Horns Rev 3 Transition Pieces In Position

  • Wind Farm Update

GeoSea has installed all 49 transition pieces on Vattenfall’s 406.7MW Horns Rev 3 wind farm in the Danish North Sea.

Jan De Nul’s installation vessel Vole au vent installed the first transition piece at the site north-west of Blåvands Huk mid-July. GeoSea completed the installation of the monopile foundations in early January.

Fred. Olsen Windcarrier’s jack-up Brave Tern is transporting the MHI Vestas 8.3MW wind turbines from the Port of Esbjerg and installing them at the site located 25-40 kilometres off the Danish west coast. A2SEA is responsible for the planning and execution of the wind turbine installation.

The wind farm is scheduled for full commissioning in 2020.