  • 10 May 2017
    Business & Finance, Wind Farm Update

    The 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm project in the German North Sea has reached financial close, Green Giraffe said. Green Giraffe was the sole financial advisor to TWBII, initially owned by EWE and Trianel. Green Giraffe helped arrange the sale of a minority stake to ewz, the Swiss utility, and compatriot […]

  • 28 March 2019
    Ports & Logistics, Wind Farm Update

    The first wind turbine nacelles built by Senvion for the Trianel Windpark Borkum II wind farm have started their journey to the Buss Terminal Eemshaven in the Netherlands. The first of the 32 Senvion 6.2M152 wind turbines are expected to be installed at the site some 40 kilometres north of the island of Borkum in the German North Sea […]

  • 15 August 2019
    Wind Farm Update

    Jan De Nul’s vessel Taillevent has installed the first turbine at the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the island of Borkum in the German North Sea. Taillevent is loading the turbine components in sets […]

  • 24 January 2023
    Contracts & Tenders, Vessels

    Trianel Windkraftwerk Borkum II (TWBII) GmbH has issued a contract notice seeking crew transfer vessel (CTV) services for its offshore wind farm in Germany. TWBII requires CTV services for the transportation of personnel as well as material, components, and spare parts to the Trianel Windpark Borkum II offshore wind farm as well as possibly other wind […]

  • 2 March 2017
    Business & Finance

    8.2 Consulting has carried out the technical due diligence on the transaction of Swiss utility Elektrizitätswerk der Stadt Zürich (ewz) together with the country’s asset manager Fontavis for Trianel Windpark Borkum II (TWB II).

  • 2 August 2019
    Vessels, Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent has left Eemshaven with a first load of turbine components to be installed on the Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea. Taillevent is loading the turbine components at the Buss Terminal Eemshaven in sets of three and transporting them to the installation […]

  • 3 December 2018
    Wind Farm Update

    All 32 turbine foundations for the 200MW Trianel Windpark Borkum II offshore wind farm have been installed at the construction site some 45 kilometers north of the island of Borkum in the German North Sea. “We are right on schedule with the construction of the offshore wind farm. We were able to compensate for the […]

  • 4 June 2018
    Vessels

    Vroon has christened its newest platform supply vessel (PSV) VOS Patriot, which is set to be deployed at the Trianel Windpark Borkum II offshore wind farm in the German North Sea.

  • 16 March 2020
    Contracts & Tenders

    Trianel Windkraftwerk Borkum II GmbH & Co. has issued a tender seeking transport services of personnel and material for the Trianel Windpark Borkum II (TWBII) in Germany. The contractor will be in charge of providing the transport of personnel and material between the harbor of Eemshaven in the Netherlands and the project construction site some 40km […]

  • 16 June 2020
    Contracts & Tenders, Wind Farm Update

    Trianel Windkraftwerk Borkum has issued a contract notice for insurance policy services covering the 200 MW Trianel Windpark Borkum I offshore wind farm in the German North Sea. The contract covers combined property damage and business interruption all risks insurance for the operational phase of the wind farm consisting of 40 offshore wind turbines including […]

  • 14 October 2019
    Operations & Maintenance, Vessels

    Trianel Windkraftwerk Borkum has issued a tender for the provision of two crew transfer vessels (CTVs) to service the 200MW Trianel Windpark Borkum I in the German North Sea and nearby offshore wind farms. The wind farm operator is looking for a provider or providers of two CTVs, one with a capacity of at least twelve persons […]

  • 15 July 2019
    Wind Farm Update

    Jan De Nul’s offshore installation vessel Taillevent is en route to Eemshaven in the Netherlands to start loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. Located in the German North Sea, the 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 wind turbines installed at the site some 40 […]

  • 4 February 2011
    Grid Connection

    On 20 December 2010, Trianel Windkraftwerk Borkum GmbH & Co KG (“TWB”) activated an order with Norddeutsche Seekabelwerke GmbH (“NSW”) to deliver and install 65 km of medium-voltage submarine cables for the first construction phase of the Trianel Borkum West II offshore wind farm. The order is worth an amount in excess of € 22 […]

  • 25 December 2019
    Contracts & Tenders

    Trianel Windkraftwerk Borkum has opened a tender seeking CPS retrofit and bolt exchange services for the Trianel Windpark Borkum offshore wind project. The awarded company will be in charge of subsea works on CPS retrofits and subsea bolt exchanges at diffusor plates, i.e. steel plate under the central column of the tripod foundation. The scope […]

