Search results for: Hornsea Two

492 results

A list of search results

  • 16 August 2016

    RenewableUK has welcomed the news that DONG Energy’s Hornsea Two offshore wind farm has gained planning consent from the UK Business and Energy Secretary, Greg Clark.  Wind power is currently delivering over 12% of the UK’s electricity, which is expected to increase to 20% by 2020 with offshore wind alone providing 10%. Offshore wind’s costs have […]

  • 30 September 2022
    Business & Finance, Wind Farm Update

    Ørsted has completed the divestment of 50 per cent of its 1.3 GW Hornsea Two project, the world’s largest offshore wind farm in operation. The developer sold half of the project to a consortium comprising AXA IM Alts, acting on behalf of clients, and Crédit Agricole Assurances. Ørsted announced the Hornsea Two offshore farm-down in […]

  • 4 December 2017
    Contracts & Tenders, Wind Farm Update

    Ørsted has hired Semco Maritime as Electrical Engineering Consultant (EEC) to develop electrical and mechanical basic engineering design of the 1.4GW offshore substation and the reactive compensation station for Hornsea Project Two.

  • 15 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK’s Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved an increase in the total works area for the Hornsea Project Two onshore substation site.

  • 31 May 2022
    Vessels

    Norway-based Norwind Offshore has taken delivery of Norwind Breeze, a former Platform Suply Vessel (PSV) that was converted into a Service Operation Vessel (SOV) by Vard. The vessel will soon be deployed on the Hornsea Two offshore wind farm under a contract with Ørsted, according to the vessel’s owner and operator. Hornsea Two, which is […]

  • 28 March 2022
    Business & Finance, Wind Farm Update

    Ørsted has signed an agreement to divest 50 per cent of its 1.3 GW Hornsea Two offshore wind farm in the UK to a consortium comprising AXA IM Alts and Crédit Agricole Assurances for GBP 3 billion (approximately EUR 3.6 billion). The transaction is expected to close in the second half of 2022, once the […]

  • 28 May 2021
    Wind Farm Update

    The first of the total 165 wind turbines has been installed on the Hornsea Two offshore wind farm in the UK, where the wind turbine installation phase began this week, as reported in our Premium news on 27 May. DEME’s installation vessel Sea Challenger, loaded with the first set of turbine components, arrived at the […]

  • 1 October 2018
    Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has awarded the South Korean LS Cable & System with a contract to supply the onshore cable for the Hornsea Project Two offshore wind farm.

  • 14 September 2020
    Wind Farm Update

    Bladt Industries has loaded out the first six out of the 135 anode cages built for the 1.4 GW Hornsea Project Two offshore wind farm. The first six transition pieces will soon follow, Bladt Industries said. The Danish company is in charge of manufacturing and delivering 135 transition pieces for the project. The units are […]

  • 10 July 2020
    Contracts & Tenders

    UK-based wireless telecommunications provider Vilicom has been appointed to provide a mobile network during the construction, development and deployment of Ørsted’s Hornsea Two offshore wind project in the UK. Vilicom’s communication infrastructure will be built and tested in the UK prior to installation on the 1.4 GW wind farm. According to the company, the fully […]

  • 11 March 2020
    Contracts & Tenders, Wind Farm Update

    The Buss Terminal Eemshaven, in the Netherlands, has secured a contract to serve as a base port for installing the foundations of the Hornsea Two offshore wind project. Under the deal secured with DEME Offshore, the Buss Terminal is responsible for the handling, storage and terminal logistics of the 165 monopiles and transition pieces at […]

  • 5 September 2022
    Business & Finance, Contracts & Tenders, Grid Connection, Wind Farm Update

    Ofgem has selected Diamond Transmission Partners as the preferred bidder for the offshore transmission of the Hornsea Two offshore wind farm in the UK. The company now has to resolve certain matters before being granted the Offshore Transmission Owner (OFTO) license for the 1.3 GW project. Diamond Transmission Partners has to establish the necessary arrangements […]

  • 30 April 2020
    Grid Connection, Wind Farm Update

    ABB has delivered and installed three shunt reactors in the onshore substation of the Hornsea Project Two offshore wind farm in the UK. In April 2018, Ørsted and Balfour Beatty started the construction of the onshore substation in North Killingholme. The project’s 39km onshore cable route runs from Horseshoe Point, east of Tetney, to the […]

  • 12 September 2018
    Business & Finance

    Ørsted is holding a supply chain event for the Hornsea Project Two offshore wind project in the UK North Sea.

