    Dogger Bank Wind Farm, a 50:50 joint venture between SSE Renewables and Equinor, has signed a contract with GE Renewable Energy for 190 wind turbines for the Dogger Bank A & B offshore wind project. Dogger Bank A & B will be the world’s first offshore wind farm to use GE’s Haliade-X 13 MW turbines, […]

  • 1 April 2019
    Ports & Logistics, R&D, Technology

    Future Wind has organized a ground-breaking event in Maasvlakte, Rotterdam, to mark the start of preparatory activities to host GE’s Haliade-X 12 MW wind turbine prototype. Earlier this year, GE Renewable Energy and Future Wind, a joint venture between Pondera Development and SIF Holding Netherlands, signed an agreement to install the first Haliade-X 12 MW wind […]

  • 16 January 2019
    Business & Finance, Technology

    GE Renewable Energy and Future Wind, a joint venture of Pondera Development and Sif, have signed an agreement to install the first Haliade-X 12MW wind turbine prototype in the Port of Rotterdam this summer. The agreement, which will see the Haliade-X 12MW prototype installed onshore to facilitate access for testing, includes five years of testing and […]

  • 5 October 2021
    R&D, Technology

    GE Renewable Energy’s Haliade-X prototype in Rotterdam, the Netherlands, has started operating at 14 MW. With this new milestone, GE Renewable Energy becomes the first industry player to operate a turbine at this power output, the turbine maker said. The Haliade-X 14 MW is an uprated version of the Haliade-X 13 MW, which received its […]

  • 7 November 2019
    Technology

    The GE Haliade-X 12MW prototype wind turbine located at Maasvlakte, the Port of Rotterdam, has produced its first power. According to GE, local teams will now proceed with the testing phase, during which different types of measurements will be performed to obtain a Type Certificate for the Haliade-X in 2020. The serial production of the […]

  • 15 August 2019
    Technology

    The first LM 107.0 P blade for GE’s Haliade-X 12MW turbine has arrived at Offshore Renewable Energy (ORE) Catapult’s testing site in Blyth, the UK. Over the coming months, the blade will undergo advanced testing procedures, with static and fatigue tests to demonstrate its ability to withstand peak wind conditions and simulate its readiness for […]

  • 17 November 2021
    Operations & Maintenance, Technology

    GE Renewable Energy has selected Cotes to provide dehumidifiers for the GE Haliade-X offshore wind turbines. The dry-air solution that Cotes provides to GE Renewable Energy, a combined desalter and dehumidifier, is now approved for global Haliade-X wind farm projects starting with the Dogger Bank wind farm in the North Sea, Cotes said. ”It is […]

  • 10 November 2020
    R&D, Technology

    LM Wind Power’s 107-metre blade for the GE Renewable Energy’s Haliade-X wind turbine has received its Component Certificate from TÜV Nord. The component certification hinged on the testing of two blades produced at LM Wind Power’s factory in Cherbourg, France, the company said. One blade completed its testing at the WTTC test facility in Boston, […]

  • 11 October 2021
    Contracts & Tenders, Wind Farm Update

    GE Renewable Energy has received a firm order from Vineyard Wind to supply Haliade-X wind turbines for Vineyard Wind 1, the first utility-scale offshore wind installation in the US. GE was announced as the preferred turbine supplier for the project in December of 2020. Vineyard Wind 1 recently became the first offshore wind farm in […]

  • 12 November 2020
    Technology

    GE Renewable Energy’s Haliade-X 12 MW prototype has received a full type certificate from DNV GL. This full type certification, which follows a provisional type certification announced in June, provides independent verification that the new turbines will operate safely, reliably, and according to design specifications, the turbine maker said. The process of certifying the Haliade-X […]

  • 21 February 2019
    R&D, Technology

    GE’s Haliade-X 12 MW offshore wind turbine is well suited and competitive for monopile solution over a wide range of site conditions, according to the specialist engineering firm Gavin and Doherty Geosolutions (GDG). GDG has been working with GE Renewable Energy to develop optimized XL Monopile soil-structure interaction models to support GE’s development of optimized foundation designs for […]

  • 14 December 2022
    Contracts & Tenders

    GE Renewable Energy and Hyundai Electric have signed a strategic partnership agreement to help localise the assembly of GE’s Haliade-X offshore wind turbines and generators in South Korea. The agreement outlines plans for the establishment of a factory in South Korea for producing the nacelles and the generators used in Haliade-X turbines, with the potential […]

  • 13 April 2021
    Contracts & Tenders, Technology

    Bakker Magnetics is about to start the production of magnetic assemblies for the GE Haliade-X turbines that will be installed at the 3.6 GW Dogger Bank offshore wind project in the UK. Bakker Magnetics will fabricate and assemble magnetic assemblies for the turbines across all three phases of what is the world’s largest offshore wind […]