  • 4 October 2019
    Contracts & Tenders, Operations & Maintenance

    Trianel Windkraftwerk Borkum has issued a tender seeking corrective maintenance work for the Trianel Windpark Borkum offshore wind farm in Germany. The contractor will be in charge of the corrective maintenance and optional repair/refurbishment of major components such as gearboxes, generators, blade sets and rotor hubs. The tender also covers work on the MV converters, MV switchboards, main […]

  • 25 February 2020
    Vessels, Wind Farm Update

    Fred. Olsen Windcarrier’s jack-up vessel Blue Tern has been contracted to finish installing the remaining eleven Senvion 6.2M152 turbines on the Trianel Windpark Borkum II (TWB II) in the German North Sea. Blue Tern will replace Jan De Nul’s Taillevent on TWB II as this jack-up is reportedly on its way to start a project […]

  • 24 December 2019
    Contracts & Tenders, Grid Connection

    Trianel Windkraftwerk Borkum has issued a tender for the replacement of defective inter-array cables at the Trianel Windpark Borkum offshore wind farm in Germany. The subject of the contract is the replacement of defective inter-array cables between turbines and/or the offshore substation, including the provision of required vessels, equipment, personnel and project execution documentation. Furthermore, the deal […]

  • 22 January 2016
    Business & Finance, Contracts & Tenders, Grid Connection, Operations & Maintenance, Wind Farm Update

    Oldenburg-based Trianel Windkraftwerk Borkum II has invited tenders for the production and turnkey installation of the inner park cabling at the 200 MW Trianel Windpark Borkum (TWB) Phase 2, situated in the German exclusive economic zone in the North Sea. The TWB Phase 2 sits 45 kilometers north of the island of Borkum at a water depth […]

  • 13 June 2017
    Wind Farm Update

    Seaway Heavy Lifting has awarded Sif Holding, in a joint venture with Smulders, a contract for production of all monopiles and transition pieces for the Trianel Windpark Borkum II (TWB II) offshore wind farm.

  • 10 June 2020
    Contracts & Tenders, Operations & Maintenance

    Trianel Windkraftwerk Borkum is seeking a provider of marine, flight, and emergency response coordination services at the Trianel Windpark Borkum I wind farm in the German North Sea. The tender is divided into two lots. Lot 1 covers the marine, flight, and emergency response coordination services, plus operations control at the 200 MW wind farm. […]

  • 4 February 2020
    Wind Farm Update

    Twenty-one of the 32 Senvion 6.2M152 turbines have been installed on the Trianel Windpark Borkum II (TWBII) offshore wind project in Germany.

  • 18 March 2016
    Wind Farm Update

    First purely municipal offshore wind farm installed off German coast, Trianel Windpark Borkum, has been in operation for half a year now, and has generated 452.33GWh of electricity, with January 2016 as the month with the highest yield so far – 95.12GWh. Construction on the wind farm began in September 2011. From July 2013, all 40 AREVA Wind M5000-116 […]

  • 17 September 2019
    Operations & Maintenance

    C-bed’s accommodation vessel Wind Innovation is servicing the installation and commissioning phases of the Trianel Windpark Borkum II (TWBII) project in Germany. The DP2 walk-to-work vessel began its deployment at the project site some 45km off the coast of the Borkum island at the end of July. C-bed is using Eemshaven as the base port for crew change and […]

  • 30 July 2014

    A huge increase in the size of wind turbines being installed and a move to installations in deeper water have led to the design and installation of huge subsea structures. One location for such installations is the Trianel Wind Farm Borkum West II, situated 45 km off the German coast. Its huge steel tripod bases […]

  • 2 March 2017

    Siem Offshore Contractors has awarded Seaproof Solutions with a contract for the design and supply of cable protection systems for the inter-array subsea cables at the Trianel Windpark Borkum II offshore wind farm in Germany.

  • 2 October 2015
    Business & Finance, Wind Farm Update

    EWE AG and Trianel have set up a joint venture to develop the second stage of the Trianel Windpark Borkum (TWB II) with a capacity of 200MW. Ines Kolmsee, Chief Operating Officer of EWE AG, stated: “EWE brings in its expertise from the development and operation of the first German offshore wind farm alpha ventus and the first […]