21 June 2019 Business & Finance

The Hornsea Project One offshore wind farm has begun receiving Contract for Difference (CfD) payments. The Low Carbon Contracts Company (LCCC) began allocating the payments for the first phase of the 1.2GW offshore wind project as it passed the required tests for its Operational Conditions Precedent (OCP). The first project phase, with a capacity of 400MW, achieved a […]

18 June 2019 Wind Farm Update

The 1,218MW Hornsea Project One wind farm has reached the halfway turbine installation point, Ørsted said. 87 out of the wind farm's 174 Siemens Gamesa wind turbines have now been installed and commissioned at the site some 120 kilometres off Yorkshire. The wind turbines are being transported from Hull and installed by Fred. Olsen Windcarrier's […]

3 June 2019 Operations & Maintenance, Wind Farm Update

Ørsted has officially started operations on the 1,214MW Hornsea One, the largest offshore wind farm in the world. The project’s first operational team of 32 set sail from Grimsby Royal Docks to the wind farm located 120 kilometres out to sea on 31 May. They are part of two shift-based teams that are responsible for […]

13 May 2019 Grid Connection

JDR Cable Systems has completed the termination and testing of east section inter-array cables at the Hornsea Project One offshore wind farm. JDR conducted the work from the service operations vessel (SOV) Edda Mistral and will now focus on completing the western cluster of the 1.2GW project, which represents the final phase. Ørsted and JDR […]

8 May 2019 Ports & Logistics, Wind Farm Update

Windhoist Limited has pre-assembled 78 out of 174 wind turbine towers for the 1,218MW Hornsea Project One wind farm at Siemens Gamesa’s pre-assembly site in Hull. The Ayrshire-based company is providing Siemens Gamesa with the pre-construction support for 174 Siemens Gamesa SWT-7.0-154 wind turbines which are currently being installed at the site some 120 kilometres offshore Yorkshire. […]

26 April 2019 Wind Farm Update

DEME Offshore installed the final of the 174 monopile foundations on the 1.2GW Hornsea Project One offshore wind farm on Thursday, 25 April. The first monopile was installed at the site some 120 kilometres off the Yorkshire coast in the UK in January 2018. According to DEME, four of the company's jack-ups has since worked at […]

24 April 2019 Operations & Maintenance, Vessels

Leask Marine’s vessel C-Fenna has completed wave buoy works on the Hornsea Project One offshore wind farm in the UK. The vessel completed wave rider recovery and deployment operations for Fugro GB, who performed a variety of maintenance service operations on each buoy at the 1.2GW offshore wind project. Each buoy was retrieved onto the deck for servicing and […]

1 April 2019 Contracts & Tenders, Grid Connection

Semco Maritime has signed a service contract for Ørsted's Hornsea Project One offshore wind farm in the UK. Under the two-year agreement, Semco will service and maintain the project's reactive compensation station (RCS) and the three offshore substations (OSS). The contract runs until the beginning of 2020 and will be carried out from Semco’s office in Grimsby, […]

27 March 2019 Vessels

Geo Therm Ltd. has won a contract to perform inspections on the Self Elevating Support Vessel (SESV) GMS Endeavour during work on the Hornsea Project One offshore wind farm. Geo Therm is collaborating with LEC Marine (Klyne) to carry out an electrical-biased thermographic inspection on the switchboards, distribution and thruster systems throughout the entire Gulf Marine Services' vessel. […]

18 March 2019 Business & Finance, Vessels

Danish company MH-O&C has taken delivery of crew transfer vessels (CTVs) MHO Gurli and MHO Esbjerg, destined for Ørsted's Hornsea Project One offshore wind farm in the UK. MH-O&C launched MHO Gurli in November last year, with the vessel's naming ceremony held this February. According to Incat Crowther, the designer, the two 39m long vessels are the largest […]

4 March 2019 Grid Connection, Wind Farm Update

Sparrows Group Cable and Pipe Lay Solutions (CPLS) division has delivered its largest renewables project through three contracts related to the 1.2GW Hornsea Project One offshore wind farm. The three contracts were awarded through Boskalis (formerly VBMS), DEME Offshore (formerly known as Tideway), and DeepOcean. The work scope saw Sparrows provide equipment and personnel to […]