  • 18 January 2021
    Contracts & Tenders, Wind Farm Update

    GE Renewable Energy has signed supply and service contracts for the 1.1 GW Ocean Wind offshore wind farm in New Jersey, which will use the company’s Haliade-X offshore wind turbines. The contracts, subject to final notice to proceed, cover the GE Haliade-X 12 MW wind turbine with an option for Ocean Wind to utilise the […]

  • 3 February 2022
    Wind Farm Update

    The Netherlands-based foundation manufacturer Sif Group has completed the first several monopiles for the world’s largest offshore wind farm under construction – the 3.6 GW Dogger Bank in the UK. Sif manufactured the monopiles at its factory on Maasvlakte 2 in the Port of Rotterdam. The monopiles produced will be installed on the 1.2 GW […]

  • 26 March 2020
    Technology

    ABB has delivered its higher power medium voltage PCS6000 converters for GE’s Haliade-X 12 MW offshore wind turbine prototype installed in the Port of Rotterdam, the Netherlands. Officially inaugurated in mid-December 2019, the Haliade-X 12 MW turbine prototype reached its nominal output of 12 MW feeding into the public grid by the end of 2019 […]

  • 20 January 2021
    Technology

    GE Renewable Energy has officially received a type certificate from DNV GL for the Haliade-X offshore wind turbine with a 13 MW power output. The Haliade-X 12 MW prototype, installed in the Port of Rotterdam in 2019, obtained a full type certificate from DNV GL in November 2020. The prototype has then been optimized to […]

  • 3 December 2019
    Business & Finance

    GE Renewable Energy is holding an official inauguration ceremony for the first Haliade-X 12MW, the world’s most powerful offshore wind turbine, on 17 December. The event will be held in the Futureland Museum at Maasvlakte Rotterdam in the Netherlands, next to where the GE Haliade-X 12MW is installed. To remind, the third and final LM […]

  • 2 December 2020
    Wind Farm Update

    Vineyard Wind has selected GE Renewable Energy as the preferred turbine supplier for the first U.S. large-scale offshore wind project. Vineyard Wind 1 will feature the GE Haliade-X units, the most powerful offshore wind turbine in operation to date. As a part of reaching this milestone, the developer has also decided to temporarily withdraw its Construction […]

  • 25 January 2021
    Authorities, Wind Farm Update

    US offshore wind developer Vineyard Wind is rescinding its recent request to withdraw the Construction and Operations Plan (COP) for the Vineyard Wind 1 wind farm, allowing the federal permitting process to resume. Back in December, Vineyard Wind temporarily withdrew the COP from further review by the Bureau of Ocean Energy Management (BOEM) to allow […]

  • 28 March 2022
    Wind Farm Update

    Offshore construction has started on Dogger Bank A, the first of the three 1.2 GW phases of the 3.6 GW Dogger Bank Wind Farm, the world’s largest offshore wind farm under construction. The offshore works are kicking off with a geophysical pre-lay survey along the Dogger Bank Aexport cable corridor in the Southern North Sea […]

  • 1 December 2020

    We bring you the ten most-read articles on the OffshoreWIND.biz site for the month of November 2020. Two-Turbine Floater Prototype Breezes Through Tests in Baltic Sea The scaled-down version of the Nezzy² floating wind turbine, a two-turbine floating wind platform, completed its two-month tests in the Bay of Greifswald in the Baltic Sea and has […]

  • 10 June 2021
    Contracts & Tenders, Technology, Wind Farm Update

    ABB will deliver 95 units of medium voltage converters for wind turbines to GE Renewable Energy for the first phase of the Dogger Bank offshore wind project. This is ABB’s first major order under its Long-Term Supply Agreement (LTSA) with GE Renewable Energy and the largest order of its kind to date. The 95 PCS6000 […]

  • 19 September 2019
    Wind Farm Update

    Ørsted has selected GE Renewable Energy as the preferred turbine supplier for two of its US offshore wind farms which marks the world’s first commercial deployment of GE’s Haliade-X 12 MW offshore wind turbine. Subject to final agreed and signed contract and all required project approvals, Ørsted will deploy Haliade-X 12MW wind turbines on the […]

  • 1 December 2022
    Authorities, Technology

    Judge Richard Meade of London’s High Court has ruled in favour of GE in a patent infringement dispute with Siemens Gamesa over the design of the GE Haliade-X offshore wind turbine. In its lawsuit against GE, Siemens Gamesa claimed that the Haliade-X infringed its European patent related to the use of bearings in rotor hubs […]

  • 19 May 2022
    Contracts & Tenders, Wind Farm Update

    UK-based Fulkrum has secured a contract to support the QA/QC-quality assurance/quality control activities for the first phase of the 3.6 GW Dogger Bank Wind Farm project offshore England. Under the contract, Fulkrum will provide inspection services during the Dogger Bank A development stage, with a possibility of a contract extension to Dogger Bank B and […]