309 results found for 'Moray West'

309 results found for 'Moray West'
Order results by

A list of search results

  • 10 February 2026
    Fixed-Bottom, Project Updates, Wind Farm Update

    Fugro is scheduled to soon start conducting geophysical surveys at a site in the Outer Moray Firth, Scotland, where Ocean Winds plans to build its 2 GW Caledonia offshore wind farm. The work, to be carried out within the wind turbine array site, will be conducted by the vessels Fugro Pioneer and Kommandor Iona. Fugro […]

  • 6 March 2026
    Contracts & Tenders, Fixed-Bottom, Supply Chain

    Quoceant has been awarded a contract by Ocean Winds to provide engineering support to the 390 MW BC-Wind offshore wind farm in Poland. Quoceant’s scope of work covers review of documentation, development of calculations and tools to support the Ocean Winds engineering team decisions, as well as the creation of detailed structural models to support […]

  • 9 March 2026
    Business & Finance, Grid Connection

    Lamprell, a UK manufacturer of offshore wind foundations with facilities in the Middle East, and RTE International, a subsidiary of RTE France specialising in electricity transmission engineering, have signed a strategic Memorandum of Understanding (MoU) under which the two companies plan to team up on offshore wind transmission projects. Lamprell said on 9 March that […]

  • 9 September 2025
    Foundations, Manufacturing, Project Updates, Supply Chain, Wind Farm Update

    Dajin Heavy Industry has sent away the first batch of six monopiles that will be installed at the 1.1 GW Inch Cape offshore wind farm in Scotland. The first six monopiles have set sail from Dajin Heavy Industry’s Penglai facility, according to the latest social media post by the Chinese company. Dajin cut the first […]

  • 26 November 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Operations & Maintenance, Supply Chain

    Føn Energy Services has secured a five-year contract to provide inspection, repair and maintenance services across six Dutch offshore wind farms after winning a combined tender issued by their owners, the company revealed on 26 November at the Offshore Energy Exhibition & Conference (OEEC) in Amsterdam. The award covers Borssele 3&4, owned by the Blauwwind […]

  • 9 December 2025
    Equipment, Foundations, Innovation, R&D, Supply Chain, Technology

    Prometeo, the Offshore Rover by AXIST: A Breakthrough That Reinvents Mono-Pile Flange Measurement In the world of offshore wind, precision is non-negotiable. Even the smallest deviation can lead to deformation, reduced performance, and costly corrective interventions. Measuring the flange of a mono-pile immediately after piling is one of the most critical moments in the entire […]

  • 5 February 2026
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Wind Farm Update

    Google has entered into a 15-year Power Purchase Agreement (PPA) with EnBW for electricity produced by 100 MW of capacity at the 960 MW He Dreiht offshore wind farm in Germany. The He Dreiht offshore wind farm is currently under construction about 85 kilometres northwest of the German island of Borkum and is set to […]

  • 29 July 2025
    Business & Finance, Contracts & Tenders, Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    Ocean Winds has entered into an agreement with Siemens Gamesa for the supply of 26 SG 14-236 wind turbines, which are capable of being boosted to 15 MW, for its BC-Wind offshore wind project in Poland. The companies have also signed a long-term service and maintenance agreement for the 390 MW project. The agreement, which […]

  • 1 August 2025
    Business & Finance, Infrastructure, Ports & Logistics

    UK energy sector construction, maintenance & enhancement solutions player Global Energy Group (GEG) has concluded an agreement with Japanese company Mitsui & Co. for the sale of its group companies, including the Port of Nigg, a multi-sector energy port and green freeport. In addition to the Port of Nigg, GEG reached an agreement with Mitsui […]

  • 24 April 2025
    Fixed-Bottom, Project Updates, Wind Farm Update

    The UK Secretary of State for Scotland, Ian Murray, switched on full power at the 882 MW Moray West offshore wind farm, built by Ocean Winds some 20 kilometres off the coast of Buckie. Moray West comprises 60 Siemens Gamesa SG 14-222 DD wind turbines, each of which can generate up to 14.7 MW with […]

  • 25 April 2025
    Fixed-Bottom, Project Updates, Supply Chain, Vessels, Wind Farm Update, Wind Turbines

    The first of 64 Vestas V236-15.0 MW wind turbines has been installed at EnBW’s He Dreiht project site offshore Germany. Completed on 24 April, the project milestone also marks the first time Vestas’s flagship wind turbine has been installed at an offshore wind farm. “With the installation of the first V236-15.0 MW, we have reached […]

  • 20 September 2019
    Business & Finance

    The Moray West offshore wind farm remains viable despite not having been selected in the UK’s third Contracts for Difference (CfD) allocation round, the project developer confirmed. The project team stated that it recognizes an opportunity for Moray West to be awarded a CfD in the next auction round in 2021 and would be on course to […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Supply Chain, Wind Farm Update, Wind Turbines

    The first Siemens Gamesa 108-metre-long wind turbine blades have left its manufacturing factory in Hull for the Moray West offshore wind project in Scotland. Nine of the 180 blades destined for the 882 MW offshore wind farm were loaded onto the Rotra Mare transporter ship at the Siemens Gamesa blade factory in Hull, and are […]

