Search results for: Arkona

129 results

A list of search results

17 April 2019 Business & Finance, Wind Farm Update

[…]

16 April 2019 Wind Farm Update

[…]

16 April 2019 Grid Connection, Wind Farm Update

[…]

24 October 2018 Ports & Logistics, Wind Farm Update

Wind turbine installation on the Arkona offshore wind farm has been completed ahead of schedule and in record time, E.ON said.

1 October 2018 Vessels, Wind Farm Update

45 out of 60 Siemens Gamesa 6MW wind turbines have been installed on the 385MW Arkona offshore wind farm in the German Baltic Sea, a spokesperson for E.ON told Offshore WIND.

24 September 2018 Grid Connection, Operations & Maintenance, Wind Farm Update

The 385MW Arkona offshore wind farm in the German part of the Baltic Sea has supplied the first electricity to the German electricity grid.

20 September 2018 Business & Finance, Contracts & Tenders, Wind Farm Update

French energy company Engie has signed a 4 year power-purchase agreement with OWP Arkona, a joint venture of E.ON and Equinor.

23 July 2018 Grid Connection

Manor Renewable Energy (MRE) Ltd will provide the full temporary power package of generators, personnel and vessels for E.ON during the turbine installation of the Arkona offshore wind farm.

9 July 2018 Vessels

Acta Marine’s first 24-passenger capacity crew transfer vessel (CTV) Offshore Wielingen is currently working at the Arkona offshore wind farm, which marks its first mobilization.

5 July 2018 Wind Farm Update

The first of the total of 60 wind turbines has been installed at the Arkona offshore wind farm, located off the coast of Rügen in the German Baltic Sea.

19 April 2018 Ports & Logistics, Wind Farm Update

The port service provider Mukran Port Terminals (MPT) has handled the first six wind turbine tower segments delivered for the 385MW Arkona offshore wind farm at the Mukran Port in Sassnitz, Germany.

9 April 2018 Operations & Maintenance, Vessels, Wind Farm Update

Vroon’s subsea-support walk-to-work (W2W) vessel VOS Stone has commenced operations at the 385MW Arkona offshore wind farm in the German Baltic Sea.

9 April 2018 Grid Connection, Vessels, Wind Farm Update

Seaway Heavy Lifting’s crane vessel Oleg Strashnow has installed the offshore substation topside on the 385MW Arkona offshore wind farm in the German Baltic Sea.

27 March 2018 Vessels, Wind Farm Update

At the beginning of April, Seaway Heavy Lifting’s vessel Oleg Strashnov will install the 4,000-tonne Arkona topside onto its jacket foundation.

22 March 2018 Grid Connection, Ports & Logistics, Wind Farm Update

The offshore substation topside built for the Arkona offshore wind farm has left STX France’s yard in Saint Nazaire and is now en route to the German Baltic Sea.

13 March 2018 Contracts & Tenders, Operations & Maintenance, Wind Farm Update

Muehlhan Wind Service (MWS) has won a contract by Siemens Gamesa to build/pre-assemble the wind turbine towers ahead of the installation on the 385MW Arkona offshore wind farm in the German Baltic Sea.

8 March 2018

Cathie Associates have performed a study which enabled the reduction of noise in the water column created by monopile driving at the Arkona offshore wind farm site in Germany, the company informed after all the 60 foundations were installed.

2 March 2018 Grid Connection, Ports & Logistics, Wind Farm Update

STX France has organised a delivery ceremony for the Arkona offshore substation in Saint-Nazaire, France.

27 February 2018 Grid Connection, Wind Farm Update

STX France has transported the offshore substation jacket foundation for the Arkona offshore wind farm to a quay in the Saint-Nazaire Port, from where it will be placed on a barge and transported to the wind farm site in the German Baltic Sea.

23 February 2018 Vessels

Following the installation of all 60 transition pieces at the Arkona offshore wind farm in mid-January, Jumbo posted a video showing the works that were completed ahead of schedule at the offshore wind farm site in Germany. 

23 February 2018 Ports & Logistics

The Mukran Port is upgrading two berths with new heavy load slabs to be used in the construction of the Arkona offshore wind farm.

30 January 2018 Grid Connection, Ports & Logistics, Wind Farm Update

STX France has moved the offshore substation topside for the Arkona wind farm from the Forme B dock in Saint-Nazaire to the Forme 1 dock belonging to the Port Authorities.

17 January 2018 Wind Farm Update

All 60 transition pieces (TPs) have been installed on the Arkona offshore wind farm ahead of schedule, E.ON, the owner and developer of the 385MW project in the German Baltic Sea.

28 December 2017 Wind Farm Update

The photo, shared by E.ON, is showing some of the 60 transition pieces waiting in the Mukran Port in Sassnitz to be installed on the Arkona offshore wind farm.

11 December 2017 Operations & Maintenance, Vessels

Vroon has christened its new subsea-support walk-to-work (W2W) vessel VOS Stone at a ceremony held in Rotterdam, the Netherlands.

4 December 2017 Vessels, Wind Farm Update

Jumbo’s Heavy Lift Crane Vessel (HLCV) Fairplayer is now installing transition pieces (TPs) at the Arkona offshore wind farm. The vessel was outfitted with an SMST gangway shortly before the works started in early November, according to SMST.