  • 25 March 2026
    Fixed-Bottom, Operations & Maintenance, Project Updates, Wind Farm Update

    RWE has officially opened the new operations and maintenance (O&M) base for the 1.1 GW Danish Thor offshore wind farm at Thorsminde Port. “The port of Thorsminde provides the quickest sea and air access to Thor offshore wind farm, making it the perfect location for our new service hub. Our first team members are already […]

  • 4 March 2026
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first wind turbine is now in place at the 1.1 GW Thor offshore wind farm site in Denmark. Thor will comprise 72 Siemens Gamesa SG 14-236 DD wind turbines, of which 40 will feature recyclable rotor blades, with 36 turbine towers to be manufactured with a significantly lower carbon footprint than usual, according to the project […]

  • 17 March 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    Denmark’s largest offshore wind farm under construction, Thor, delivered electricity into the national grid, operated by Energinet, for the first time on 16 March. “Reaching this milestone so soon after installing the first turbine demonstrates the exceptional performance of our project teams and partners, and how effectively they collaborate. Thor is progressing exactly as planned”, […]

  • 26 January 2026
    Authorities, Fixed-Bottom, Planning & Permitting, Project Updates, Wind Farm Update

    The Danish Energy Agency (DEA) has approved a 30-year electricity production licence to the Thor offshore wind farm, under construction at a site located approximately 22 kilometres off the west coast of Jutland. With a total installed capacity of 1.1 GW, Thor will become Denmark’s largest offshore wind project once fully operational in 2027, generating […]

  • 16 March 2026
    Contracts & Tenders, Operations & Maintenance, Supply Chain, Vessels

    Fred. Olsen Windcarrier and Siemens Gamesa have signed a long-term agreement, under which Fred. Olsen Windcarrier’s vessels will be deployed for operations and maintenance (O&M) work on offshore wind farms featuring Siemens Gamesa turbines. The agreement, which has a firm duration of ten years with additional optional periods, covers the provision of offshore wind O&M […]

  • 9 April 2026
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Waters off Denmark’s west coast are now home to what RWE says is the world’s first offshore wind turbine featuring a CO2‑reduced steel tower and recyclable rotor blades. The 1.1 GW Thor offshore wind farm, currently under construction some 22 kilometres off the west coast of Jutland, will comprise 72 Siemens Gamesa SG 14-236 DD […]

  • 6 May 2026
    Business & Finance, Industry

    RWE has announced changes to the management board of its offshore wind business, with CEO Sven Utermöhlen set to leave the company on 30 September 2026. Utermöhlen will not renew his contract and will step down at his own request, after which he will continue to advise RWE’s offshore wind division for a period of […]

  • 11 November 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    All 72 wind turbine foundations at the Danish Thor offshore wind site, developed by RWE, are now equipped with secondary steel and ready for the wind turbine installation, which is expected to start in the spring of 2026. The installation of the secondary steel structures, including boat landings, main access platforms, and internal cassettes, was […]

  • 10 November 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 150 recyclable blades have been installed at the 1.4 GW Sofia offshore wind farm, with more than half of the wind turbines now in place at the UK construction site. All 150 recyclable blades are now installed, 50 sets of three blades, one set per turbine, marking the UK’s first large-scale use of this […]

  • 14 October 2025
    Business & Finance, Business development, Vessels

    Dajin Heavy Industry has launched its first self-built heavy deck carrier designed to transport XXL components and equipment for the offshore wind, oil, and gas industries. The vessel is the first of four of the same type that the company is currently building, and could be the first in a fleet of 20 heavy deck carriers […]

  • 25 September 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    All 72 monopile foundations have been installed at RWE’s Thor offshore wind farm in the Danish North Sea. The monopiles are around 100 metres in length and weigh up to 1,500 tonnes each. The units were shipped from the heavy-lift terminal in Eemshaven, in the Netherlands, to the Thor construction site in the Danish North […]

  • 1 September 2025
    Authorities, Fixed-Bottom, Planning & Permitting

    The Danish Energy Agency (DEA) has revised the applications for feasibility study permits under the open-door scheme, for which the process was suspended in 2023 and reactivated last year. The DEA has now made new decisions in the cases and maintains the rejection of all 37 applications. The DEA put the processing of cases under […]

  • 28 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The jacket foundation and the substation topside have been installed at the 1 GW Thor offshore wind farm site in Denmark. Following the jacket and topside’s sail-away from HSM Offshore Energy’s Schiedam yard in the Netherlands, the installation of the 2,600-tonne topside was executed offshore, with the heavy-lift vessel Gulliver of Scaldis SMC placing the […]

  • 16 July 2025
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Vessels, Wind Farm Update