  • 12 December 2022
    Contracts & Tenders, Vessels, Wind Farm Update

    DEME has won the contract to install foundations at the 882 MW Moray West wind farm offshore Scotland. DEME Offshore’s scope on Moray West includes the installation of monopile foundations and transition pieces. The contract is valued between EUR 50 million and EUR 150 million. This marks the return of DEME to the Moray Firth, […]

  • 20 February 2024
    Fixed-Bottom, Project Updates, Vessels, Wind Farm Update

    DEME’s vessel Orion has installed its first XXL monopile foundation at the 882 MW Moray West offshore wind farm in Scotland. The company’s jack-up vessel Apollo is also joining the offshore work, taking care of installing the transition pieces at the construction site. Orion is performing monopile installation in addition to Bokalift 2, which kicked […]

  • 19 December 2023
    Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    Boskalis’ DP installation vessel Bokalift 1 has installed the first offshore substation platform (OSP) at the Moray West offshore wind farm site in Scotland. The heavy lift operations in the Port of Nigg and on-site were completed safely and successfully, according to the developer Ocean Winds. As offshore commissioning starts, the previously laid export cable […]

  • 20 July 2023
    Wind Farm Update

    Dajin Heavy Industry Corporation has delivered 24 out of the total 48 monopiles that the company is manufacturing for the 882 MW Moray West offshore wind farm in Scotland. On 14 July, the 3rd shipment of XXL monopiles, which weigh about 2,000 tonnes and have a diameter of ten metres, set sail from the Dajin […]

  • 25 October 2023
    Equipment, Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    The first batch of transition pieces (TPs) for the Moray West offshore wind farm have sailed out of Lamprell’s Hamriyah yard in UAE and are on their way to a marshalling harbour in the UK. “I want to congratulate the project team and thank our client for their trust in Lamprell as we underwent both […]

  • 18 November 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    The 60th and final turbine has been installed at the 882 MW Moray West offshore wind farm in the Moray Firth, located in northern Scotland. The Moray West offshore wind farm is nearing the end of the construction phase and will become fully operational during 2025, in line with the originally projected commercial operations date, […]

  • 11 March 2024
    Cables, Fixed-Bottom, Grid Connection, Offshore Platforms, Project Updates, Wind Farm Update

    France-headquartered Nexans has completed the offshore export cable pull-ins for both offshore substation platforms at the 882 MW Moray West wind farm, located in the Moray Firth in the northeast of Scotland. The cable-laying vessel Nexans Aurora took advantage of a recent period of favorable weather to carry out the task, according to Ocean Winds’ […]

  • 5 October 2023
    Fixed-Bottom, Foundations, Project Updates, Supply Chain, Wind Farm Update

    Boskalis’ heavy lift crane vessel, Bokalift 2, has installed the first monopile at the 882 MW Moray West offshore wind farm in Scotland. The Scottish offshore wind farm will feature 60 Siemens Gamesa 14.7 MW wind turbines and two offshore substations, all installed on monopile foundations. Dajin Heavy Industry will supply 48 monopiles while Navantia Seanergies and […]

  • 23 November 2023
    Foundations, Project Updates, Supply Chain, Wind Farm Update

    China’s Dajin Heavy Industry has delivered the final batch of eight XXL monopiles for the 882 MW Moray West offshore wind farm in Scotland. In June 2022, Dajin Heavy Industry was contracted by the wind farm’s developer, Ocean Winds, to supply 48 XXL monopiles for the project. The units weigh about 2,000 tonnes and have […]

  • 15 December 2021
    Contracts & Tenders, Grid Connection, Wind Farm Update

    Siemens Energy has won the contract to provide an onshore substation for the 860 MW Moray West offshore wind project in Scotland. Subject to the award of a Contract for Difference in 2022 and Financial Close, the onshore substation for the wind farm will feature Siemens High Voltage Alternating Current (HVAC) equipment. Project design and […]

  • 21 October 2021
    Contracts & Tenders, Wind Farm Update

    Moray West, an offshore wind farm in the outer Moray Firth, Scotland, has selected Siemens Gamesa as the preferred bidder for the supply of offshore wind turbines. Subject to the award of a Contract for Difference in 2022 and Financial Close, the wind farm would feature Siemens Gamesa’s latest offshore Direct Drive wind turbines, including […]

  • 31 July 2024
    Fixed-Bottom, Project Updates, Wind Farm Update

    UPDATE: On 16 August, the Moray West project developer, Ocean Winds, said via social media that more than half of the wind turbines were now installed. The Moray West offshore wind farm in Scotland is nearing the halfway point of its wind turbine installation, according to the latest Notice to Mariners issued by the Moray […]

  • 10 October 2024
    Cables, Fixed-Bottom, Grid Connection, Project Updates, Wind Farm Update

    Seaway7 has finished the full engineering, procurement, installation, and commissioning (EPIC) work for the cables at the 882 MW Moray West offshore wind farm in Scotland. Seaway7 has installed 118 kilometres of 66 kV inter-array cables, linking the wind farm’s 60 turbines to two offshore substations, along with an additional 15 kilometres of 66 kV […]