26 February 2019 Wind Farm Update

Fred. Olsen Windcarrier's jack-up Bold Tern has departed from Hull, the UK, carrying the second batch of turbines for the Hornsea Project One offshore wind project. The vessel installed the first Siemens Gamesa 7MW turbine at the site some 120km off the Yorkshire coast in early February. Bold Tern is in charge of transporting and installing half […]

20 February 2019 Vessels

Danish company MH-O&C has held a naming ceremony for the crew transfer vessel (CTV) MHO Gurli. The 39m long Fast Supply Cat vessel was ordered by Ørsted for the Hornsea Project One offshore wind farm in the UK and is expected to enter service shortly. MHO Gurli has a 10.3m beam, a max draft of […]

18 February 2019 Vessels, Wind Farm Update

A2SEA's wind turbine installation vessel Sea Challenger has left Hull with a first load of turbine components to be installed on the 1,218MW Hornsea Project One offshore wind farm. A2SEA is in charge of transporting and installing half of the wind farm's 174 Siemens Gamesa 7MW turbines. The remaining half of the turbines is being […]

6 February 2019 Vessels, Wind Farm Update

Fred. Olsen Windcarrier's jack-up vessel Bold Tern has arrived at the Hornsea Project One offshore wind farm in the UK ready to install the first turbines. According to the UK-based company, the vessel left the Alexandra Dock in Hull yesterday morning after picking up the first batch of Siemens Gamesa 7MW turbines. Bold Tern is in […]

1 February 2019 Vessels, Wind Farm Update

Fred. Olsen Windcarrier's jack-up vessel Bold Tern has arrived in Hull, the UK, where it will begin its work for the Hornsea Project One offshore wind farm. According to Fred. Olsen Windcarrier, the vessel arrived in Hull yesterday afternoon and is ready to pick up the turbines for the 1.2GW project. Bold Tern is in charge of […]

25 January 2019 Operations & Maintenance, Wind Farm Update

Windhoist Limited has pre-assembled the first Siemens Gamesa turbines destined for the Hornsea Project One offshore wind farm in the UK. According to the UK-based company, 24 Siemens Gamesa SWT-7.0-154 turbines are now standing ready for the vessel to pick them up next month. Siemens Gamesa awarded Windhoist with the contract for the onshore turbine pre-assembly in September 2018. […]

3 January 2019 Contracts & Tenders, Operations & Maintenance

Siemens Gamesa has contracted Associated British Ports (ABP) to provide storage for 37 of its wind turbine blades destined for the Hornsea Project One offshore wind farm.

11 December 2018 Grid Connection, Wind Farm Update

Tideway BV, part of DEME Group, has completed the installation of the export cable at the Hornsea Project One offshore wind farm in the UK.

28 November 2018 Business & Finance, Vessels

MH-O&C has launched the newbuild crew transfer vessel (CTV) MHO Gurli which Ørsted ordered for its Hornsea Project One offshore wind farm in the UK.

28 November 2018 Business & Finance

The UK-based Aviva Investors has invested GBP 400 million to help fund the construction of Ørsted's Hornsea Project One offshore wind farm.

27 November 2018 Business & Finance, Wind Farm Update

Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

8 November 2018 Contracts & Tenders, Wind Farm Update

Manor Renewable Energy (MRE) has signed a contract with Ørsted for the Hornsea Project One offshore wind farm, under which MRE will provide the full temporary power package of generators, personnel and vessels in case of need during the turbine installation and commissioning.

2 November 2018 Ports & Logistics

The first of the 174 wind turbine towers for the 1.2GW Hornsea Project One has been upended at Siemens Gamesa's pre-assembly site in Hull.

1 November 2018 Wind Farm Update

104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed on the 1,218MW Hornsea Project One wind farm, Ørsted said.

5 October 2018 Wind Farm Update

Waves Group is providing Marine Warranty Surveyor services during the construction of the world’s largest offshore wind farm - the 1.2GW Hornsea Project One.