First Beatrice OTM Heads for Installation

The first Siemens Offshore Transformer Module (OTM) has left Rosyth and is on its way to the Beatrice offshore wind farm in the Outer Moray Firth, Scotland.

Source: Beatrice Offshore Windfarm Ltd.

Earlier this week, Seaway Heavy Lifting installed the first of two BiFab’s jacket foundations which will support the wind farm’s OTMs.

In May 2016, Siemens signed a contract to supply, install and commission 84 7MW wind turbines, and provide grid access solution for the wind farm, which will feed the power to the grid through Nexans’ export cable.

For the grid access solution, Siemens is delivering two OTMs, which are one third smaller in size and weight compared to a conventional alternating-current (AC) platform.

The first wind turbines at the 588MW Beatrice offshore wind farm are scheduled to be installed in the summer, with the wind farm expected to be commissioned by the end of 2019.

The wind farm is being developed by Beatrice Offshore Windfarm Ltd., a joint venture partnership between SSE, Copenhagen Infrastructure Partners and Red Rock Power Ltd.

Related news

List of related news articles

Posted: 5 months ago

Ouyang Launches Wind Turbine Installation Vessel (Photos)

China’s Ouyang Offshore has launched its wind turbine installation vessel, OuYang 1, at Dayang...

Categories:
  • Vessels
Posted: 5 months ago
Posted: 5 months ago

Swedish Offshore Wind Farm Is No More

Offshore wind O&M specialist Ziton has completed the decommissioning of the Utgrunden offshore ...

Categories:
  • Business & Finance
Posted: 5 months ago
Posted: 5 months ago

BorWin Gamma Preps for Installation

The BorWin gamma topside is currently being prepared for installation onto its jacket foundation in ...

Categories:
  • Grid Connection
Posted: 5 months ago
Posted: 5 months ago

SSC Wind and Robur Combine Forces

SSC Wind and Robur have signed an agreement to join forces with an aim to expand their wind energy s...

Categories:
  • Business & Finance
Posted: 5 months ago