329 results found for 'kriegers flak'

329 results found for 'kriegers flak'
Order results by

A list of search results

  • 26 October 2017
    Business & Finance, Contracts & Tenders, Grid Connection, Vessels, Wind Farm Update

    Energinet and 50Hertz Transmission GmbH are seeking a jack up rig or a vessel capable of providing accommodation and other services for crew and personnel to be positioned next to an offshore substation on the Kriegers Flak offshore wind farm in the Danish Baltic Sea.

  • 22 January 2021
    Authorities, Grid Connection, Wind Farm Update

    On 21 January, the Danish Energy Agency (DEA) granted an electricity production permit and issued an electricity production license to Vattenfall for the Kriegers Flak offshore wind farm in Denmark. The permit is valid for 25 years from the time when the first electricity is delivered from the offshore wind farm to the grid. The […]

  • 4 December 2020
    Wind Farm Update

    Asso.subsea has completed the boulder removal campaign for the Kriegers Flak offshore wind project in the Danish Baltic Sea. ASSO was responsible for the boulder clearance of 68 turbine installation locations for jacking operations and all related MBES & SSS surveys, approximately 3500 targets in total. The operations were executed in two campaigns, the first […]

  • 19 November 2019
    Wind Farm Update

    EEW Special Pipe Construction has completed steel construction on all of the monopiles for Vattenfall’s Kriegers Flak offshore wind farm at its plant in Rostock, Germany. 72 monopiles are now structurally ready and the next step is to coat the units, some of which are up to 65.6 metres long. This work should be completed […]

  • 21 December 2018
    Contracts & Tenders, Wind Farm Update

    Vattenfall has contracted Bladt Industries to deliver 72 transition pieces for the Danish Kriegers Flak offshore wind farm.

  • 10 April 2016
    Authorities, Business & Finance, Environment, Grid Connection, Operations & Maintenance, Vessels, Wind Farm Update

    World’s Largest OW Jack-Up Vessel Installs World’s Heaviest Monopile at Veja Mate OWF Offshore construction of the Veja Mate offshore wind farm has started with Seajacks Scylla having installed the heaviest monopile produced so far at the project site, according to DGI Doedijns, which provided hydraulic and software equipment for the pile-gripper used at the […]

  • 14 November 2019
    Grid Connection

    Danish transmission operator Energinet has selected AP Sensing to monitor the cables at the Kriegers Flak offshore wind project. AP Sensing is monitoring a total of 300km of cable, using 6 Distributed Temperature Sensing (DTS) units with a range of 30-50km for thermal profiling and to detect thermal abnormalities and 9 Distributed Acoustic Sensing (DAS) […]

  • 22 October 2019
    Business & Finance

    The Danish Energy Agency (DEA) is planning to grant the final approval for Vattenfall’s Kriegers Flak offshore wind project in January 2020. DEA has initiated a public consultation period regarding the project’s supplement environmental impact assessment (EIA) report. Relevant authorities and the public are invited to submit comments on the report by 17 December. After […]

  • 6 May 2015
    Authorities, Business & Finance

    The Danish Energy Agency (DEA) has launched a tendering process for country’s largest offshore wind farm, Kriegers Flak. The deadline for prequalification for the 600MW project is 1 October 2015, after which up to 10 applicants will be invited to submit the full tender by 8 November 2016. According to the document published by DEA, […]

  • 2 October 2015
    Wind Farm Update

    Danish Energy Agency (DEA) reported yesterday that it received eight applications for pre-qualification to participate in the tender for the 600MW Kriegers Flak, Denmark’s largest offshore wind farm. This is the largest number of applicants for a wind farm tender in Danish wind history. DEA said that the great interest shows that Denmark offers attractive framework conditions and an […]

  • 15 May 2020
    Wind Farm Update

    The first foundation at the Kriegers Flak offshore wind farm is now in place. Van Oord’s heavy lift vessel Svanen arrived at the project site off Denmark a few days ago to begin the installation work. The vessel will install a total of 72 monopile foundations, with the work expected to be completed in the […]

  • 4 March 2021
    Wind Farm Update

    Global Offshore has laid all of the inter-array cables at Vattenfall’s Kriegers Flak offshore wind farm in the Danish Baltic Sea. Using the cable lay vessel Normand Clipper, Global Offshore has now installed all 72 inter-array cables at the 605 MW wind farm. This is an interim milestone on the project, Global Offshore said, as […]

  • 1 September 2020
    Wind Farm Update

    On 28 August, the 72nd and final foundation including a monopile and a transition piece was installed at the Kriegers Flak offshore wind site in the Danish part of the Baltic Sea. The monopile foundations, installed by Van Oord’s havy lift vessel Svanen, were manufactured by EEW SPC in Germany, while Bladt Industries delivered the transition […]

