663 results found for 'Hornsea Project One'

663 results found for 'Hornsea Project One'
Order results by

A list of search results

  • 26 April 2018
    Grid Connection, Vessels, Wind Farm Update

    The first Hornsea Project One substation topside, Z12, has been installed at the site 120km off the Yorkshire coast.

  • 26 April 2019
    Wind Farm Update

    DEME Offshore installed the final of the 174 monopile foundations on the 1.2GW Hornsea Project One offshore wind farm on Thursday, 25 April. The first monopile was installed at the site some 120 kilometres off the Yorkshire coast in the UK in January 2018. According to DEME, four of the company’s jack-ups has since worked at […]

  • 1 October 2018
    Ports & Logistics, Wind Farm Update

    Rostock-based EEW SPC has loaded out and delivered 116 out of 174 monopiles for Ørsted’s Hornsea Project One offshore wind farm.

  • 13 April 2018
    Contracts & Tenders, Wind Farm Update

    Bladt Industries has contracted a partnership of BIC Electric and Resolux to take part in the outfitting of 124 transition pieces built for Ørsted’s 1.2GW Hornsea Project One offshore wind farm.

  • 18 April 2018
    Grid Connection, Vessels, Wind Farm Update

    Tideway BV, part of DEME Group, has laid the first offshore export cable section at Hornsea Project One, Ørsted’s 1.2GW wind farm offshore Yorkshire, UK.

  • 27 December 2017
    Wind Farm Update

    Ørsted has shared a photo of four substation jacket foundations currently under construction at Dragados Offshore’s yard in Spain for the 1.2GW Hornsea Project One offshore wind farm.

  • 10 June 2016
    Business & Finance, Grid Connection, Wind Farm Update

    DONG Energy has awarded Dragados Offshore, a Spanish engineering, procurement, and construction (EPC) contractor and a part of the ACS Group, with a contract to deliver four substation jackets for the 1.2GW Hornsea Project One offshore wind farm in the UK. The scope of work awarded to Dragados Offshore is the procurement and fabrication of the jackets and piles […]

  • 21 February 2018
    Grid Connection, Ports & Logistics, Vessels, Wind Farm Update

    Gulf Marine Services’ Self Elevating Support Vessel (SESV) GMS Evolution has joined her sister vessel GMS Endeavour in the Port of Blyth to undergo mobilisation for operations at the 1.2GW Hornsea Project One offshore wind farm.

  • 20 August 2018
    Ports & Logistics, Wind Farm Update

    Teesside-based Wilton Engineering has sent off the first four transition pieces built for Ørsted’s 1.2GW Hornsea Project One offshore wind farm. 

  • 28 June 2018
    Vessels

    DEME Group’s cable laying and multipurpose vessel Living Stone has completed sea trials and will soon head to its first cable laying assignment at Hornsea Project One in the UK.

  • 7 February 2017
    Business & Finance, Wind Farm Update

    DONG Energy has hired Germany’s Steelwind Nordenham and Teesside-based Wilton Engineering Services Limited to supply the 1.2GW Hornsea Project One offshore wind farm with 20 transition pieces. The multi-million pound contract was signed in Port Clarence in Middlesbrough on Monday, 6 February. Wilton Engineering Services Limited will provide a significant part of the work scope including outfitting, […]

  • 3 January 2020
    Grid Connection

    Hornsea One Ltd has agreed to pay out GBP 4.5 million to Ofgem for not remaining connected after the lightning strike in August 2019. To remind, the Hornsea Project One offshore wind farm suffered a reduction in the energy supply on 9 August due to a lightning strike. The 1.2GW wind farm immediately de-loaded from […]

  • 23 April 2018
    Grid Connection, Wind Farm Update

    The first of the four jacket foundations has been installed at Ørsted’s Hornsea Project One wind farm site 120 kilometres off the coast of Yorkshire.

  • 20 September 2017
    Operations & Maintenance, Wind Farm Update

    DONG Energy has awarded CHC Group with a six-year contract for aviation services for the Hornsea Project One offshore wind farm in the UK. Working with Uni-Fly as a sub-contractor, CHC will support the construction phase and the first five years of operations and maintenance of the wind farm.

  • 8 November 2018
    Contracts & Tenders, Wind Farm Update

    Manor Renewable Energy (MRE) has signed a contract with Ørsted for the Hornsea Project One offshore wind farm, under which MRE will provide the full temporary power package of generators, personnel and vessels in case of need during the turbine installation and commissioning.

  • 24 January 2017
    Grid Connection, Wind Farm Update

    Spain’s Dragados Offshore has awarded compatriot IKM Testing Spain with a contract to manufacture sheet metal panels which will be used for the construction of offshore substation jackets for the 1.2GW Hornsea Project ONE offshore wind farm. IKM Testing Spain, part of the IKM Group, plans to fabricate the steel plates at its newly opened steel works […]

  • 19 March 2018
    Ports & Logistics, Vessels, Wind Farm Update

    ALE’s latest marine investment, the SARAH S barge, has been deployed on its inaugural job to transport transition pieces (TPs) for the 1.2GW Hornsea Project One offshore wind farm.

  • 29 March 2018
    Ports & Logistics, Vessels

    Port of Blyth has shared a photo of Gulf Marine Services testing the jack-up operation of the Self Elevating Support Vessel (SESV) GMS Endeavour at the port’s South Harbour.

  • 7 February 2016

    Sea Worker Capsizes off Denmark Due to harsh weather, the offshore installation vessel Sea Worker has capsized during the night between Tuesday and Wednesday. VIDEO: How Big is Hornsea Project One? After reaching the Final Investment Decision for the 1.2 GW Hornsea Project One offshore wind farm earlier today, Dong Energy has published this short […]

  • 20 February 2017
    Business & Finance, Grid Connection, Technology, Wind Farm Update

    Lancaster-based First Subsea, has entered the offshore wind market after signing a multi-million pound contract with DONG Energy to provide cable protection system units for the 1.2GW Hornsea Project One offshore wind farm.

  • 11 September 2017
    Business & Finance, Wind Farm Update

    DONG Energy has taken a Final Investment Decision for its Hornsea Project Two, following the UK government’s allocation of the Contracts for Difference (CfD) and the offshore wind giant winning a CfD for what will become the world’s biggest wind farm.

  • 28 March 2018
    Authorities, Environment, Grid Connection, Wind Farm Update

    UK governmental agencies, conservation organisations and companies have responded positively to Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.

  • 12 April 2018
    Operations & Maintenance, Wind Farm Update

    Spain-based Dragados Offshore has sent off all four jacket foundations for the offshore substations at Ørsted’s Hornsea Project One offshore wind farm.

  • 19 September 2018
    Business & Finance, Wind Farm Update

    EKF, Denmark’s Export Credit Agency, has provided a GBP 800 million guarantee for the Hornsea Project One offshore wind farm, making this the largest financing in EKF’s history and the largest wind financing that any public export credit agency has ever provided.

  • 15 February 2018
    Authorities, Business & Finance, Grid Connection, Wind Farm Update

    Ørsted has sent an application to the UK’s Planning Inspectorate to reduce the maximum number of offshore HVAC collector substations permitted under the Hornsea Project Two Development Consent Order (DCO).

  • 5 October 2018
    Wind Farm Update

    Waves Group is providing Marine Warranty Surveyor services during the construction of the world’s largest offshore wind farm – the 1.2GW Hornsea Project One.