Search results for: Kriegers Flak

195 results

A list of search results

5 June 2019 Grid Connection

NKT has commissioned the 170kV high-voltage cable system at the Kriegers Flak Combined Grid Solution (CGS) connecting Denmark and Germany. According to NKT, the work on the CGS cable connecting the Kriegers Flak and Baltic 2 offshore wind farms was completed on schedule and on budget. The high-voltage cable system connects the Danish region of […]

28 May 2019 Contracts & Tenders, Grid Connection

Vattenfall has awarded Kraken Subsea Solutions with a contract for employer's representation for the inter-array cable installation at the Kriegers Flak offshore wind project. The French engineering and consultancy company will provide supervision services to Vattenfall during the offshore installation operations at the 605MW wind farm, which will take place from July 2019 to November 2020. […]

23 May 2019 Wind Farm Update

Rostock-based EEW Special Pipe Constructions GmbH has started manufacturing the monopiles for Vattenfall's 605MW Kriegers Flak offshore wind farm. The first pipe for the Danish offshore wind farm was made in the Rostock production site this May. By September 2019, all 72 monopiles will have been produced and coated, according to the company. In spring […]

29 April 2019 Business & Finance

The Danish Hvide Sande Shipyard, Steel and Service has received an order to supply cranes for Vattenfall's Kriegers Flak offshore wind farm. Hvide Sande will provide 72 cranes for the 605MW project in the order placed by Bladt Industries, which in charge of delivering the wind farm's transition pieces. According to Carl Erik Kristensen, Director of Hvide Sande, […]

22 March 2019 Contracts & Tenders, Grid Connection

Global Offshore, part of Global Marine Group, has won an inter-array cable installation contract by Vattenfall for the Kriegers Flak offshore wind farm in Denmark. Global Offshore will carry out the inter-array cable installation, burial, testing and termination at the 605MW project. The company said its multi-purpose vessel Global Symphony will complete the installation supported by the […]

19 March 2019 Contracts & Tenders, Grid Connection, Wind Farm Update

JDR Cables has secured an inter-array cable contract by Vattenfall for the Kriegers Flak offshore wind farm in Denmark. Under the deal, JDR will manufacture more than 170km of aluminium core inter-array cables and a range of termination accessories. According to the UK-based company, the cable will be assembled at JDR’s Hartlepool facility, while the project completion […]

21 December 2018 Contracts & Tenders, Wind Farm Update

Vattenfall has contracted Bladt Industries to deliver 72 transition pieces for the Danish Kriegers Flak offshore wind farm.

21 December 2018 Contracts & Tenders, Vessels

Vattenfall has contracted Van Oord for the transport and installation of the foundations for the Kriegers Flak offshore wind farm.

21 December 2018 Contracts & Tenders

EEW Special Pipe Constructions has secured a contract with Vattenfall to manufacture the monopile foundations for the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea.

20 December 2018 Business & Finance, Wind Farm Update

Vattenfall has made the final investment decision for the Kriegers Flak offshore wind farm in Danish Baltic Sea waters, which is planned to be in full operation before the end of 2021.

2 November 2018 Contracts & Tenders, Grid Connection, Vessels

Jack Up Barge (JUB) has completed a support and supply contract for the hook-up and commissioning of two offshore platforms at the Kriegers Flak offshore wind farm in the Danish Baltic Sea.

8 October 2018 Grid Connection

The commissioning of the Kriegers Flak Combined Grid Solution (CGS) between Germany and Denmark has been delayed until May 2019.

13 July 2018 Business & Finance, Contracts & Tenders, Wind Farm Update

Global healthcare company Novo Nordisk and bio innovator Novozymes have signed a long-term Power Purchase Agreement (PPA) with Vattenfall to source their electricity from the Kriegers Flak offshore wind farm, currently under construction off Denmark.

6 July 2018 Grid Connection

Both offshore cables of the Kriegers Flak Combined Grid Solution (CGS) are now in place, connecting the Danish and German transmission grids in combination with the infrastructure of offshore wind farm grid connection in the Baltic Sea.

2 July 2018 Grid Connection, Vessels, Wind Farm Update

Jack-Up Barge's vessel JB-115 has been deployed at the Kriegers Flak site off Denmark to accommodate the crew working on the hook up and commissioning of the substation that will be the heart of the Kriegers Flak Combined Grid Solution (CGS).

1 June 2018 Ports & Logistics

The Port of Rønne in Denmark has been selected as the departure point for the 72 Siemens Gamesa 8MW turbines destined for the Kriegers Flak offshore wind farm and will undergo upgrades to service the project.

4 May 2018 Grid Connection, Vessels, Wind Farm Update

Heavy lift vessel Rambiz has installed the Kriegers Flak substation topsides in the Danish Baltic Sea, Energinet reports.

23 April 2018 Grid Connection, Ports & Logistics, Wind Farm Update

Hollandia Offshore and Croonwolter&dros have loaded two out of the three substation topsides built for the Kriegers Flak project onto a barge.

4 April 2018 Grid Connection, Wind Farm Update

Energinet has resumed onshore cable installation works for the Kriegers Flak offshore wind farm after the winter break, and is now ready to start with the final stage of cable excavation on land.

8 March 2018 Technology, Wind Farm Update

Greek Assodivers Underwater Contractors have taken delivery of two MERMAC winches from MacArtney to be used on the Kriegers Flak offshore wind project in the Danish Baltic Sea.

23 February 2018 Grid Connection, Wind Farm Update

The foundation for the second Kriegers Flak offshore substation was installed on 22 February, a few days after Jan de Nul installed the first one.

19 February 2018 Grid Connection, Wind Farm Update

Jan De Nul has installed the first of the two gravity-based foundations that will support the offshore substations on the 605MW Kriegers Flak offshore wind farm in the Danish Baltic Sea.

17 January 2018 Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

A barge loaded with two gravity-based foundations (GBFs) for the high voltage station of the 605MW Kriegers Flak offshore wind farm has arrived in Koge, Denmark, Blue Water Shipping (BWS), the port agents for the project, told Offshore WIND.

9 January 2018 Ports & Logistics, Vessels, Wind Farm Update

A barge carrying two gravity based foundations (GBFs) for the high voltage station of the Danish 605MW Kriegers Flak offshore wind farm has left the port of Ostend, Belgium.

14 December 2017 Business & Finance, Contracts & Tenders, Operations & Maintenance, Ports & Logistics, Wind Farm Update

Vattenfall has chosen Klintholm Harbour in Denmark as its base for the servicing and maintenance of the 605MW Kriegers Flak offshore wind farm.

11 December 2017 Wind Farm Update

Jan De Nul and Iemants have completed the two gravity-based foundations for Kriegers Flak substations. The steel structures, designed and built by Iemants (Smulders), have been placed on top of their corresponding concrete structures and the foundations are now being prepared to be transported from the port of Ostend in Belgium to Denmark by the end of December.