  • 11 May 2020
    Vessels, Wind Farm Update

    Van Oord’s heavy lift vessel Svanen has arrived at the Kriegers Flak offshore wind project in Denmark to begin the installation of monopile foundations. The monopiles, manufactured by EEW Special Pipe Constructions, will be transported floating from Rostock, Germany, to the project site. The transition pieces are produced by Bladt Industries in Aalborg, Denmark. Van […]

  • 3 February 2020
    Authorities, Environment, Wind Farm Update

    Expected to be completed by the end of 2021, Kriegers Flak will comprise 72 Siemens Gamesa 8.4MW wind turbines and will be Denmark’s largest offshore wind farm once commissioned.

  • 29 November 2017
    Contracts & Tenders, Technology, Wind Farm Update

    UK-based cable protection systems specialist Tekmar Energy has won a contract to supply it’s Polyurethane J-tube bellmouths and cover disks for the HVAC transformer platforms on the 600MW Kriegers Flak project in the Danish Baltic Sea.

  • 15 May 2023
    Authorities, Business development, Research & Development

    Danish transmission system operator (TSO) Energinet has awarded Fugro a contract to deploy multiple floating LiDARs at the new offshore wind farm sites in Denmark. There are four new sites the Danish government has designated for offshore wind farms, which could add as much as 7.2 GW of new capacity: North Sea I (Nordsø I), […]

  • 10 March 2016
    Grid Connection

    ABB has received an order worth around $140 million from Energinet.dk in Denmark and 50Hertz Transmission in Germany to design, supply and install an HVDC converter station in Bentwisch, Northern Germany. The company will provide the complete HVDC station including transformers, converter valves, cooling systems, control and protection and other related equipment at the converter station. […]

  • 5 May 2020
    Wind Farm Update

    Sabik Offshore has marked the construction site at Vattenfall’s Kriegers Flak wind farm in the Danish Baltic Sea ahead of the offshore installation work scheduled to start this spring. The navigational safety specialist laid the planned 29 warning buoys at the site despite challenging weather conditions in February, with only a three-day installation window. Expected […]

  • 13 July 2018
    Business & Finance, Contracts & Tenders, Wind Farm Update

    Global healthcare company Novo Nordisk and bio innovator Novozymes have signed a long-term Power Purchase Agreement (PPA) with Vattenfall to source their electricity from the Kriegers Flak offshore wind farm, currently under construction off Denmark.

  • 28 September 2015
    Grid Connection

    The European Commission has granted the revised technical layout for the “Kriegers Flak – Combined Grid Solution” interconnection, planned by two transmission system operators, Energinet.dk from Denmark and 50Hertz from Germany. The project will receive funding of up to EUR 150 million from the European Energy Programme for Recovery (EEPR). The new interconnection is planned […]

  • 14 August 2017
    Authorities, Vessels

    Danish subsea services provider JD-Contractor assisted the Copenhagen Police with a recovery of the 17-metre submarine – UC3 Nautilus – which sank in Koge Bay on Friday, 11 August, under suspicious circumstances.

  • 14 August 2013
    Business & Finance, Grid Connection, Wind Farm Update

    Three suppliers have just been prequalified to bid for the supply of two transformer substations for the Kriegers Flak offshore wind project. During the fall, a tender for DC cable will be invited. “We are required to be ready with power supply 1st July 2018, when the first offshore wind turbines are scheduled to start […]

  • 21 August 2020
    Wind Farm Update

    Bladt Industries has loaded out the final transition piece for the Kriegers Flak offshore wind project in Denmark. According to the company, transition piece number 72 has been loaded onto the barge in Aalborg and is ready for sail-away towards the 605 MW wind farm. In total, 432 cans have been rolled, welded, painted and […]

  • 16 March 2015
    Authorities, Wind Farm Update

    The Danish Energy Agency (DEA) has issued updates on the latest developments in the country’s offshore wind sector.  On Wednesday, March 11, the DEA held a presentation on the Danish tenders at the seminar ‘Experience and Explore Denmark’. Kriegers Flak offshore wind farm status: The contract notice and the results from the last round of dialogue […]

  • 22 February 2013
    Authorities, Contracts & Tenders, Wind Farm Update

    In March 2012, the Danish Government entered into an energy agreement with several other political parties from the Danish Parliament. The agreement secures the needed investments for a further step to improve Denmark’s production of renewable energy. By the agreement the parties have decided to initiate a tendering process covering the installation of offshore wind […]