    Half of the monopile foundations are now in place at the Thor offshore wind farm site, as Jan De Nul’s heavy-lift vessel Les Alizés installed the 36th of the project’s total 72 monopiles on 15 July. “With Thor we are constructing Denmark’s largest offshore wind farm to date. Reaching halfway in the safe installation of […]

  • 17 July 2025
    Fixed-Bottom, Grid Connection, Manufacturing, Offshore Platforms, Project Updates, Supply Chain, Wind Farm Update

    The offshore substation for the 1 GW Thor offshore wind farm has left HSM Offshore Energy’s Schiedam yard in the Netherlands and is on its way to the project site in the Danish North Sea. “[The] sail-away of the fully assembled substation for THOR is an important step for us in the project team”, said […]

  • 21 August 2025
    Fixed-Bottom, Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    China’s Dajin Heavy Industry has completed the delivery of all 45 TP-less monopiles for the first phase of the 1.6 GW Nordseecluster development in the German North Sea. Dajin started manufacturing the monopiles at its Penglai facility in China in November 2024. The units are around 85 metres long on average and weigh approximately 1,500 […]

  • 4 July 2025
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    The fully assembled offshore substation for the 1 GW Thor offshore wind farm has been loaded out at HSM Offshore Energy’s Schiedam yard in the Netherlands. Both the jacket and the topside are now on the barges, and the structures are being prepared for sail-away to their destination off the Danish coast. In 2022, RWE, […]

  • 30 June 2025
    Cables, Grid Connection, Project Updates, Wind Farm Update

    Jan De Nul has pulled two export cables for the 1,080 MW Thor offshore wind farm, currently under construction in Denmark. The export cables will transport clean, renewable electricity from the offshore site 22 kilometres out in the North Sea to the Danish mainland. In 2023, Jan De Nul, together with Hellenic Cables, won a […]

  • 18 June 2025
    Grid Connection, Onshore Infrastructure, Project Updates, Wind Farm Update

    Danish transmission system operator (TSO) Energinet has completed the construction work related to the connection of the 1 GW Thor offshore wind farm to the national grid. The construction work began in January 2023 and has been completed on time, said Energinet. The scope of work included moving 95,000 cubic metres of soil and laying […]

  • 19 October 2023
    Business development, Contracts & Tenders, Research & Development, Supply Chain

    Dutch geo-data specialist company, Fugro, has been appointed by RWE to complete a geophysical survey off the Danish coast, where RWE will build the 1 GW Thor offshore wind farm. Up to three survey vessels will be deployed to carry out a detailed pre-construction survey including a search for unexploded ordnance (UXO) up to approximately 34 kilometres […]

  • 8 November 2024
    Contracts & Tenders, Fixed-Bottom, Ports & Logistics, Supply Chain

    RWE has selected Thyborøn Port as the offshore construction base for its 1.1 GW Thor offshore wind farm in Denmark. Thyborøn will be the home port for the project’s service vessels and the control centre for managing marine logistics and traffic throughout the offshore construction phase. In addition, secondary steel structures will be handled from […]

  • 31 May 2021
    Authorities, Wind Farm Update

    The Danish Energy Agency has concluded that the Plan for the Thor offshore wind project can be realized in the dedicated site west of Thorsminde in the Danish North Sea without significant impacts to the environment. At the same time, the Danish Energy Agency has narrowed down the site for the wind farm from 440 […]

  • 31 March 2020
    Contracts & Tenders, Wind Farm Update

    Danish Energy Agency (Energistyrelsen) plans to launch the tendering process for the Thor offshore wind farm in the third quarter of 2020 with the issuance of the contract notice and the tender documents. The deadline for final bids and the appointment of the concession winner is scheduled for the fourth quarter of 2021, the agency […]

  • 1 February 2021
    Authorities, Wind Farm Update

    The Danish Energy Agency (DEA) has launched an eight-week public consultation on the plan for the Thor offshore wind farm and the related Strategic Environmental Assessment (SEA) of the plan for the wind farm. The public consultation runs from 1 February to 29 March, during which period around 5,000 local landowners, relevant organisations and local […]

  • 2 March 2021
    Authorities, Business & Finance, Wind Farm Update

    The European Commission has approved, under EU State aid rules, Danish support for the Thor offshore wind farm project. Denmark notified the Commission of an aid measure, with a total maximum budget of DKK 6,5 billion (approximately EUR 870 million), to support the design, construction, and operation of the Thor offshore wind farm in the […]

  • 25 September 2020
    Contracts & Tenders, Wind Farm Update

    Danish Energy Agency (Energistyrelsen) has invited offshore wind developers to pre-qualify for the tender to build and operate the Thor offshore wind farm. The pre-qualification period is open until noon on 1 December, with the invitation to selected candidates to bid at the tender expected to be issued on 14 January 2021. The shortlisted developers […]