 2017
    Operations & Maintenance, Technology, Wind Farm Update

    Palfinger Marine has won a contract to supply davit cranes for DONG Energy’s 450MW Borkum Riffgrund 2 offshore wind farm in the German part of the North Sea. Palfinger Marine will supply a total of 56 davit cranes which will be installed on the platform of each wind turbine at the site. The offshore wind […]