  • 5 August 2020
    Wind Farm Update

    Per Aarsleff A/S has produced 89 out of the 165 concrete working platforms (CWPs) for Ørsted’s 1.4 GW Hornsea Project Two offshore wind farm. The CWPs are being built at Per Aarsleff’s concrete precast factory in Poland, Aarsleff BIZ, for Bladt Industries and EEW OSB, which are producing 135 and 30 transition pieces for the […]

  • 8 October 2021
    Wind Farm Update

    DEME Offshore has installed 100 turbines on the Hornsea Two offshore wind farm, with 65 more of Siemens Gamesa 8.4 MW units left to be put into place. The jack-up vessel Sea Challenger installed the first wind turbine at the end of May and in less than three months later the project had 50 wind turbines installed […]

  • 2 April 2019
    Contracts & Tenders

    Ørsted has contracted AMS Trenchless Specialists to conduct part of the onshore cable works for the Hornsea Project Two offshore wind farm in the UK. AMS Trenchless Specialists will conduct Horizontal Directional Drilling (HDD) at the landfall site in Horseshoe Point where the offshore cables meet the onshore cables under the more than GBP 1 million worth contract. Using […]

  • 28 February 2020
    Wind Farm Update

    EEW Offshore Structures Britain (EEW OSB) has upended the first transition piece for the Hornsea Two offshore wind project in the UK. In June 2019, Ørsted placed an order with EEW Special Pipe Constructions for 30 transition pieces for the 1.4GW project. The remaining 135 transition pieces will be manufactured and delivered by Denmark’s Bladt Industries. EEW […]

  • 24 July 2019
    Contracts & Tenders, Grid Connection

    Seaway 7, a unit of Subsea 7, has won a contract for the installation of the inter-array grid cable system at the Hornsea Project Two offshore wind farm in the UK. In addition to the submarine cable installation works, Seaway 7 will undertake a pre-installation submarine cable route survey, perform pre-installation boulder clearance activities and […]

  • 11 February 2021
    Wind Farm Update

    Around 20 per cent of foundations has been installed at the 1.4 GW Hornsea Two, which is soon to become the world’s largest offshore wind farm, Ørsted said. The export cable installation works are on schedule and turbine installation is set to commence in the second half of this year, the project’s owner and developer […]

  • 21 October 2021
    Wind Farm Update

    Ørsted’s 1,386 MW Hornsea Two offshore wind farm, soon to be the world’s largest, has reached several significant construction milestones, with more to come in the coming days. All of the wind farm’s turbine foundations have now been installed, as well as the project’s offshore substation at the North Sea site 89 kilometres off the […]

  • 26 April 2022
    Business & Finance, Grid Connection, Wind Farm Update

    NKT has commissioned the 220 kV HVAC export cable system connecting the 1.3 GW Hornsea Two offshore wind project to the UK grid. NKT manufactured the power cables for the project at its factory in Karlskrona, Sweden. The installation of the subsea cables was completed by the cable-laying vessel NKT Victoria. “Constructing a project of […]

  • 18 January 2019
    Business & Finance

    Ørsted is holding a series of community information events about the onshore cable route for the Hornsea Project Two offshore wind project in the UK. According to the Danish company, the aim of the events is that local people in North East Lincolnshire and East Lindsey find our more about the onshore cabling works for the […]

  • 8 June 2021
    Ports & Logistics, Vessels, Wind Farm Update

    DEME Offshore’s jack-up Sea Installer has arrived at the Port of Hull in the UK to load the first set of turbine components to be installed on the 1,386 MW Hornsea Two offshore wind farm. Sea Installer is joining her sister vessel Sea Challenger on the project which has already installed the first batch of […]

  • 9 August 2021
    Operations & Maintenance, Ports & Logistics, Vessels, Wind Farm Update

    Ørsted’s new service operations vessel (SOV) Wind of Hope has arrived in the Port of Grimsby in the UK to prepare for working out at sea on the world’s largest offshore wind farms. Up to 60 of Ørsted’s wind turbine technicians will call the 84-metre vessel home for two weeks at a time, whilst they […]

  • 21 August 2015
    Business & Finance, Wind Farm Update

    Today, DONG Energy acquired the Hornsea Zone and the project rights to Hornsea Project Two and Three, which have the potential of 3 gigawatts (GW) of offshore wind capacity. This follows DONG Energy’s acquisition of Hornsea Project One, a 1,200 megawatt (MW) offshore wind project in the Round 3, which was announced in February 2015. […]